Kerala

Palakkad

CC/81/2012

Velayudhan Nair - Complainant(s)

Versus

Unnikrishnan - Opp.Party(s)

20 Apr 2013

ORDER

 
Complaint Case No. CC/81/2012
 
1. Velayudhan Nair
S/o.Krishnan Nair, Karuvalli House, Kavalapara, Shornur, Palakkad
 
BEFORE: 
 HONARABLE MRS. Seena.H PRESIDENT
 HONARABLE MRS. Bhanumathi.A.K Member
 HON'BLE MRS. Preetha.G.Nair Member
 
PRESENT:
 
ORDER

CONSUMER DISPUTES REDRESSAL FORUM

PALAKKAD, KERALA

Dated this the 20th day of April, 2013.

 

Present: Smt. Seena. H, President

  : Smt. Preetha. G. Nair, Member

  : Smt. Bhanumathi. A.K, Member               Date of filing: 25/04/2012

 

CC/81/2012

 

Velayudhan Nair,

S/o. Krishnan Nair, Karuvalli House,                                 - Complainant

Kavalapara, Shornur,

Palakkad – 679 523

(By Adv. Manoj Ambat)

V/s

Unnikrishnan,                                                                  - Opposite party

Kuruppamthodiyil house, Panjal,

Cheruthuruthi, Thrissur – 679 531

(By Adv. M. Abdul Gafoor)

 

O R D E R

BY SMT. BHANUMATHI. A.K, MEMBER

Complaint in brief :-

The complainant had entered in to an agreement with the opposite party dated 16/11/2011 for constructing a concrete building adjacent to his house. The said agreement envisaged the opposite party to construct basement, bhithi, roof and windows of wood, electric wiring and plumbing, to have laid vetrified tiles in the floor and to install fittings including Europeon Closet in the bathroom and also undertake painting. The work ought to be completed within  5 months from the agreement and the complainant had paid an amount of Rs. 1 lakh as advance. But the opposite party had abandoned the work. Despite repeated requests the opposite party has not completed the work. The work done by the opposite party is only for an amount of                                      Rs. 30,000/-. The act of opposite party caused mental agony and financial loss to the complainant. So the complainant praying an order directing the opposite party to pay an amount of Rs. 2,50,000/- to the complainant.

 

Opposite party entered appearance and filed version with the following.

The alleged agreement was executed on 16/09/2011 but in the complaint it is stated as 16/11/2011. The opposite party has completed the construction of basement of the complainants building and the basement has been filled with mud, watered and made it paste to make it fit for constructing. The opposite party has put up the concrete belt alround. 100 Concrete solid blocks also have been bought to the site. For these work opposite party has spent more than Rs. 1,00,000/- inclusive of labour charges. For construction of the super structure municipal permit is necessary. The complainant has not obtained necessary permit for construction of his building. To get river sand, necessary pass has to be obtained from the competant authority. The opposite party is put to considerable difficulty and hardship due to the fact that no permit is obtained by the complainant. Work costing more than Rs. 1lakh have already been done. There is no deficiency of service on the part of opposite party and complaint is liable to be dismissed.

Both parties filed their affidavits. Ext. A1 and C1 series marked on the side of the complainant. Complainant and opposite party cross examined as PW1 and DW1 respectively.

Issues to be considered are

1. Whether there is any deficiency of service on the part of opposite party?

  1. If so what is the relief and cost?

Issues I and II

 

          The complainant is regarding deficiency in service on the part of opposite party with regard to the housing construction.  The complainant had entered into  an agreement with the opposite party dtd. 16/09/2011 for constructing a concrete building adjacent to his house.  The said agreement is marked as Ext. A1.  In the complaint the agreement date is stated as 16/11/2011.  This agreement envisaged the opposite party to construct the Bhithi and roof, plaster the same, to make door and windows of wood, electric wiring and plumbing, to have laid vetrified tiles in the floor and to install fittings including European closet in the bathroom and also undertake painting.  The work should be completed within 5 months of the agreement

 

and the complainant had paid an amount of  Rs.i1 lakh as advance.  But the opposite party has not completed the work as promised.  According to complainant the opposite party has done the work only costing an amount of Rs. 30,000/-.  Opposite party states that they have constructed the basement of the complainants building and made it fit for constructing, put up the concrete belt alround 1000 Concrete solid block also have been brought to the site.  For this works the opposite party has spent more than   Rs. 1,00,000/-.  For construction of the super structure muncipal permit is necessary.  The complainant has not obtained  the  same.  Also the complainant has not taken the pass for getting river sand.  An expert commissioner was appointed and filed detailed report marked as Ext. C1 series.

 

         

 

The agreement and advance payment is admitted by the opposite party.  According to C1 series, the work is not completed as per the agreement dated. 16/09/2011 between the parties.  The work of wall and roof is completed properly.  But it is not plastered both sides.  The doors and windows has not fixed.  Only the frames made of concreted were there.  There was no doors and windows which was kept to install there.  The work for electrification and plumbing  works was not started.  Vetrified tiles in floors and European closet were not fixed, painting was also not done.   As per commissioner report the estimate cost for the work done is                 Rs. 1,64,178.10.  To complete the work of the building an amount of Rs. 2,02,718.00 more is required. 

According to opposite party he was abonden the work as the complainant had not got the building permit and sand permit.  At the time of cross examination the complainant deposed that ]md-a-WÂ sIm­mWv work  sNbvXXv. Complete work \v agreement3 lakhs Bbn-cp¶p th­n-bn-cp-¶-Xv

In the agreement the amount is written as Rs.2,75,000/- is decided for completing the work.  In Ext. A1 it is not stated that getting building permit is the responsibility of the complainant.  Even after the execution of the agreemt opposite party did not inform this fact to the complainant .  If all the work was done by M sand the sand pass is not necessary. 

 

          As per agreeement the complete work should be completed within 5 months from the date of agreement.  As per Ext.C1 series the work is not completed.   Total amount for complete work is stipulated as Rs. 2,75,000/- .  The complainant has paid 1 lakh as advance.  Balance amount should be paid in 3 instalments as per the status of the work done.  These facts are evident from  Ext. A1 document.  But at the time of cross examination the complainant deposed that “ complete work \v agreeement

 

3 lakhs Bbn-cp¶p th­n-bn-cp-¶-Xv.

 

 

 

As per the commission report Ext. C1 series dtd. 13/09/2012 the opposite party has done the work which costs Rs. 1,64,178.10.  Complainant has not a  case that he has paid this  much amount to the opposite party.  In cross examination complainant deposed that he has paid Rs.16,000/-  more to the opposite party over and above                  Rs. 1 lakh. But no document is produced.  At the time of cross examination the complainant  admitted  that  the  old shed was removed at the cost of opposite party. 

         

          From the above discussions we are of the view that  opposite party has done the work costs Rs. 1,64,178.10 for the complainant for which the complainant has paid only Rs.1 lakh to the opposite party.  So that we are not in a position to attribute deficiency of service on the part of opposite party.

 

          In the result complaint dismissed.  No order as to cost.

Pronounced in the open court on this the 20th day of April, 2013.

 

     Smt. Seena. H

        President

 

Smt. Preetha.G.Nair

Member

 

Smt. Bhanumathi.A.K

Member

 

A P P E N D I X

Exhibits marked on the side of complainant

Ext. A1– Agreement between the complainant and opposite party dtd. 16/09/2011.

 

Exhibits marked on the side of opposite party

Nil

Witness examined on the side of complainant

PW1- K. Velayudhan Nair

Witness examined on the side of opposite party

DW1- Unnikrishnan.K

Commission Report

C1 series – Commissioner report 2 nos.

Cost allowed

Nil

 

 

Forwarded by / By order

 

 

Senior Superintendent

 

Fair copy on: 17/01/2013

Despatched on:

 

 

 

Order shall be complied within one month from the date of receipt of order, failing which the complainant is entitled for 9% interest per annum for the whole amount from the date of order till realization.

Pronounced in the open court on this the 26th day of March, 2013

      Sd/-

Smt. Seena. H

   President

 

                                                                                            Sd/-

   Smt. Preetha.G.Nair

                                                                                           Member

      Sd/-

                                                                                  Smt. Bhanumathi.A.K.

    Member

 A P P E N D I X

 

Exhibits marked on the side of complainant

Ext. A1 series – Copy of lawyer notice and receipt  sent by the complainant to the                opposite parties dtd. 27/09/2012.

Ext. A2 – Acknowledgement cards orginal  .

Ext. A3 – Reply notice sent by the 1st opposite party to the complainant dtd. 10/10/2012.

Ext. A4 –  Pass book of the complainant issued by State Bank of India.

Ext. A5 – Bills issued by the 4th respondent to the complainant dtd. 09/02/2012.

Ext. A6 - Bills issued by the 4th respondent to the complainant dtd. 30/06/2012.

Ext. A7 - Bills issued by the 4th respondent to the complainant dtd. 12/07/2012.

Ext. A8 - Bills issued by the 4th respondent to the complainant dtd. 15/05/2012.

Ext. A9 - Bills issued by the 4th respondent to the complainant dtd. 26/06/2012.

Ext. A10  series – Photo with CD of the vehicle of the complainant.

 

Exhibits marked on the side of opposite party

Ext. B1 series – Service History of the complainants vehicle.

Witness examined on the side of complainant

PW1 – Subhash.K.V

Witness examined on the side of opposite party

Nil

Cost allowed

Rs. 1000/- (One Thousand only )allowed as cost of the proceedings.

 
 
[HONARABLE MRS. Seena.H]
PRESIDENT
 
[HONARABLE MRS. Bhanumathi.A.K]
Member
 
[HON'BLE MRS. Preetha.G.Nair]
Member

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.