Chandigarh

StateCommission

CC/177/2016

Sanjeev Dhir - Complainant(s)

Versus

Unitech Ltd. - Opp.Party(s)

Sh. N.S. Jagdeva, Adv.

01 Aug 2016

ORDER

STATE CONSUMER DISPUTES REDRESSAL COMMISSION,

U.T., CHANDIGARH

 

Complaint case No.

:

177 of 2016

Date of Institution

:

03.05.2016

Date of Decision

:

01.08.2016

 

Sanjeev Dhir son of Krishan Gopal aged 48 years, resident of House No.52, Sector 20-D, Subhash Nagar, Mandi Gobindgarh, District Fatehgarh Sahib, Punjab.

…… Complainant

V e r s u s

Unitech Limited, through its Chairman/Managing Director, SCO No.189-191, Sector 17-C, Chandigarh.  

              .... Opposite party

Complaint under Section 17 of the Consumer Protection Act, 1986

 

BEFORE:         JUSTICE JASBIR SINGH (RETD.), PRESIDENT.

                        MR. DEV RAJ, MEMBER.

                        MRS. PADMA PANDEY, MEMBER.

 

Argued by:-     Sh.N.S. Jagdeva  Advocate for the   complainant.

Mrs.Vertika H.Singh, Advocate for the opposite party.

 

PER JUSTICE JASBIR SINGH (RETD.), PRESIDENT

                The facts in brief are that the complainant approached the opposite party, in the year 2011, in order to purchase a house/flat, for his residential purpose, in a project, launched by it, under the name and style of  ‘Uniworld City,  Sector 97, Mohali, Punjab. Flat was booked by him, with the opposite party on making payment of Rs.5,05,141/- towards booking amount. Vide Agreement dated 10.07.2012, the complainant was allotted apartment no.0092 (3BHK), Floor-02, measuring 1796 square feet, Block D, (in short the unit) in the said project, for a total sale consideration of Rs.53,38,370/-, inclusive of External Development Charges (EDC), Preferential Location Charges (PLC) etc. The complainant opted for construction linked payment plan. As per Article 4.a.(i) of the Agreement, the  opposite party was liable to deliver possession of the constructed unit, to the  complainant, within a period of 24 months, from the date of execution of the same (Agreement) i.e. on or before 09.07.2014. It was further stated by the complainant that as per agreed terms and conditions between the parties, in case of delay in handing over possession of the unit, penalty @Rs.5/- per square feet, per month of the saleable area, for the period of delay was payable by the  opposite party, to him. To make payment towards price of the said unit, the complainant availed loan from the Bank, against which, he has been paying Equated Monthly Installment (EMI) @Rs.30,000/- .

  1.         As per record, from time to time, against the total sale consideration of Rs.53,38,370/-, the complainant paid an amount of Rs.48,03,140/-, to the opposite party. However, possession of the unit was not offered to the complainant by the stipulated date. After making payment of substantial amount, the complainant contacted the  opposite party, number of times, to know the stage of development and construction work at the site but no positive response was given. Construction at the spot was stopped by the opposite party. Legal notice dated 04.02.2016 sent by the complainant to the opposite party, seeking refund of the deposited amount alongwith interest also failed to get any result.  It was stated that the  opposite party is not in a position to deliver possession of the unit(s) in the said project, even as on today.

                By stating as above, prayer has been made to issue directions to the  opposite party to refund the amount deposited, alongwith interest, compensation and litigation expenses.

  1.         Upon notice, reply was filed by the  opposite party, wherein numerous preliminary objections were taken stating that since the unit, in dispute, is situated in Mohali; Buyer’s Agreement was executed at New Delhi; and even the demand for payment was raised from Gurgaon Office; payments were also made through bank in an account maintained by the opposite party at New Delhi; this Commission lacks territorial jurisdiction. It was averred that the demand draft(s)/cheque(s) were received by the opposite party from the complainant, at Chandigarh, only as a facilitator. Pecuniary Jurisdiction of this Commission was also disputed. It was stated that time was not the essence of contract, as the period mentioned in the Agreement for delivery of possession was only tentative. It is averred that the complaint is premature. It is asserted that the unit, in question, was purchased for future gain, as such, the complainant being investor, would not fall within definition of a consumer, as defined under Section 2 (1) (d) of the Consumer Protection Act, 1986.
  2.         On merits, it is admitted that the complainant had purchased a residential unit, in question, from the  opposite party. Fact qua price of the unit, as mentioned in the complaint was also not disputed. Payment made by the complainant towards price of the unit, as mentioned in the complaint was admitted. It is stated that the dispute being a contractual one, consumer complaint is not maintainable, and only a Civil Court, could adjudicate the same. It was also not disputed that as per Article 4.a.(i) of the Agreement, the  opposite party was to hand over possession of the fully constructed unit, to the  complainant within a period of 24 months, from the date of execution of the same (Agreement), subject to force majeure conditions. It is clarified that the opposite party could not complete the construction/development work and hand over possession of  the unit to the  complainant, by the stipulated date, as there was global meltdown/recession of the economy worldwide, resulting into cash crunch throughout and also due to some objection raised by the Punjab State Power Corporation Limited (PSPCL), a number of times, as such, electricity could not be made available at the site, by the opposite party, due to which, rest of the construction/development work and providing of the basic amenities was delayed. It is stated that recently vide letter dated 16.05.2016, it was intimated by the PSPCL to get the proposed new route, to be vetted by the GMADA. Vide letter dated 18.05.2016, No Objection Certificate in that regard, was provided to the PSPCL. It is stated that development work at the site, is being carried out, in full swing and the  opposite party is  making sincere efforts to hand over possession of the constructed unit, to the complainant. It is averred that for any delays, stipulated penalty has been provided in the Agreement, which safeguarded rights of the complainant. It was also stated that the  opposite party vide letter dated 03.02.2016, has applied to the Competent Authority, to issue partial completion certificate, in respect of the project, in question. It was averred that if still the complainant is interested in seeking refund of the amount deposited, his case will be governed strictly, in accordance with the terms and conditions of the Agreement. In other words, it is said that forfeiture Article shall be attracted and the complainant will lose considerable amount, in case, refund of the deposited amount is ordered by this Commission. The remaining averments are denied, being wrong. It is prayed that the complaint having no substance, be dismissed.
  3.         In the rejoinder filed, the complainant reiterated all the averments contained in the complaint and repudiated those, contained in the written version of the  opposite party.
  4.         The parties led evidence in support of their case, by way of filing their respective affidavits, alongwith which, number of documents were attached. 
  5.         On completion of the proceedings, arguments of the parties were heard, in detail.
  6.         We would first like to deal with the objection raised by the  opposite party that this Commission has got no territorial Jurisdiction, to entertain and decide the complaint. According to Section 17 of the Act, a consumer complaint could be filed by the complainant, before the State Consumer Disputes Redressal Commission, within the territorial Jurisdiction whereof, a part of cause of action arose to him. It is apparent on record that the Branch Office of the opposite party is situated at Chandigarh. In the Buyer’s Agreement dated 10.07.2012, description of first party to the Agreement is given as under:-

UNITECH LIMITED, a Public Limited Company duly incorporated under the Companies Act 1956, having its Marketing Office at Unitech Ltd., SCO 189-90-91, Sector 17-C, Chandigarh and its Registered Office at 6, Community Centre, Saket, New Delhi 110017 (hereinafter referred to as the Developers which expression shall, unless it be repugnant to the context or meaning thereof, be deemed to include its executors, administrators, successors and assigns) acting through its authorized signatory(ies).”

  1.         It is clearly mentioned that the Company has its Marketing Office at SCO 189-90-91, Sector 17-C, Chandigarh. Registered Office is situated at 6, Community Centre, Saket, New Delhi.  Be that as it may, as per documents placed on record by the opposite party, alongwith written statement, it becomes apparent that Marketing Office at Chandigarh/opposite party was responsible for development and marketing of the project, in question. Entire correspondence with the Authorities qua development of the project and getting necessary permissions were being taken up by the Officers of the opposite party,  posted at Chandigarh. Above fact makes it clear that the Branch Office at Chandigarh was substantially taking up the activities qua the project, in question. Copy of customer ledger account Annexure C-25 in respect of the unit, in question, was also issued by the opposite party at Chandigarh. In para no.1 of the preliminary submission, it is also mentioned that Marketing Office of the Company is situated at Chandigarh. Besides all above, it has been candidly admitted by the opposite party, in para no.24 of its reply on merits, that that all the payments were received from the complainant by Chandigarh Office of the Company. The Hon’ble Supreme Court of India in State of Punjab Vs. Nohar Chand, 1984 SCR (3) 839 held that the Court(s), in whose Jurisdiction, products/goods are marketed, will have the territorial Jurisdiction to entertain and decide a complaint. The principle of law laid down in the aforesaid case is fully applicable to the facts of the present case. In view of fact of Marketing Office of  the opposite party at Chandigarh and also as per the documents, referred to above, a part of cause of action, arose to the complainant, at Chandigarh, this Commission has got territorial Jurisdiction to entertain and decide the complaint.  The objection taken by the  opposite party, in its written version, in this regard, therefore, being devoid of merit, must fail, and the same stands rejected. 
  2.         Another objection raised by Counsel for the  opposite party, with regard to pecuniary jurisdiction, also deserves rejection. It may be stated here, that the complainant has sought refund of an amount of Rs.48,03,140/-, paid by him, towards price of the unit, in question, alongwith interest @18% p.a. from the respective dates of deposits, till realization;  compensation to the tune of Rs.3 lacs, for mental agony & physical harassment, deficiency in providing service and adopting unfair trade practice; and cost of litigation, to the tune of Rs.33,000/-, aggregate value whereof [excluding the interest claimed] fell above Rs.20 lacs and below Rs.1 crore. Thus, this Commission has got pecuniary Jurisdiction, to entertain and decide the complaint.

                As far as the interest claimed by the complainant, on the deposited amount and litigation expenses is concerned, it is not required to be added, at this stage, to the value of the reliefs claimed, for determining the pecuniary Jurisdiction of this Commission, in view of law laid down by three Member Bench of the National Commission, in a case titled as Shahbad Cooperative Sugar Mills Ltd. Vs. National Insurance Co. Ltd. & Ors. II (2003) CPJ 81 (NC), wherein it was clearly held that since rate and the period for which interest has to be allowed, is within the discretion of Consumer Foras, and that too at the stage, when the complaint is finally disposed of, as such, the same being imaginary would not be taken into consideration, at the time of filing of the same (complaint), for the purpose of determination of pecuniary jurisdiction. Not only as above, in the case of Denis Exports Pvt. Ltd Vs. United India Insurance Co. Ltd, Consumer Case No. 196 of 2016, decided on 08 March 2016, it was clearly held by the National Commission that interest component being imaginary, will not be added in the reliefs sought by the consumers, for determining pecuniary jurisdiction of the Consumer Foras. The principles of law, laid down, in the cases referred to above, are fully applicable, to the facts of the instant case. In view of the above, the submission of Counsel for the  opposite party, that this Commission lacks pecuniary Jurisdiction, being devoid of merit, must fail and the same stands rejected.

  1.         To defeat claim of the  complainant, another objection was raised by Counsel for the opposite party, that the complainant is a speculator, as he has purchased the unit, in question, for earning profits i.e. for resale, as and when there is escalation in the prices of real estate, therefore, he would not fall within the definition of consumer, as defined by Section 2 (1) (d) (ii) of the Act.

                It may be stated here that there is nothing, on record to show, that the complainant is a property dealer, and is indulged in sale and purchase of property, on regular basis. On the other hand, the complainant, in paragraph no.2 of his complaint supported by his affidavit and also in the rejoinder, has clearly averred that he had purchased the said unit, for his residential purpose. In the absence of any cogent evidence, in support of the objection raised by the opposite party, mere bald assertion to that effect, cannot be taken into consideration. In a case titled as Kavita Ahuja Vs. Shipra Estate Ltd. and Jai Krishna Estate Developer Pvt. Ltd. 2016 (1) CPJ 31, by the National Consumer Disputes Redressal Commission, New Delhi, it was held that the buyer(s) of the residential unit(s), would be termed as consumer(s), unless it is proved that he or she had booked the same for commercial purpose. Similar view was reiterated by the National Commission, in DLF Universal Limited Vs Nirmala Devi Gupta, 2016 (2) CPJ 316. The principle of law, laid down, in the aforesaid cases, is fully applicable to the present case. Under these circumstances, by no stretch of imagination, it can be said that the unit, in question, was purchased by the complainant, by way of investment, with a view to earn profit, in future. The complainant, thus, falls within the definition of ‘consumer’, as defined under Section 2(1)(d) of the Act. Such an objection, taken by the  opposite party, in its written reply, therefore, being devoid of merit, is rejected.  

  1.         Another objection was raised by Counsel for the  opposite party that the consumer complaint is not maintainable, and only a Civil Court can decide the case. It may be stated here, that the complainant hired the services of the  opposite party, for purchasing the unit, in the manner, referred to above. According to Article 4.a.(i) of the  Agreement, the  opposite party was liable to deliver physical possession of the constructed unit, within a period of 24 months, from the date of execution of the same (Agreement) i.e. latest by 09.07.2014, alongwith all basic amenities as mentioned in Article 2.a.(iii) [at page 35 of the file) of the Agreement. Section 2 (1) (o) of the Act, defines service as under:-

“service” means service of any description which is made available to potential users and includes, but not limited to, the provision of facilities in connection with banking, financing insurance, transport, processing, supply of electrical or other energy, board or lodging or both,  housing construction, entertainment, amusement or the purveying of news or other information, but does not include the rendering of any service free of charge or under a contract of personal service”

From the afore-extracted Section 2(1)(o) of the Act, it is evident that housing/construction, also comes within the definition of a service. In Narne Construction P. Ltd., etc. etc. Vs.  Union Of India and  Ors. Etc., II (2012) CPJ 4 (SC),  it was held that when a person applies for the allotment of a building or site or for a flat constructed by the Development Authority and enters into an agreement with the Developer, or the Contractor, the nature of transaction is covered by the expression ‘service’ of any description. Housing construction or building activity carried on by a private or statutory body constitutes ‘service’ within the ambit of Section 2(1)(o) of the Act. Similar principle of law, was laid down, in Haryana Agricultural Marketing Board Vs. Bishambar Dayal Goyal & Ors. (AIR 2014 S.C. 1766). Under these circumstances, the complaint involves the consumer dispute, and the same is maintainable. Not only this, Section 3 of the 1986 Act, provides an alternative remedy. Even if, it is assumed that the complainant has a remedy to file a suit, in the Civil Court, the alternative remedy provided under Section 3 of the Act, can also be availed of by him, as he falls within the definition of a consumer. In this view of the matter, the objection of the  opposite party, in this regard, being devoid of merit, must fail, and the same stands rejected.

  1.         Admittedly, possession of the unit, was not delivered to the  complainant, by 09.07.2014 or even till date. Even, in the written version, the  opposite party, frankly admitted that possession of the unit, in question, could not be offered to the  complainant, by the stipulated date, as it had failed to complete the development work, on account of extreme financial hardship, due to recession in the market/global meltdown, and also on account of non-provision of electricity in the said project, by the Punjab State Power Corporation Limited (PSPCL). Even partial completion certificate has not been obtained by the opposite party, till date, what to speak of obtaining final completion certificate, which is mandatory, before delivery of possession of the unit. Admission made by the  opposite party, itself makes it clear that it has not obtained necessary approvals/sanctions from the PSPCL, as a result whereof, it was not provided with electricity, for the project in question. Still, the opposite party is working on obtaining permissions, from the PSPCL/GMADA. Secondly, when the  opposite party, had already received more than 90% of the sale consideration, towards the unit(s), from the allottee(s), then it does not lie in its mouth, that it faced extreme financial hardship, due to recession in the market, as far as the project, in question, is concerned. It is not that the  opposite party was, in the first instance, required to develop the project, by arranging funds out of its own sources, and, thereafter, the units were to be sold to the allottees, on future payment basis. Had this been the case of the  opposite party, only in those circumstances, the plea with regard to facing extreme financial hardship would have been considered to be correct, by this Commission.

                Even otherwise, the said difficulty/ground i.e. recession in the market/global meltdown would not fall under the definition of force majeure circumstances, for not completing the construction and development work at the site. A change in economic or market circumstances affecting the profitability of a contract or the circumstance, is not regarded as a force majeure condition. Neither any new legislation was enacted nor an existing rule, regulation or order was amended, stopping suspending or delaying the construction/development work of the project, in which flat(s)/plot(s) were agreed to be sold to the consumers. There is no allegation of any lock-out or strike by the labour, at the site of the project. There is no allegation of any slow-down having been resorted to by the labourers of the  opposite party or the contractors engaged by it, at the site of the project. There was no civil commotion, war, enemy action, terrorist action, earthquake or any act of God, which could have delayed the completion of construction/development work in the project, within the time stipulated in the Agreement. A similar question fell for determination before the Hon'ble National Consumer Disputes Redressal Commission, New Delhi, in a case titled as Swaran Talwar & 2 others v. M/s Unitech Limited (along three connected complaints),  2015 (4) CPR 34. The National Commission, in that case, while rejecting the plea of the builder, held as under:-

“Coming to the pleas that there was recession in the economy and a disruption due to agitation by farmers and acute shortage of labour, etc., the following view taken by us In Satish Kumar Pandey (Supra) is relevant.

Neither any new legislation was enacted nor an existing rule, regulation or order was amended stopping suspending or delaying the construction of the complex in which apartments were agreed to be sold to the  complainant. There is no allegation of any lock-out or strike by the labour at the site of the project. There is no allegation of any slow-down having been resorted to by the labourers of the  opposite party or the contractors engaged by it at the site of the project. There was no civil commotion, war, enemy action, terrorist action, earthquake or any act of God which could have delayed the completion of the project within the time stipulated in the Buyers Agreement. It was contended by the counsel for the OP that the expression ‘slow down’ would include economic slow-down or recession in the Real Estate sector. I, however, find no merit in this contention. The word ‘slow down’ having been used alongwith the words lock-out and strike, I has to be read ejusdem generis with the words lock-out and strike and therefore, can mean only a slow down if resorted by the labourers engaged in construction of the project.”.

  1.         The principle of law laid down in the aforesaid case is fully applicable to the facts of the present case. The  opposite party, therefore, cannot take shelter under Article 8.b. of the Agreement, for extension of period, for delivery of possession of the unit. By making a misleading statement, that  possession of the unit, in question, would be delivered within a period of 24 months, from the date of execution of the Agreement but on the other hand, by not abiding by the commitments made, the  opposite party was not only deficient, in rendering service, but also indulged into unfair trade practice.
  2.         Another objection raised by Counsel for the opposite party that time was not the essence of contract, is also devoid of merit. It may be stated here that it was clearly mentioned in Article 4.a(i) of the Agreement that possession of the unit was proposed to be delivered by the opposite party, within a period of 24 months, subject to force majeure circumstances. At the same time, force majeure conditions claimed by the opposite party has been negated by this Commission, while giving detailed findings, as per law. Thus, under these circumstances, as per Article 4.a.(i) of the Agreement, the opposite party was bound to deliver possession of the unit, within a maximum period of 24 months, from the date of execution of the same i.e. 09.07.2014. The time was, thus, unequivocally made the essence of contract.

                Even otherwise, the opposite party cannot evade its liability, merely by saying that since the word proposed or tentative was mentioned in the Agreement, for delivery of possession of the unit, as such, time is not to be considered as essence of the contract. Non-mentioning of exact date of delivery of possession of the unit(s) in the Buyer’s Agreement, is an unfair trade practice, on the part of the Builder. The builder is bound to mention the exact/specific date of delivery of possession of the unit(s) to the allottees/purchasers thereof.  It was so said by the Hon'ble National Commission, in Rajeev Nohwar & Anr. V/S Sahajanand Hi Tech Construction Pvt Ltd, 2016 (2) CPR 769. Relevant portion of the said case reads thus:-

“Merely making possession by a particular date will also not meet the requirement of law and the promotor is under a legal mandate to stipulate a specific date for delivery of possession of the flat in the agreement which he executes with the flat buyer”.

In view of above, the plea of Counsel for the opposite party in this regard also stands rejected.

  1.         The next question, that falls for consideration, is, as to whether, the complainant is entitled to refund of the amount of Rs.48,03,140/-, deposited by him. It is an admitted fact that the  opposite party is unable to deliver  possession of the unit, in question, on account of pending development works; construction  of the unit; want of basic amenities etc.  as admitted by it, and firm date of delivery of possession of the unit, could not be given to him (complainant). Still, the opposite party is saying that it is making efforts to complete the construction and deliver possession of the unit to the complainant. No firm date has been given in this regard. The complainant cannot be made to wait for an indefinite period, for delivery of actual physical possession of the unit. As stated above, the  opposite party failed to prove, by placing on record, any cogent and convincing material, that it actually encountered any force majeure circumstances, as a result whereof, its stand has been negated by this Commission. The  opposite party, therefore, had no right, to retain the hard-earned money of the complainant, deposited towards price of the unit, in question. The complainant is thus, entitled to get refund of amount deposited by him. In view of above facts of the case, the  opposite party is also under an obligation to compensate the complainant, for inflicting mental agony and causing physical harassment to him, as also escalation in prices.
  2.         It is to be further seen, as to whether, interest, on the amount refunded, can be granted, in favour of the  complainant. It is not in dispute that an amount of Rs.48,03,140/-,  was paid by the complainant, without getting anything, in lieu thereof. The said amount has been used by the  opposite party, for its own benefit. There is no dispute that for making delayed payments, the  opposite party was charging heavy rate of interest (compounded quarterly @18%) as per Article 2.c. of the Agreement, for the period of delay in making payment of instalments.  It is well settled law that whenever money has been received by a party and when its refund is ordered, the right to get interest follows, as a matter of course. The obligation to refund money received and retained without right implies and carries with it, the said right. It was also so said by the Hon'ble Supreme Court of India, in UOI vs. Tata Chemicals Ltd (Supreme Court), (2014) 6 SCC 335 decided on March 20th, 2014 (2014) 6 SCC 335). In view of above, the  complainant is certainly entitled to get refund of the amount deposited by him, to the tune of Rs.48,03,140/-, alongwith interest @15% compounded quarterly, from the respective dates of deposits (less than the rate of interest charged by the  opposite party, in case of delayed payment i.e. 18% compounded quarterly, as per Article 2.c. of the Agreement), till realization.       
  3.         The next question, that falls for consideration, is, as to whether, the complaint filed by the complainant, is premature or not. It may be stated here, that possession of the unit, was required to be delivered, in favour of the complainant by 09.07.2014. Admittedly, possession of the unit, in question, was not even offered to the complainant by the stipulated date, or even by the time, the complaint was filed, for want of construction and basic amenities. Under these circumstances, the complainant was at liberty to file the complaint after 09.07.2014 i.e. the promised date, when after waiting for sufficient time, he found that the opposite party is unable to deliver possession of the unit, in question. Had the complainant filed this complaint before 09.07.2014 (promised date), only in those circumstances, it would have been said that the complaint filed is premature. In view of above, an objection taken by the opposite party, in this regard, is rejected out-rightly.        
  4.         As far as the plea taken by the  opposite party regarding forfeiture of earnest money is concerned, it may be stated here that the same also stands rejected, because it is not the case of the  opposite party, that it was ready with possession of the fully constructed unit, to be delivered to the complainant, by the stipulated date i.e. 09.07.2014, but the complainant wanted to rescind the contract, on account of some financial constraints or for any personal reason, and is seeking refund of the amount deposited. Had this been the case of the  opposite party, only in those circumstances, it would have been held that since the complainant himself is rescinding the contract, as such, he is entitled to the amount deposited, after deduction of the earnest money, as per the terms and conditions of the Agreement. In this view of the matter, the plea taken by the  opposite party, in this regard, has no legs to stand and is accordingly rejected.   
  5.         It was, however, submitted by the Counsel for the  opposite party, that since the parties are governed by the terms and conditions of the Agreement, in case of delay, in delivery of physical possession of the unit, it (opposite party), was only liable to make payment of penalty, in the sum of Rs.5/- (Rupees Five only) per sq.feet, per month of the saleable area, for such period of delay, as per Article 4.c. of the Agreement. She further submitted that the opposite party is ready to pay this amount, for the period of delay, in delivery of possession of the unit. The hard-earned money of the complainant was used by the  opposite party, for investment, for a long time. He was not refunded the amount, to which he was entitled to. If the opposite party is allowed to invoke Article 4.c. of the Agreement, in the instant case, that would amount to enriching it, at the cost of the complainant. Under these circumstances, shelter cannot be taken by the opposite party, under Article 4.c. of the Agreement. In this view of the matter, the plea taken by the  opposite party, in this regard, has no legs to stand and is accordingly rejected.           
  6.         No other point, was urged, by Counsel for the parties.
  7.         For the reasons recorded above, the complaint is partly accepted, with costs. The  opposite party is directed as under:-

 

  1. To refund the amount Rs.48,03,140/-,  to  the  complainant, alongwith interest @15% compounded quarterly,  from the respective  dates  of  deposits onwards.
  2. To pay compensation, in the sum of Rs.3 lacs, for causing mental agony and physical harassment, to the complainant, as also escalation in prices.
  3. To pay cost of litigation, to the tune of Rs.33,000/- (as prayed) to the  complainant.
  4. The payment of awarded amounts mentioned at sr.nos.(i) to (iii), shall be made, within a period of 02 (two) months from the date of receipt of a certified copy of this order, failing which, the amount mentioned at sr.no.(i) shall carry penal interest @18% compounded quarterly, instead of @15%, from the respective dates of deposits onwards, and interest @15% compounded quarterly, on the amounts mentioned at sr.nos.(ii) and (iii), from the date of filing of this complaint, till realization.

 

 

 

  1.         However, it is made clear that, if the complainant has availed loan facility from any banking or financial institution, for making payment of installments towards the said unit, it will have the first charge of the amount payable, to the extent, the same is due to be paid by him  (complainant).
  2.         Certified Copies of this order be sent to the parties, free of charge.
  3.         The file be consigned to Record Room, after completion.

Pronounced.

01.08.2016

Sd/-

[JUSTICE JASBIR SINGH (RETD.)]

PRESIDENT

 

 

Sd/-

(DEV RAJ)

MEMBER

 

 

Sd/-

(PADMA PANDEY)

        MEMBER

 

Rg.

 

 


 

 

 

 

 

 

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.