NCDRC

NCDRC

CC/2392/2017

RAJ KUMAR DHIMAN - Complainant(s)

Versus

UNITECH LTD. - Opp.Party(s)

MR. RAJEEV RANJAN KUMAR & MR. RAKESH BAJAJ

04 Oct 2018

ORDER

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION
NEW DELHI
 
CONSUMER CASE NO. 2392 OF 2017
 
1. RAJ KUMAR DHIMAN
S/O LATE SHRI MAST RAM R/O H.NO. 1590, FIRST PLOT, SECTOR-69,
MOHALI-160059
PUNJAB
...........Complainant(s)
Versus 
1. UNITECH LTD.
THROUGH ITS AUTHORIZED PERSON SCO 189-190-191, SECTOR-17 C,
CHANDIGARH-160017
...........Opp.Party(s)

BEFORE: 
 HON'BLE MR. JUSTICE V.K. JAIN,PRESIDING MEMBER

For the Complainant :
Mr. Rajeev Ranjan, Advocate
Mr. Rakesh Bajaj, Advocate
For the Opp.Party :
NEMO

Dated : 04 Oct 2018
ORDER

JUSTICE V.K. JAIN, PRESIDING MEMBER (ORAL)

          A residential plot in a project namely “Uniworld City” which the opposite party was to develop in Sector 107 of Mohali in Punjab was booked by SDS Contractors & Builders Private Limited.  Plot No. 0080 in Block B was allotted to the aforesaid company by the opposite party for a consideration of Rs.74,72,010/-.  The said allotment was later purchased by the complainant and the buyers’ agreement, which the opposite party had executed with SDS Contractors & Builders Pvt. Ltd. on 02.4.2008, was endorsed in favour of the complainant on 05.5.2011.  In terms of Clause 4.A(i) of the said agreement, the possession of the plot was to be delivered within thirty six months of its execution.  Therefore, the possession ought to have been delivered by 02.4.2011. Even if the time for delivery of possession is computed from the date of transfer of the allotment to the complainant, the possession ought to have been delivered by 05.5.2014.  This complaint was instituted much later in the year 2017.   The grievance of the complainant is that the possession of the plot has not even been offered to him despite he and his predecessor having already paid a sum of Rs.90,55,800/- to the opposite party.  The complainant is therefore before this Commission, seeking refund of the aforesaid amount along with compensation etc.

2.      The opposite party did not file its written version despite having been served on 03.10.2017.  The right of the opposite party to file its written version therefor was closed vide order dated 25.1.2018.

3.      I have heard the learned counsel for the complainant and have considered the affidavit filed by the complainant by way of evidence.

4.      The affidavit and documents filed by the complainant prove the allotment as well as the agreement executed between the opposite party and the predecessor in interest of the complainant.  The payment alleged to have been made to the opposite party also stands proved by way of the evidence and the statement of account filed by the complainant.

5.      In terms of Clause 4.A(i) of the agreement, the possession of the plot ought to have been delivered by 02.4.2011.  Since the possession has not even been offered to the complainant, he is entitled to seek refund of the entire principal amount paid to the opposite party along with appropriate compensation.

6.      Though, no written version has been filed by the opposite party, the grounds on which several other consumer complaints, relating to allotment of plot in this every project were contested by the opposite party, have already been rejected by this Commission.  A reference in this regard is made to the decision of this Commission in Harinder Singh Vs. M/s. Unitech Limited, CC/25/2016 decided on 19.12.2016.  The order passed by this Commission in Harinder Singh (supra), to the extent it is relevant reads as under:-

“2.      The complaint has been opposed by the OP which has admitted the allotment made to the complainant as well as the payment made by him.  It has been stated in the written version filed by the OP that though they tried their best to hand over the possession of the plot but the project got delayed on account of reasons and circumstances beyond their control.  The following, according to the OP, are the main reasons which resulted in delaying the aforesaid project:

          (i) There was a slump in the real estate industry.

          (ii) There was extreme shortage of labour/workers due to Commonwealth Games organized in 2010. 

          (iii) There was shortage of labour on account of schemes like National Rural Employment Guarantee Act (NREGA) and Jawaharlal Nehru National Urban Renewal Mission (JNNURM).

          (iv) There was an acute shortage of water in NCR region.

         (v) Vide notification dated 14.09.1999, Ministry of Environment and Forest had barred excavation of soil for manufacture of bricks. 

          (vi) There was shortage of raw materials such as sand on account of mining operations having been suspended by the Hon’ble Supreme Court vide its order dated 08.05.2009.

          It is also stated in the written version filed by the OP that in case of delay in offering possession, the purchaser is entitled to a penalty compensation of Rs.50/- per sq. yard per month of the area of the plot and therefore, the calculation of the compensation cannot exceed the said amount. 

3.      The learned counsel for the complainant submits that the present complaint is squarely covered by the decision of this Commission in CC No. 346 of 2013 Lt. Col. Anil Raj & Anr. Vs. M/s Unitech Ltd. & Anr. decided on 02.05.2016.  In Col. Anil Raj (Supra), the complainants had entered into an agreement for purchase of a plot in this very project i.e. Uniworld City in Mohali, Punjab but the OP had failed to deliver possession of the said plot within the time stipulated in the Buyers Agreement.  The OP, during the course of hearing of the aforesaid complaint, expressed willingness to refund the amount deposited by the complainant alongwith interest @ 10% per annum.  They were directed by this Commission to refund accordingly.  The OP however, failed to comply with the said order.  This Commission, considering the deficiency on the part of the OP in rendering services to the aforesaid complainant and also taking note of the conduct of the OP in not honouring its own commitment of refund alongwith interest @ 10% per annum, directed it to pay simple interest @ 18% per annum from the date of each deposit till realization.  The OP was also directed to pay cost of Rs.3,00,000/- to the complainant and deposit Rs.2,00,000/- with the Consumer Welfare Fund of this Commission. 

4.      Even on merits, I find no justification for the delay in offering possession of the plot to the complainant.  As far as the Commonwealth Games are concerned, they were held way back in October 2010, almost five years before the parties entered into the second Buyers Agreement.  Therefore, reference to the said Games is wholly misplaced. 

          There is absolutely no evidence of the OP having tried to recruit labourers and having not been able to do so on account shortage of labour in the market.  Therefore, there is no merit in the plea that the project could not be completed on account of shortage of labour.  In any case, the alleged shortage of labour refers to NCR region whereas the plot in question is stated in Mohali. 

5.      As regards the alleged shortage of water, the order passed by the Punjab and Haryana High Court on 16.07.2012, the notification issued by the Ministry of Environment and Forest on 14.09.1999 as well as the order of the Hon’ble Supreme Court dated 08.05.2009 suspending the mining operations in Aravali Region are concerned, all these events happened prior to the parties entering into the second Buyers Agreement dated 23.03.2015.  The OP despite the aforesaid events, having agreed to deliver possession of the plot to the complainant within six months of the said Buyers Agreement, cannot take the plea that the completion of the project has been delayed on account of the aforesaid reasons.  I am therefore, satisfied that there was no justification for the delay in completion of the project and offering possession to the complainant.” 

7.        The learned counsel or the complainant states on instructions that the complainant is restricting his claim to the refund of the entire principal amount along with simple interest @ 10% per annum in terms of Clause 4(e) of the Buyers’ Agreement, which reads as under:

“4.e. If for any reason the Developers are not at all in a position to offer the plot, as agreed herein, the Developers may offer the purchaser(s) an alternative property or refund the amount in full with interest @ 10% per annum without any further liability to pay damages or any other compensation.”

8.    For the reasons stated hereinabove, the complaint is disposed of with the following directions:

(i)      The OP shall pay the entire principal amount of Rs.90,55,800/- alongwith compensation in the form of simple interest @ 10% per annum with effect from the date of each payment till the date on which the entire principal amount along with compensation in the form of interest is actually refunded.

(ii)     The opposite party shall also pay a sum of Rs.25,000/- as the cost of litigation to the complainants.

         (iii)    The payment in terms of this order shall be paid within three months from today.

 
......................J
V.K. JAIN
PRESIDING MEMBER

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.