View 2283 Cases Against Unitech
Mohinder Pal Ahuja filed a consumer case on 16 Apr 2018 against Unitech Limited in the StateCommission Consumer Court. The case no is CC/720/2017 and the judgment uploaded on 19 Apr 2018.
STATE CONSUMER DISPUTES REDRESSAL COMMISSION,
U.T., CHANDIGARH
Complaint case No. | : | 720 of 2017 |
Date of Institution | : | 03.10.2017 |
Date of Decision | : | 16.04.2018 |
…… Complainants
…. Opposite parties
Complaint under Section 17 of the Consumer Protection Act, 1986
BEFORE: JUSTICE JASBIR SINGH (RETD.), PRESIDENT.
MR. DEV RAJ, MEMBER.
MRS. PADMA PANDEY, MEMBER.
Argued by:- Sh.Abhishek Bhateja, Advocate for the complainants.
Mrs.Vertika H. Singh, Advocate for opposite parties No.1 and 2.
Ms.Kshitija Mittal, Advocate for opposite party no.3.
PER JUSTICE JASBIR SINGH (RETD.), PRESIDENT
The complainants are real brothers. They have filed this complaint, by alleging that believing glossy advertisements, made by the opposite parties, regarding launching of their residential project, under the name and style ‘UNIHOMES, situated in Mega Township, Uniworld City, Sector 107, Mohali, Punjab, they purchased a flat bearing no.0012 (3 bedroom), Block B, Ground Floor, measuring 1077 square feet, (in short the unit). As per brochure issued, venture launched was projected to be masterpiece of urban living. Total sale consideration of the said unit was fixed at Rs.29,51,886/-, which included Rs.26,90,259/- towards basic sale price; Rs.1,50,000/- towards preferential location charges and Rs.1,11,627/- towards External Development Charges (EDC). The complainants opted for construction linked payment plan. Buyer’s Agreement was executed between the parties on 13.03.2010.
“It is evident from a bare perusal of Sections 21, 17 and 11 of the Consumer Protection Act that it’s the value of the goods or services and the compensation, if any, claimed which determines the pecuniary jurisdiction of the Consumer Forum. The Act does not envisage determination of the pecuniary jurisdiction based upon the cost of removing the deficiencies in the goods purchased or the services to be rendered to the consumer. Therefore, the cost of removing the defects or deficiencies in the goods or the services would have no bearing on the determination of the pecuniary jurisdiction. If the aggregate of the value of the goods purchased or the services hired or availed of by a consumer, when added to the compensation, if any, claimed in the complaint by him, exceeds Rs. 1.00 crore, it is this Commission alone which would have the pecuniary jurisdiction to entertain the complaint. For instance if a person purchases a machine for more than Rs.1.00 crore, a manufacturing defect is found in the machine and the cost of removing the said defect is Rs.10.00 lacs, it is the aggregate of the sale consideration paid by the consumer for the machine and compensation, if any, claimed in the complaint which would determine the pecuniary jurisdiction of the Consumer Forum. Similarly, if for instance, a house is sold for more than Rs.1.00 crore, certain defects are found in the house, and the cost of removing those defects is Rs.5.00 lacs, the complaint would have to be filed before this Commission, the value of the services itself being more than Rs.1.00 crore. ”
In the present case also, total value of the unit, in question, i.e. Rs.29,51,886/-, plus compensation claimed by way of interest @18% p.a. on the deposited amount of Rs.28,03,895/-and also Rs.10 lacs, for mental agony and physical harassment, if taken into consideration, in no way, exceeds Rs.1 crore. Thus, this Commission has got pecuniary Jurisdiction, to entertain and decide the complaint. The objection taken by opposite parties no.1 and 2, that this Commission lacks pecuniary jurisdiction, being devoid of merit, must fail and the same stands rejected.
Not only as above, since it has been proved on record that Marketing office of the Company is located at Chandigarh; the project, in question, was marketed from Chandigarh; in that case also, this Commission has territorial jurisdiction to entertain and decide this complaint, in view of law laid down by the Hon’ble Supreme Court of India in State of Punjab Vs. Nohar Chand, 1984 SCR (3) 839, in which it was held that the Court(s), in whose Jurisdiction, products/goods are marketed, will have the territorial Jurisdiction to entertain and decide a complaint. Not only as above, similar findings were given by the National Commission, in a case titled as Parsvnath Developers and anr. Vs. Som Nath Sharma and 2 ors., First Appeal No.1613 of 2016, decided on 21.03.2017. Relevant contents of the said order read thus:-
“Regarding the question of territorial jurisdiction, the some part of cause of action accrues in Delhi as the agreement was signed at New Delhi. The payment was received at Panchkula in the office of OPs 1 and 2. Similar issue was decided by this Commission in the case of Ravinder Kumar Bajaj vs. Parsvnath Developers Pvt. Ltd. & Ors., first appeal No. 515 of 2016 decided on 23.08.2016 qua same very builder. It was held that “officers of opposite parties no.1 and 2 sitting in Branch Office at Chandigarh were actively participating in marketing and propagating the project, in question. They were dealing with the complainants throughout, by receiving their letters qua progress at the spot and also accepted payment made through cheques. In view of above, objection raised in this regard, stands rejected.”
In view of above, objection taken by the opposite parties, in this regard, therefore, being devoid of merit, must fail, and the same stands rejected.
“service” means service of any description which is made available to potential users and includes, but not limited to, the provision of facilities in connection with banking, financing insurance, transport, processing, supply of electrical or other energy, board or lodging or both, housing construction, entertainment, amusement or the purveying of news or other information, but does not include the rendering of any service free of charge or under a contract of personal service”
From the afore-extracted Section 2(1)(o) of the Act, it is evident that housing/construction, also comes within the definition of a service. In Narne Construction P. Ltd., etc. etc. Vs. Union Of India and Ors. Etc., II (2012) CPJ 4 (SC), it was held that when a person applies for the allotment of a building or site or for a flat constructed by the Development Authority and enters into an agreement with the Developer, or the Contractor, the nature of transaction is covered by the expression ‘service’ of any description. Housing construction or building activity carried on by a private or statutory body constitutes ‘service’ within the ambit of Section 2(1)(o) of the Act. Similar principle of law, was laid down, in Haryana Agricultural Marketing Board Vs. Bishambar Dayal Goyal & Ors. (AIR 2014 S.C. 1766). Under these circumstances, the complaint involves the consumer dispute, and the same is maintainable. Not only this, Section 3 of the 1986 Act, provides an alternative remedy. Even if, it is assumed that the complainants have a remedy to file a suit, in the Civil Court, the alternative remedy provided under Section 3 of the Act, can also be availed of by them, as they fall, within the definition of consumer. In this view of the matter, objection taken by the opposite parties, in this regard, being devoid of merit, must fail, and the same stands rejected.
The above objection taken by the opposite parties is also bereft of merit, in view of judgment passed by the Hon’ble National Commission, titled as M/s. Karwa Developers & 3 Ors. Vs. Shree Vinayak Co-Operative Housing Society Ltd. & 3 Ors., First Appeal No. 980 of 2016, decided on 3rd March, 2017, wherein, a similar plea of the builder was negated, while holding as under:-
“We also do not find any substance in the plea taken by the appellant that under clause 14(a) of the development agreement, the complainant was required to file a civil suit under the Specific Relief Act only, because they were asking for monetary relief. The State Commission rightly stated that the relief sought in the complaint were on account of deficiencies committed by the OP Developers, vis-à-vis, the society. Since there is a specific clause in the agreement for giving the possession of the flat within specific time frame and penalty has been provided if the developers failed to develop the same, the society was well within its rights to file consumer complaint against the OP builder.”
It is not in dispute that the complainants purchased the unit, in question, vide Agreement dated 13.03.2010. Constructed unit was sold in favour of the complainants, for an amount of Rs.29,51,886/-, which includes basic sale price, external development charges etc. In all, the complainants have paid an amount of Rs.28,03,895/-, towards price of the said unit. As per condition no. 4.a.(i) of the Agreement, possession of the fully constructed unit, in a developed project, was to be delivered to the complainants within a period of 36 months, from the date of execution of the same (Agreement), subject to force majeure conditions i.e. on or before 12.03.2013. Before delivery of possession, as per condition no.4.b. of the Agreement, it was incumbent upon the opposite parties, to give notice to the complainants, in case of delay in handing over possession of the unit, beyond the period of 36 months, subject to force majeure circumstances. It was further provided in condition no.4.c. in the Agreement that penalty @Rs.5/- per square feet, per month of the saleable area, for the period of delay in delivery of possession of the flat shall be paid by the opposite parties, to the complainants. The due date of offer of possession of the unit i.e. 12.03.2013 already stood expired. Now it is April 2018.
Contention of Counsel for the complainants that construction at the spot is not complete needs acceptance. By the date, when arguments were addressed before us, possession has not been offered to the complainants. It is not a case of the opposite parties that possession of the unit was ready to be delivered by the stipulated date, but the complainants have refused to come forward to accept the same (possession). Rather, at the time of arguments, Counsel for the opposite parties failed to give any positive date/time, as to when, possession of the constructed unit will be given. It is only said that opposite party no.3 is making best efforts to deliver possession, as it has already applied for issuance of completion certificate vide letter dated 03.02.2016. Qua this very project, in a large number of cases, it has been found as a matter of fact that construction has come to stand still. As stated above, even at the time of arguments, no commitment was made to deliver possession of the unit, in near future.
Even otherwise, not even a single convincing document has been placed on record, by the opposite parties to prove that the unit, in question, is habitable or that the development at the project is complete in all respects. It is well settled law that the onus to prove that the project has been completed and the area/site, in question, is fully developed, is on the builder/the opposite parties. It was so said by the National Commission, in Emaar MGF Land Limited and another Vs. Krishan Chander Chandna, First Appeal No.873 of 2013 decided on 29.09.2014. In the present case, it is very strange that not even a single document has been placed on record, by the opposite parties, in respect of the flat, in question, to prove that the construction is complete and they are actually ready for offer and delivery of possession. In case, all the development activities had been undertaken and construction of the flats is complete at the project site, then it was for the opposite parties, which could be said to be in possession of the best evidence, to produce cogent and convincing documentary evidence, in the shape of the reports and affidavits of the Engineers/Architects, as they could be said to be the best persons, to testify, as to whether, all these development and construction activities, had been undertaken and completed at the site or not, but they failed to do so. At the same time, the opposite parties were also required to produce on record, a copy of the occupation and partial/final Completion Certificates (if obtained), having been issued by the Competent Authorities, which could be said to be best evidence, to prove their case, but they miserably failed to do that also. Mere placing on record an application dated 03.02.2016, allegedly sent to the Competent Authorities, seeking completion certificate in respect of the project, in question, is of no help to the opposite parties.
Under these circumstances, it can be said that there is a material violation on the part of the opposite parties. At the same time, it is also a settled law that when there is a material violation on the part of the builder, in not handing over possession by the stipulated date, the purchaser is not bound to accept the offer, even if the same is made at a belated stage and on the other hand, can seek refund of amount paid. It was so said by the Hon’ble National Commission, in a case titled as Aashish Oberai Vs. Emaar MGF Land Limited, Consumer Case No. 70 of 2015, decided on 14 Sep 2016, wherein, under similar circumstances, while negating the plea taken by the builder, it was held as under:-
“I am in agreement with the learned senior counsel for the complainants that considering the default on the part of opposite parties no.1 and 2 in performing its contractual obligation, the complainants cannot be compelled to accept the offer of possession at this belated stage and therefore, is entitled to refund the entire amount paid by him along with reasonable compensation, in the form of interest.”
Not only as above, in a case titled as Brig Ajay Raina (Retd.) and another Vs. M/s Unitech Limited, Consumer Complaint No.59 of 2016, decided on 24.05.2016, wherein possession was offered after a long delay, this Commission, while relying upon the judgments rendered by the Hon`ble National Commission, ordered refund to the complainants, while holding as under:-
“Further, even if, it is assumed for the sake of arguments, that offer of possession, was made to the complainants, in July 2015 i.e. after a delay of about three years, from the stipulated date, even then, it is not obligatory upon the complainants to accept the same.
Furthermore, in another case titled as M/s. Emaar MGF Land Ltd. & Anr. Vs. Dr.Manuj Chhabra, First Appeal No.1028 of 2015, decided on 19.04.2016, the Hon’ble National Commission, under similar circumstances, held as under:-
“I am of the prima facie view that even if the said offer was genuine, yet, the complainants was not obliged to accept such an offer, made after a lapse of more than two years of committed date of delivery”.
In the present case, as stated above, possession of the unit, has not even been offered, what to speak of delay in offering thereof. Under these circumstances, it is held that since there was a material violation on the part of the opposite parties, in not offering and handing over possession of the unit by the stipulated date or by the time, this complaint was filed, the complainants are, thus, entitled to get refund of amount actually deposited by them. In view of above facts of the case, the opposite parties are also under an obligation to compensate the complainants, for inflicting mental agony and causing physical harassment to them, as also escalation in prices.
Furthermore, plea taken by the opposite party no.3 in its written statement and also raised at the time of arguments, to the effect that delay aforesaid, in handing over possession of the units, is solely attributable to the Govt. Department(s), as they took a long time to grant approval for supply of electricity to the project, has no legs to stand. To substantiate its stand, the Company was required to place on record cogent and convincing evidence on record, to convince this Commission that despite the fact that every step was taken at its end, but the said Department(s) delayed the matter, unnecessarily leading to delay in completing the project. Had this been actually the case of the Company, they would have definitely taken up the matter with the Competent Authorities, by sending letters followed by reminders, to grant approval with regard to provision of electricity to the project or would have lodged complaint against them, at appropriate platform. However, no such, documents are on record.
As such, it can very well be said that such a plea has been taken by the opposite parties, just with a view to evade their liability. Under these circumstances, no help, therefore, can be drawn by the opposite parties, from Clause 8 (b) of the Agreement, relating to force majeure circumstances, as far as the present case is concerned. The complainants are certainly entitled to get refund of the amount deposited by them, towards price of the said unit, as held above.
Since it has been held above that the complainants are entitled to refund of the amount deposited alongwith interest, as such, the plea taken by opposite party no.3 that it is ready to pay delayed compensation @Rs.5/- per square feet, per month, of the saleable area of the unit, in question, for the period of delay cannot be taken into consideration. Had possession of the unit, in question, been sought by the complainants, the matter would have been different, and in those circumstances, necessary directions would have been passed, as per law.
At the same time, it is also held that because the opposite parties were themselves, at fault, in not completing the construction and offering possession of the unit, in question, by the stipulated date or even as on today, as such, their plea that forfeiture clause will be applicable, in the present case, is devoid of merit, and, as such, rejected. Had possession of the unit, in question, been offered by the stipulated date and had the complainants refused to take the same, on account of some personal or financial excuse, the matter would have been different and in that event, necessary directions with regard to forfeiture would have been passed by this Commission, as per law,
It may be stated here that this issue has already been dealt with, by this Commission, in a case titled as ‘Sarbjit Singh Vs. Puma Realtors Private Limited’, IV (2016) CPJ 126, while relying upon ratio of judgments of the Hon’ble Supreme Court, titled as Fair Air Engg. Pvt. Ltd. & another Vs. N. K. Modi (1996) 6 SCC 385, C.C.I Chambers Coop. Housing Society Ltd. Vs Development Credit Bank Ltd. (2003) 7 SCC 233, Rosedale Developers Private Limited Vs. Aghore Bhattacharya and others, (Civil Appeal No.20923 of 2013), Secretary, Thirumurugan Cooperative Agricultural Credit Society v. M. Lalitha (2004) 1 SCC 305 and United India Insurance Co. Ltd. Vs. M/s Pushpalaya Printers, I (2004) CPJ 22 (SC), and LIC of India and another Vs. Hira Lal, IV (2011) CPJ 4 (SC), and held that even in the face of existence of arbitration clause in an Agreement/Allotment Letter, to settle disputes between the parties through Arbitration, in terms of provisions of Section 8 (amended) of 1996 Act, this Commission has jurisdiction to entertain the consumer complaint. Recently, the larger Bench of the National Commission in a case titled as Aftab Singh Vs. Emaar MGF Land Limited & Anr., Consumer Case No. 701 of 2015, vide order dated 13.07.2017, has held that an Arbitration Clause in the Agreements between the complainants and the Builder cannot circumscribe the jurisdiction of a Consumer Fora, notwithstanding the amendments made to Section 8 of the Arbitration Act. Feeling aggrieved against the said findings, the builder filed Civil Appeal bearing No.23512-23513 of 2017 before the Hon’ble Supreme Court of India, which was dismissed vide order dated 13.02.2018.
In view of the above, stand taken by Counsel for the opposite parties, being devoid of merit stands rejected.
Pronounced.
16.04.2018
Sd/-
[JUSTICE JASBIR SINGH (RETD.)]
PRESIDENT
Sd/-
(DEV RAJ)
MEMBER
Sd/-
(PADMA PANDEY)
MEMBER
Rg.
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.