View 9575 Cases Against The New India Assurance
View 8274 Cases Against Construction
View 15959 Cases Against New India Assurance
M/S SBM Nirman Construction Pvt. Ltd. filed a consumer case on 19 Sep 2022 against The New India Assurance Co. Ltd in the Sambalpur Consumer Court. The case no is CC/6/2021 and the judgment uploaded on 19 Sep 2022.
PRESIDENT, DISTRICT CONSUMER DISPUTES REDRESSAL COMMISSION, SAMBALPUR
CONSUMER COMPLAINT NO. 06/2021
M/S SBM Nirman Construction Pvt. Ltd.,
At- Govindtola, PO/Ps- Dhanupali, Dist- Sambalpur.
Represented through Its Managing Director
Sunil Kumar Mohapatra,
Aged about 54 years, S/o- Late Duryodhan Mohanty,
R/O- Gobindtola, Po/Ps- Dhanupali
Dist- Sambalpur. ...………..Complainant
Versus
The New India Assurance Co. Ltd.,
Cuttack District Branch(550401), infront of Arunadaya Market,
Link Road, Cuttack-753012. Represented through the
Senior Branch Manager, The The New India Assurance Co. Ltd.
At/Po-Budharaja, Ps- Ainthapali, Dist- Sambalpur. …………...Opp.Party
Counsels:-
Date of Filing:18.01.2021,Date of Hearing :10.08.2022, Date of Judgement : 19.09.2022
Presented by Dr. Ramakanta Satapathy, PRESIDENT,
The Complainant while executing work of the Executive Engineer (R&B) Division, Jharsuguda vide Agreement No. 464 P1 of 2018-19 for the period 19.01.2019 to 18.03.2020 on 01.09.2019 at Patrapali, Kulabira worksite due to excessive torrential rain, rain water rushed to the site and slowly submerging rain muddy water driver tried his best to save the machine but could not save and ultimately left the machine and informed the O.P.
Being informed Manoj Hota, Surveyor and loss assessor of the O.P. on 02.09.2019 verified and saw that the machine partially submerged inside the muddy water and reported the loss. As asked duly filed up and signed claim form was submitted in 13.09.2019, on 13.09.2019 submitted estimate. The O.P. conducted final survey on 15.09.2019 and joint inspection on 16.09.2019. The O.P. assured to finalize the claim, only if, any one of the options given below is accepted.
It was expected that the machine will run 30,000 hours in ten years and the Complainant preferred the ‘b’ option, communicated the option to insurer on 11.11.2019.
On 13.11.2019 the O.P. insurance company informed that the liability as well as financial assessment of the loss can be ascertained after receiving the technical report of the surveyor. The Complainant waited for surveyor report. The Complainant with the knowledge of O.P. for replacement of the engine spent Rs. 14,69,347/- vide invoice No.SANY-19-20/1541 dated 23.11.2019 although got delivery challan on 10.11.2019. Each and every step was taken with the consultation of surveyor and experts opinion.
On 24.02.2020 the surveyor made a querry to the dealer that how the machine was shifted from accident side, about the difference of 1.73 hours in the hour meter reading, regarding precaution to minimize the loss and regarding the reason while the machine was cleaned and engine started before final survery. The dealer sent letter dated 24.02.2020 and intimated the final Surveyor Mr. H.P. Singh.
On 14.03.2020 the final surveyor submitted his report and categorically mentioned that engine oil and machine was drained and replaced to minimize the loss of insured machine.
The Complainant received letter No. 550401/CLAIM/2020/18596 dated 14.07.2020, the no CLAIM letter with reason that it is coming under ‘O’ and ‘E’ clause of the exception of the policy. ‘E’ clause is not applicable in his case. ‘O’ clause deals about “loss or damage directly or indirectly cause by or arising out of or aggravates by the willful act or negligence of the insured or his representative.” The repudiation of claim is arbitrary, illegal, unilateral and without any basis. The reports of the surveyors and experts were not supplied after repeated request also. The O.P. is guiltily of unfair trade practice by not furnishing the documents. The surveyor not submitted his report in time.
Being aggrieved with the letter of repudiation, the complainant preferred the complaint.
The O.P. referred the exceptions clauses (e), (o) and (m) to (q).
The O.P. admitted the intimation of the insured, damaged to the excavator on 01.09.2019, preliminary survey on 02.09.2019, reported the matter on 24.09.2019 to the insurer.
The final surveyor assessed the loss on two basis:
The O.P. on receipt of survey report repudiated the claim on the following grounds:
The no claim/repudiation is legal and justified.
Issue No. 1 Whether this Complaint is not a Consumer dispute?
Both the parties to the complaint admitted the execution of policy No. 55040144186500000066 and period of insurance as 08.02.2019 to 07.02.2020. The Complainant has paid Rs. 17,830/- to-wards premium Rs. 3210/- GST total Rs. 21,040/- to the O.P. Both the parties have entered in to contract of insurance with conditions and limitations. Accordingly, the complaint is a consumer dispute.
Issue No.2 Whether the O.P. followed due procedure for settlement of claim?
01.09.2019- 4P.M.- Date and time of loss.
02.09.2019- Date of survey.
13.09.2019- Claim submitted by the Complainant.
15.09.2019 & final survey conducted.
24.09.2019-Preliminary survey report.
14.03.2020-Final Survey report submitted.
14.07.2020- Repudiated the claim.
The I.R.D.A. Regulation 2017 in Regulation 15 clearly provide the claim procedures. In the preliminary survey report dated 24.09.2019 Er. Manoj Hota submitted that the machine while in operation in digging the soil engaged for road construction work suddenly due to heavy rain and subsequently flow of heavy rain and subsequent flow of heavy water near the operation side partially submerged inside the muddy water and the damage is consistent with reported cause/nature of loss. As per the regulation with 90 days the surveyor has to submit his final report. On 15.09.2019 and 16.09.2019 the final survey conducted, report submitted on 14.03.2020. Neither the O.P. submitted the date of report submission appointment of surveyor not it is pressed by the complainant. Date of final survey and date of report submission if both dates are taken, within 90 days the final report has not been submitted, which is a clear violation of the IRDA Regulation.
The Complainant on the quarry of the surveyor vide mail dated 24.02.2020 clearly narrated the fact of difference of HMR reading. When the machine was slowly submerging in to the rain muddy water the driver tried his best to save the machine from being drowned. The driver tried to save it by running the machine for more than 1.7 hours but could not save then left the machine and informed the customer. Second time HMR reading was not taken. Further in the final report the surveyor mentioned the explanation given by Complainant about draining of engine oil of the machine. The reason of drainage is to minise the loss to the machine. The surveyor also mentioned that in the drained oil some pieces of foreign materials are found. From the above observation of the surveyor it is very clear that the driver has taken due care and caution to save the machine but failed.
In the other hand the complainant cited L.I.C. of India Vs Bhupender Pal & others case decided by Hon’ble Himachal Pradesh SCDRC which is relating to Regulation 3 of the IRDA. In the present case it is not applicable.
The issue is answered against the O.P.
Issue No.3 What relief the Complainant is entitled to get?
In consultation with the surveyor the complainant has replaced the engine for Rs. 14,69,347/- although the surveyor assessed Rs. 11,43,684.21P. on replacement basis. The Sum insured in the machine is Rs. 53.00lakhs. The Complainant is entitled for the damage from the O.P. and accordingly it is ordered:
ORDER
The Complaint is allowed on contest against the O.P. The O.P. is liable to pay Rs. 14,69,347/- with 7 % interest P.A. w.e.f. 01.09.2019 to the Complainant within one month of this order. Further the O.P. is liable to pay Rs. 70,000/- fitting charges, and compensation of Rs. 2.00lakhs. In case of non payment the entire amount will carry 12% interest P.A. till realisation. The O.P. is to pay litigation cost of Rs. 10,000/- to the complainant.
Order pronounced in open court on this 19th September 2022.
Supply free copies to the parties.
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.