Kerala

Kollam

CC/2/2019

Subhash Memorial Grandhasala, - Complainant(s)

Versus

The Executive Engineer, - Opp.Party(s)

Adv.SACHIN.C

01 Jul 2019

ORDER

Consumer Disputes Redressal Forum
Civil Station , Kollam-691013.
 
Complaint Case No. CC/2/2019
( Date of Filing : 17 Jan 2019 )
 
1. Subhash Memorial Grandhasala,
Anappara,Kadakkal Village,Kollam District-691536.Represented by Secretorty
...........Complainant(s)
Versus
1. The Executive Engineer,
P.H.Division Kottarakkara,(Water Authority Kottarakkara)Pin-691 506.
2. The Assistant Executive Engineer,
Water Authority P.H.Sub Division, Chingeli,Pulippara.P.O,Kadakkal-691 536,Kollam Dist.
............Opp.Party(s)
 
BEFORE: 
 HON'BLE MR. JUSTICE E.M.MUHAMMED IBRAHIM PRESIDENT
 HON'BLE MRS. SANDHYA RANI.S MEMBER
 
For the Complainant:
For the Opp. Party:
Dated : 01 Jul 2019
Final Order / Judgement

IN THE CONSUMER DISPUTES REDRESSAL  FORUM, KOLLAM

Dated this the    1st    Day of  July   2019

 

  Present: -  Sri. E.M.Muhammed Ibrahim, B.A, LL.M. President

                   Smt.S.Sandhya Rani, BSc,LL.B, Member

                                               

                                                        CC No.02/19

Secretary                                                    :         Complainant

Subhash Memorial Grandhasala

Anappara

Kadakkal Village

Kollam-691536

[By Adv.Sachin.C]

V/s

  1. The Executive Engineer                    :         Opposite parties

          P.H.Division, Kottarakkara

       (Water Authority, Kottarakkara)

        Pin-691506.

  1. The Assistant Executive Engineer

        Water Authority  P.H Sub Division

        Chingeli, Pulippara P.O

        Kadakkal-691536

       Kollam Dist.

     [By Adv.Sabitha.G.Nath]

ORDER

E.M.MUHAMMED IBRAHIM , B.A, LL.M,President

                Complainant represented.  Opposite party present.  Settled for Rs.4316/-.  Complainant agreed to pay the amount in 2 equal monthly instalment on 05.08.19 and 05.09.19 failing  which the opposite party is at liberty to proceed according to law.  After final payment the  opposite party shall reconnect the water connection on paying reconnection charge .  Complaint stands closed in terms of the above settlement.

No costs.

Dated this the 1st   day of  July  2019.

E.M.Muhammed Ibrahim:Sd/-

S.Sandhya Rani:Sd/-

Forwarded/by Order

Senior Superintendent

 
 
[HON'BLE MR. JUSTICE E.M.MUHAMMED IBRAHIM]
PRESIDENT
 
[HON'BLE MRS. SANDHYA RANI.S]
MEMBER

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.