Date of filing : 28.03.2018
Judgment : Dt.13.03.2020
Mrs. Balaka Chatterjee, Hon’ble Member
This petition of complaint is filed under 12 of the C.P.Act, 1986 by Samrat Biswas alleging deficiency in service on the part of the Opposite Parties (1) The District Engineer, CESC (2) Santi Rani Biswas.
Case of the complainant in brief is that the complaint has been residing at premises no. 149/3, Becharam Chatterjee Road along with his mother and younger brother and has been enjoying electricity through the existing meter standing in the name of Opposite Party No.2 ( referred as OP No.2 hereinafter ) happens to be grandmother of the complainant. The complainant has stated that his father who died on 07.06.2016 was the co-owner of said premises along with Santi Rani Biswas (OP No.2 herein), Dipanwita Halder and Santa Roy Chowdhury and after demise of his father legal heirs of said deceased i.e. his wife and two sons became the joint owners of the part of the said premises by the way of inheritance. The complainant has stated that his grandmother (OPNo.2 herein) along with one of her daughter has been in possession of the 1st floor of the building situated on the said premises but due to some internal family disputes relating to consumption of electricity relations between the complainant and his grandmother became sour which resulted the complainant to seek different meter to use electricity as per his own discretion. The complainant has further stated that he applied for providing new connection in his favour on 09.11.2017 with the CESC but the said application was rejected by CESC on 13.11.2017 vide notice being no. 02/15379/17 in violation of Constitutional Rights of the complainant and the complainant again on 08.03.2018 submitted another application with the OP No.1 which was acknowledged by CESC vide letter dt. 08.03.2018 and an estimate of Rs. 17,120/- for installation of new meter was raised and sent to the complainant on 8.3.2018 but without giving any opportunity to deposit the said amount the CESC vide notice dt. 10.3.2018 cancelled the application on the ground that more than one application were under process of the said premises in favour of the complainant. It is stated by the complainant that he contacted Grievance Redressal Cell of the CESC and also sent mail but no result had been yielded and being aggrieved the complainant by filing the instant consumer complainant prayed for direction upon the OP No.1 to provide new connection installing new meter in favour of the complaint, to direct OP No.2 to render all assistance to the OP No.1, to pay Rs. 5000/- towards cost of litigation, Rs. 7,000/- towards compensation.
The complainant annexed application dt. 8.3.2018, letter dt. 8.3.2018 issued by OP No1, Provisional Demand Note, Letter of Cancellation dt. 10.03.2018, letter issued by the complainant to the Greivance Redressal Officer, Letter dt. 13.11.2017 issued by OP No.1, Property tax invoice, Death Certificate of Arup Biswas Electricity Bill for January 2018.
Notices were served but the OP No.2 did not turn up so the case proceeded exparte against OP No.2 vide order dt.2.7.2018.
The OP No.1 contested the case by filing written version denying and disputing all the allegations made out in the petition of complaint stating inter alia , that on receiving application on 9.11.2017 from the complainant for providing new electricity connection the OP No.1 carried out inspection on the said premises and noticed that the said premises had already been provided with the electricity connection and the complainant had been enjoying electricity through the said connection and the complainant was requested to register his grievance as per terms of Clause 14 of the Regulation 53 since new connection could not be provided in his favour. However, the complainant on 8.3.2018 again applied for new connection which was denied on the ground the previous one was rejected. The complainants thereafter approached the Grievance Redressal Officer. It is stated by OP No.1 that as per the Electricity Act, 2003 of West Bengal Regulatory Commission Regulation 2013 the onus lies upon the applicant to prove that the new connection sought not for the purpose of splitting load and, further, any dispute relating to the same is to be settled by the Ombudsman. The OPNo.1 prayed for dismissal of the case.
The complainant and the OP No.1 adduced evidence followed by cross-examination in the form of questionnaire and reply thereto.
In course of argument Ld. Advocate narrated the facts mentioned in the petition of complainant. Ld. Advocate on behalf of the OP submits that the complainant wanted to obtain new connection only for splitting load.OP filed Brief Notes of Argument.
Points for determination :
- Whether there is deficiency in service on the part of the OPs
- Whether the complainant is entitled to the reliefs as prayed for .
Decision with reasons
Point Nos. 1 & 2 : Both points are taken up for comprehensive discussion and decision . The complainant has claimed that his father was the co-owner of a piece of land having premises no. 149/3, Beharam Chatterjee Road, and after his demise the complainant along with his mother and younger brother became the co-owner of the undivided proportionate share of the said premises.
Tax invoice generated by Kolkata Municipal Corporation supports that Shanti Rani Biswas ( OP =No.2 herein) Arup Biswas , Dipanwita Halder, Santa Roy Chowdhury are the joint owners of the said piece of land. Death Certificate of Arup Biswas shows that said Arup Biswas (father of the complainant ) died on 7.6.2016 and being the legal heir of said Arup Biswas the complainant along with his mother namely Sonali Biswas and younger brother namely Swarup Biswas became then owner of the said premises by way of inheritance. The complainant has claimed that he applied for a new electric connection on 9.11.2017 and the same was rejected by the OP /CESC on 13.11.2017. It appears from letter dt. 13.11.2017 issued by District Engineer, South West District to the complainant that in response to the application filed by the complainant on 9.11.2017 an inspection was carried out and the OP found that the premises had already been provided with electricity connection. The complainant has further stated that since on 8.3.2018 he applied again for providing a new electricity connection he was provided with estimated cost for installation of new meter but on 10.3.2018 he was informed that more than one application at the said premises in favour of the complainant were under process. Letter dt. 8.3.2018, Provisional Demand Notice, letter dt. 10. 3.2018 issued and generated from the end of the OP No.1 supports such averment of the complainant.
It appears from documents on record that the application dt. 09.11.2017 submitted by the complaint for obtaining new connection was rejected and thereafter the complainant filed another application on 08.03.2018.
The OP alleged that the new connection was asked to be provided only to split load. However, no document has been filed by OP in support of such averment. Moreover, the complainant by swearing affidavit has stated in his petition of complaint as well as in evidence that due to some disputes regarding consumption of electricity from the existing meter stands in the name of OP no.2 and continuous threatening to disconnect the said connection from the end of the OP no.2 the complainant compelled to submit application for obtaining new connection. It is also observed that the OP No.1 did not cross-examined the evidence of the complainant and did not file any reply against questionnaire of the complaint which suggests that there was nothing to contradict in the evidence of the complainant and nothing to state against questionnaire advanced by the complainant.
In such view of the matter, we are inclined to hold that the complainant is entitled to get relief in respect of installation of new meter after completion of all formalities.
Regarding prayer to direct the OP No.2 to render all assistance to the OP No.1 at the time of installation of new meter. Considering the circumstances, we are inclined to direct the OP No.2 not to create any obstruction at the time of installation of new meter . Regarding prayer for compensation , we do not find any ground to allow the same.
However, the OP No.1 compelled the complenant to file the instant case and, therefore, they are liable to pay litigation cost.
Point Nos. 1 & 2 are decided.
Hence,
Ordered
That CC/162/2018 is allowed on contest against OP No.1 with cost and exparte against the OP No.2.
OP No.1 is directed to install new meter in favour of the complainant at the scheduled premises mentioned in the petition of complaint within two months from the date of this order and the OP No.2 is directed not to create any obstruction at the time of installation of new meter. OP No.1 is further directed to pay Rs. 5,000/- towards cost of litigation within the above-mentioned period.