Col. Rajinder Singh filed a consumer case on 16 May 2024 against Taneja Developers & Infrastructure Ltd. in the StateCommission Consumer Court. The case no is CC/27/2012 and the judgment uploaded on 16 May 2024.
STATE CONSUMER DISPUTES REDRESSAL COMMISSION,
U.T., CHANDIGARH
Complaint case No. | : | 27 of 2012 |
Date of Institution | : | 09.05.2012 |
Date of Decision | : | 16.05.2024 |
Col. Rajinder Singh, Aged about 54 years son of Sh. Iqbal Singh, resident of House No.1607 (HIG), Phase 9, Mohali, Punjab.
...Complainant
Versus
…..Opposite Parties
BEFORE: JUSTICE RAJ SHEKHAR ATTRI, PRESIDENT
MR. RAJESH K. ARYA, MEMBER
Present:- Sh.Amit Mahajan, Advocate for the complainant alongwith complainant in person.
Sh.Puneet Tuli, Advocate for the opposite parties.
JUSTICE RAJ SHEKHAR ATTRI, PRESIDENT
PRELUDE:-
This case involves an Ex-Army Officer, who is a Kargil War veteran, embroiled in a prolonged litigation over the possession of a plot he purchased in the project of the opposite parties, in resale. The dispute has spanned over a decade and seen multiple legal proceedings. Earlier, on 18.05.2011, the complainant had filed consumer complaint bearing no.214 of 2011 before the District Consumer Disputes Redressal Forum-II, U.T., Chandigarh (now District Commission), seeking possession of the plot in question, which was dismissed by it vide order dated 30.03.2012 for want of pecuniary jurisdiction. Thereafter, the complainant filed this complaint before this Commission on 09.05.2012, which was dismissed by this Commission vide order dated 06.11.2012. Feeling aggrieved against the order dated 06.11.2012, the complainant preferred First Appeal No.69 of 2013 before the Hon’ble National Commission, wherein, vide order dated 11.03.2019, the case has been remanded back to this Commission for deciding this consumer complaint afresh, after giving an opportunity to the parties to produce additional documents including the allotment letter if any, issued to Mr. Pradeep Kumar Gupta and Mr. Sanjeev Maheshwari and the demand letters, if any, issued to the complainant by the opposite parties, from time to time. Thereafter, this Commission vide order dated 15.01.2020 directed the opposite parties to furnish following information:-
The said order dated 15.01.2020 was also challenged by the opposite parties by way of filing First Appeal No.149 of 2020, wherein the Hon’ble National Commission vide order dated 27.01.2020 held that this Commission shall not pass final order in the consumer complaint pending before it and there shall be an ad-interim stay of the impugned order dated 15.1.2020, though this Commission could proceed with the consumer complaint in terms of the order of this Commission dated 11.3.2019. Accordingly, this Commission has proceeded with this consumer complaint in terms of order dated 11.03.2019 passed by the Hon’ble National Commission
Other facts of the case:-
At the time of Booking | 20% | |
2 Month from the date of launch | 10% | |
4 Month from the date of launch | 10% | |
6 Month from the date of launch | 10% | |
8 Month from the date of launch | 10% | |
10 Month from the date of launch | 10% | |
12 Month from the date of launch | 10% | |
14 Month from the date of launch | 10% | |
At the time of offer of possession | 10% |
“………Subject:- Intimation regarding due payment.
Dear Sir(s)/Madam,
Pursuant to your Advance Registration Form for allotment of a Residential Plot in our future township Project, we offered you a Residential Plot of 250 sq. yd. in our project TDI CITY MOHALI, Punjab on Chandigarh - Kharar road (Ν.Μ.-21)
The said offer stipulates Schedule of Payments. Time being the essence of payments, you were bound by the terms of the same by making timely payments.
An amount of Rs.2,06,250.00 (Rupees Two Lakh Six Thousand Two Hundred Fifty only) is due against tentative E.D.C. i.e. 1650/- per sq. yd. on your plot.
You are requested to make payment of above said amount within 10 days of date of this letter.
Further this is to remind you that an amount of Rs.1,62,500.00 (Rupees One Lakh Sixty two Thousand Five Hundred only) is due on 22nd May 2008 against your plot as next installment.
Thanking you, assuring you of our best services at all times.
Note (You may ignore this letter, in case you have already paid the above said amount.)
Yours faithfully,
for TANEJA DEVELOPERS & INFRASTRUCTURE LTD.
(Authorised Signatory)…..”
Written version of the opposite parties:-
Evidence of the parties:-
Observations/findings of this Commission:-
Pecuniary Jurisdiction:-
“….17. Jurisdiction of the State Commission.—(1) Subject to the other provisions of this Act, the State Commission shall have jurisdiction— (a) to entertain— (i) complaints where the value of the goods or services and compensation, if any, claimed exceeds rupees twenty lakhs but does not exceed rupees one crore; and..”
In the present case, the complainant has sought directions to the opposite parties to deliver possession of the plot in question value whereof is Rs.16,25,000/- over and above compensation to the tune of Rs.5 lacs. As such, if we add the value of the goods and also the compensation claimed, it exceeds Rs.20 lacs but does not exceed rupees one crore. In this view of the matter, this Commission has pecuniary jurisdiction to entertain and decide this complaint. As such, objection taken by the opposite parties in this regard stands rejected.
Complainant is a consumer:-
Territorial Jurisdiction:-
“(2) A complaint shall be instituted in a State Commission within the limits of whose jurisdiction,—
(a) the opposite party or each of the opposite parties, where there are more than one, at the time of the institution of the complaint, actually and voluntarily resides or carries on business or has a branch office or personally works for gain; or
(b) any of the opposite parties, where there are more than one, at the time of the institution of the complaint, actually and voluntarily resides, or carries on business or has a branch office or personally works for gain, provided that in such case either the permission of the State Commission is given or the opposite parties who do not reside or carry on business or have a branch office or personally work for gain, as the case may be, acquiesce in such institution; or
(c) the cause of action, wholly or in part, arises…”
It may be stated here that perusal of following documents reveals that the same have been issued by the opposite parties from their Chandigarh Regional Office i.e. SCO No.1098-1099, 1st Floor, Sector 22-B, Chandigarh:-
Under above circumstances, it can easily be said that the opposite parties were having their Regional Office at Chandigarh, where they have received payments from the complainant and his predecessor, as such, this Commission has territorial jurisdiction to entertain and decide this complaint in view of the provisions of Section 17 (a) to (c) to the CPA 1986. As such, objection of territorial jurisdiction taken by the opposite parties being devoid of merit, stands rejected.
Cancellation of plot by the opposite parties:-
At the time of Booking | 20% | |
2 Month from the date of launch | 10% | |
4 Month from the date of launch | 10% | |
6 Month from the date of launch | 10% | |
Month from the date of launch | 10% | |
10 Month from the date of launch | 10% | |
12 Month from the date of launch | 10% | |
14 Month from the date of launch | 10% | |
At the time of offer of possession | 10% |
In the Schedule-1 of this payment plan, it is mentioned that that booking amount for the plot in question measuring 250 square is Rs.3 lacs, which amount admittedly stood received by the opposite parties from predecessor of the complainant vide cheques dated 03.06.2005 as acknowledged by them in the application form, Annexure R-1 itself.
It is further coming out from para no.(a) of the said application form that the opposite parties committed to issue offer of allotment letter for the plot in question within a period of six months i.e. on or before 02.12.2005. Relevant part of the said application is reproduced hereunder:-
“..(a) That your offer of allotment of a residential plot in your future scheme shall be made to you on or after 6 months of my registration application made herein..”
Thus, after making payment of booking/registration amount of the plot in question, the next amount to the extent of 10% of the sale consideration was payable at the time of launching the project in question and allotment of residential plot therein. It is significant to mention here that though the opposite parties have stated in para no.2 of their preliminary objection that they made offer of allotment letter of plot in the said project to the predecessor of the complainant, yet, no evidence in this regard has been placed on record. This fact also stood noted by the Hon’ble National Commission in the order dated 11.03.2019 having been passed in FA No.69 of 2013 titled as Col. Rajinder Singh Vs M/s Taneja Developers and Infrastructure Ltd. which had been filed by the complainant/appellant against the order dated 06.11.2012 passed by this Commission, whereby this complaint had been dismissed. The Hon’ble National Commission in its order dated 11.03.2019 has clearly held that no evidence has been led by the parties to prove the date on which the project in question wherein the plot is situated, was launched. It was further observed by the Hon’ble National Commission that though the opposite parties have contended that they had issued allotment letter to the predecessor-in-interest of the complainant as is stated in the written version filed before the State Commission, yet, no copy of the said allotment letter seems to have been placed before the State Commission. As such, it was ultimately held by the Hon’ble National Commission that the project can be said to have been launched latest by the date on which the allotment letter was allegedly issued to the predecessor-in-interest of the complainant and therefore, it would be necessary to consider the allotment letter issued, in order to find out by which date the complainant was required to pay the installments stipulated in the registration form and then decide whether there was any default on his part in making payment to the respondent or not. As such, the case was remanded back to this Commission with the specific directions to decide this complaint afresh, after giving due opportunities to the parties to produce additional documents including the said allotment letter, if any, issued by the opposite parties to either the complainant or his predecessor. Relevant part of the order of the Hon’ble National Commission is reproduced hereunder:-
“…..Two persons namely Pradeep Kumar Gupta and Mr. Sanjeev Maheshwari had registered with the respondent for allotment of a plot admeasuring 250 sq. yards, paying a sum of Rs.3 lacs to the respondent.
2. The payment plan given in Schedule-1 annexed to the registration form reads as under:
3. It would thus be seen that the registrant was required to pay 20% of the sale consideration at the time of booking. Since the basic price of the plot was Rs.16,25,000/-, as is evident from Schedule-1 annexed to the registration form, the basic per sq. yard price being Rs.6,500/- and the size of the plot being 250 sq. yards, about Rs.3,25,000/- was payable at the time of registration itself. The registrant Mr. Pradeep Kumar Gupta and Mr. Sanjeev Maheshwari had paid Rs.3 lacs and the remaining booking amount of Rs.25,000/- was obviously not insisted by the respondent. The rest of the payment was linked with the date of launch and 90% of the payment was to be made within 14 months from the date of launch. The balance 10% was payable at the time of offer of possession.
4. No evidence has been led by the parties before the State Commission to prove the date on which the project in which a plot is alleged to have been allotted to the predecessor-in-interest of the complainant was launched. The learned counsel for the respondent points out that they had issued allotment letter to the predecessor-in-interest of the complainant as is stated in the written version filed before the State Commission. However, no copy of the said allotment letter seems to have been placed before the State Commission. Only three documents were made annexures to the written version and none of them was the letter of allotment issued to the predecessor-in-interest of the complainant. However, I am in agreement with the learned counsel for the respondent that the project can be said to have been launched latest by the date on which the allotment letter was allegedly issued to the predecessor-in-interest of the complainant. Therefore, it would be necessary to consider the allotment letter issued by the respondent to the predecessor-in-interest of the complainant in order to find out by which date the complainant was required to pay the installments stipulated in the registration form and then decide whether there was any default on his part in making payment to the respondent or not.
5. The learned counsel for the respondent submits that while seeking transfer of the registration in his name, the complainant had submitted several documents for transfer of registration of plot no. MPP-Temp. 19693 in his name. It would be necessary to examine the allotment letter, if any, issued to the predecessor-in-interest of the complainant to find out whether any particular plot was allotted to him by the respondent or not.
6. For the reasons stated hereinabove, the impugned order is set aside and the matter is remitted back to the State Commission for deciding the complaint afresh after giving an opportunity to the parties to produce additional documents including the allotment letter if any, issued to Mr. Pradeep Kumar Gupta and Mr. Sanjeev Maheshwari and the demand letters, if any, issued to the complainant by the respondent from time to time.
7. The parties are directed to appear before the concerned State Commission on 15.04.2019. The additional documents in terms of the liberty granted to the parties, shall be filed before the State Commission within four weeks from today. The State Commission shall decide the complaint afresh within three months of the parties appearing before it.
8. During the course of hearing today in the Court, the learned counsel for the respondents, on instructions, had offered to refund the entire amount received from the complainant with reasonable interest but the said offer was not acceptable to the complainant who wants possession of the plot alongwith compensation…”
Thus, from the order dated 11.03.2019, it is clearly coming out that default if any, on the part of the complainant in making payment of installments, referred to above, could have been established, only in case, it is found that the project has been launched, after the opposite parties have issued offer of allotment letter to the predecessor of the complainant or in favour of the complainant.
It is significant to mention here that after remand of this case, there were ample opportunities available with the opposite parties to place on record the offer of allotment letter in respect of the plot in question, had the same been issued to the predecessor of the complainant or in favour of the complainant but they miserably failed to do so. Under these circumstances, an adverse inference could easily be drawn against the opposite parties that by the date, when the plot in question was cancelled on 06.08.2009 or even thereafter, the opposite parties never issued any offer of allotment letter. Thus, once the project in question was not launched by the opposite parties in the year 2008 as no offer of allotment letter was issued by them, which they had committed in para no.(a) of their application within a period of 6 months from the date of registration of the said application, it cannot be said that there was any default on the part of the complainant in making payment to the opposite parties, which was demanded by them vide letter dated 26.04.2008.
Thus, it is coming out from the record that by 01.06.2009, the opposite parties have already received substantial amount from the complainant, yet, there is nothing on record that they complied with condition of para no.(a) of the application form, qua issuance of offer of allotment letter in respect of a plot in the said project or that buyer’s agreement was ever sent to the complainant for its execution, thereby, violating the provisions of Section 6 of the PAPR Act, which lays a duty on the opposite party to execute the agreements for sale as per law, after obtaining the maximum sale consideration of 25%.
As far as payment of Rs.80,000/- by the complainant as depicted in receipt Annexure C-1 is concerned, it may be stated here that the opposite parties have disputed the receipt of this amount. We have also gone through the said receipt, Annexure C-1 and did not find any endorsement of company in the shape of its stamp, receiving the said amount. As such, in the absence of any cogent evidence, it cannot be accepted that the amount of Rs.80,000/- has been received by the opposite parties, from the complainant. Under these circumstances, it is open to the complainant to prove this payment of Rs.80,000/- to the opposite parties, after adopting other legal remedy available to him, under the law.
“…..v) He would not undertake any development work in the colony until notification under Section 44 of PAPRA, 1995 is issued. Chief Town Planner, Punjab/Nodal Agency would ensure before passing the final lay out plan of the proposed project that the site of the promoter is compact and contiguous.
xi) The promoter would not launch booking of plots and issue any advertisement in this regard, until the final approval is obtained from the Competent Authority….”
Furthermore, as per clause (ii) of letter dated 21.12.2005, Annexure C-18 (Grant of Special Package of Incentives), having been issued by the Director of Industries and Commerce, Punjab, Chandigarh, it was made clear to the opposite parties that the project shall not be advertised, launched and no money will be collected from general public for allotmentof land/plot/flat etc. till the time layout and zoning plans are cleared from the competent Authorities. Relevant part of the said clause (ii) is reproduced below:-
“……In case of land falling under Periphery Control Area, any land use change shall only be allowed in accordance with the Periphery Policy of the State Government and in accordance with the draft Zoning / Layout Plan and Master Plan of the area. The project shall not be advertised / launched and no money will be collected from general public for allotment of land / plot/flat/ any space till such time the layout / zoning plans are cleared from the competent authority.……”
Compensation for the period of delay:-
Limitation:-
Pronounced
16.05.2024
[JUSTICE RAJ SHEKHAR ATTRI]
PRESIDENT
(RAJESH K. ARYA)
MEMBER
Rg.
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.