BEFORE THE CONSUMER DISPUTES REDRESSAL FORUM, IDUKKI Dated this the 26th day of June, 2009 Present: SRI.LAIJU RAMAKRISHNAN PRESIDENT SMT.SHEELA JACOB MEMBER SMT.BINDU SOMAN MEMBER
C.C No.32/2009 Between Complainant : C.N.Sankar S/o Narayanan Chelaplackal House, Upputhodu Kara, Upputhodu P.O. (By Adv: Sibi Thomas) And Opposite Parties : 1. Tahsildar, Devikulam. 2. Village Officer, Mankulam Village Office Mankulam P.O. O R D E R
SRI.LAIJU RAMAKRISHNAN(PRESIDENT)
Complainant appeared through counsel. Opposite party appeared directly. Opposite parties are ready for settlement, if the complainant files an application before the 1st opposit party at the opposit parties office, 4 months time is needed for opposite party for conducting mutation for the property of the complainant because, the relevant documents from the Superintendent of Survey is needed for the same. Complainant also agreed. Hence the petition closed with a direction to the complainant to produce all the relevant documents before the opposit parties office and apply for mutation. Opposit party is directed to consider the same and mutation must be done within 4 months.
Hence the petition dismissed.
Pronounced in the Open Forum on this the 26th day of June, 2009.
Sd/- SRI.LAIJU RAMAKRISHNAN(PRESIDENT) Sd/- SMT.SHEELA JACOB(MEMBER) Sd/- SMT. BINDU SOMAN(MEMBER)
| HONORABLE Sheela Jacob, Member | HONORABLE Laiju Ramakrishnan, PRESIDENT | HONORABLE Bindu Soman, Member | |