View 7534 Cases Against Electricity
Amiya Panja filed a consumer case on 18 Sep 2023 against Station Manager, Indus Group Electricity Supply, WBSEDCL, Indus, P.O. & P.S. - Indus, Dist. Bankura, in the Bankura Consumer Court. The case no is CC/52/2015 and the judgment uploaded on 19 Sep 2023.
IN THE DISTRICT CONSUMER DISPUTES REDRESSAL COMMISSION, BANKURA
Consumer Complaint No.52/2015
Date of Filing: 12/05/2015
Before:
1. Samiran Dutta Ld. President.
2. Rina Mukherjee Ld. Member.
3. Siddhartha Sankar Bhui Ld. Member.
For the Complainant:Ld. Advocate, Mahiuddin Ahmed
For the O.P: Ld. Advocate Jayanta Chowdhury
Complainant:
Amiya Panja, S/o Late Mahitosh Panja, Vill-Barul, P.O.Roll, P.S.Indas, District-Bankura
Opposite Party:
Station Manager, Indas Gr. Electric Supply, WBSEDCL, Indas, Bankura
FINAL ORDER / JUDGEMENT
Order No.48
Dated:18-09-2023
Both parties file hazira through Advocate.
The case is fixed for argument.
After hearing argument from both sides the Commission proceeds to dispose of the case as hereunder: -
The Complainant’s case is that he being a small farmer applied for electric connection to his submersible pump for cultivation purpose on 30/03/2010 on payment of earnest money of Rs.1,000/- and thereafter the Complainant paid Rs.46,217/- to the O.P. on 23/12/2010 as quotation money but the O.P. has still failed to install electric connection to the Complainant as applied for. The Complainant has therefore approached this Commission for appropriate relief.
O.P. contested the case by filing a written version contending inter alia that they are ready and willing to install electric connection to the submersible pump of the Complainant subject to supply of all installation materials or costs thereof by the Complainant on Turn Key basis.
-: Decision with reasons: -
Having regard to the facts of the case, contention, submission and documents on both sides the Commission finds that the quotation dt: 27/12/2010 itself shows that service connection
Contd……p/2
Page: 2
materials are to be supplied by the consumer. According to WBSEDCL Procedure-A (2010) the consumer has to supply the cost of materials for installation of electricity which is known as Turn Key Contract but the Complainant has not complied with the same till now. So there cannot be any deficiency of service on behalf of O.P. in installation of submersible pump connection. The Complainant must supply the requisite materials or the cost thereof otherwise he will not be entitled to get the connection as applied for.
Hence it is ordered…….
That the case be and the same is disposed of on contest by directing the O.P. to install submersible pump connection to the Complainant subject to supply of materials or cost thereof under Turn Key contract within one month from the supply of requisite materials or cost thereof by the Complainant.
Both parties be supplied copy of this Order free of cost.
____________________ _________________ _________________
HON’BLE PRESIDENT HON’BLE MEMBER HON’BLE MEMBER