Sri Birendra Naik filed a consumer case on 10 Dec 2021 against Sri sudhir Dash in the Rayagada Consumer Court. The case no is CC/77/2020 and the judgment uploaded on 06 Jan 2022.
DISTRICT CONSUMER DISPUTES REDRESSAL COMMISSION, RAYAGADA,
AT: KASTURI NAGAR, Ist. LANE, L.I.C. OFFICE BACK,PO/DIST: RAYAGADA, STATE: ODISHA, PIN NO.765001,.E-mail- dcdrfrgda@gmail.com
…
C.C.CASE NO.__77_______/2020 Date. 10 .12. 2021.
P R E S E N T .
Sri Gopal Krishna Rath, President.
Smt.Padmalaya Mishra,. Member
Sri Birendra Naik, S/O: Late Sankar Prasad Naik, At: Sriram Nagar, Po/Dist:Rayagada(Odisha). …..Complainant.
Versus.
Sri Sudhir Dash, S/o: Sri SubashChandraDash,
C/O: SamparkFire& Safety Pvt. Ltd., Besides IOB, New Colony,Rayagada(Odisha)765001.…Oppositeparties.
For the Complainant:- Self.
For the O.Ps:- Sri Ram Prasad Patra , Advocate, Rayagada.
JUDGEMENT
The crux of the case is that the above named complainant alleging deficiency in service against afore mentioned O.Ps for non payment of balance amount a sum of Rs.87,000/- towards labour charges for construction of residential house for which the complainant sought for redressal of the grievances raised by the complainant. The brief facts of the case are summarized here under.
That the Opposite Party (First Party) and Complainant(Second Party) had made agreement between the parties on Dt. Ist. Day of March, 2014. The O.P. has owned a house site situated at Rohit colony, of Rayagada. The O.P. had intended to construct a RCC slabbed house at Ground & First floor over under scheduled land and the complainant had agreed to construct the houses over the same of complainant by masonry contract as per the approved plan supplied by the O.P. The complainant had agreed to build the ground and first floor houses as per the approved plan at the request of the O.P. That both the parties had agreed to execute the work at the cost of Rs.150.00 per square feet of the total slab area which includes the Stair case. The complainant had completed the work of ground floor of the house and the O.P. had not constructed the first floor. The complainant had completed all the works of the ground floor of the O.P. As per agreement the complainant was entitled Rs.87,000.00 (Rupees eighty seven thousand)only to receive from the O.P. towards labour charges for construction of house of the O.P. But till date the O.P. has not paid the above amount for some or other plea. Hence this C.C. case has filed by the complainant before this commission and prays direct the O.P to refund balance amount a sum of Rs.87,000/- towards labour charges for construction of residential house and such other relief as the District Commission deems fit and proper for the best interest of justice.
Upon Notice, the O.Ps put in their appearance and filed written version in which they refuting allegation made against them. The O.Ps taking one and another pleas in the written version sought to dismiss the complaint as it is not maintainable under the C.P. Act, The facts which are not specifically admitted may be treated as denial of the O.P. Hence the O.Ps prays the forum to dismiss the case against them to meet the ends of justice.
Heard arguments from the learned counsels for the O.P and from the complainant. Perused the record, documents, written version filed by the parties.
This commission examined the entire material on record and given a thoughtful consideration to the arguments advanced before us by the parties touching the points both on the facts as well as on law.
FINDINGS.
Undisputedly the Opposite Party (First Party) and Complainant(Second Party) had made agreement between the parties on Dt. Ist. Day of March, 2014. The O.P. has owned a house site situated at Rohit colony, of Rayagada. Again undisputedly the O.P. had intended to construct a RCC slabbed house at Ground Floor over under scheduled land and the complainant had agreed to construct the houses over the same by masonry contract as per the approved plan supplied by the O.P. Again undisputedly both the parties had agreed to execute the work at the cost of Rs.150.00 per square feet of the total slab area which includes the Stair case.
The main grievance of the complainant was that he is entitled balance amount from the O.Ps towards labour charges. Hence this C.C. case filed by the complainant to get the balance amount.
The O.Ps in their written version contended that the case is not maintainable.
The O.Ps are taking one and another pleas in the written version and sought to dismiss the complaint as it is not maintainable under the C.P. Act.
The O.Ps further has field payment details to the complainant in different dates total a sum of Rs.2,98,390.00 which are available in the file marked as Annexure-I.
It is clearly stated in the C.P. Act (Section-100 of the C.P.Act, 2019) that this Act is in addition to and not in derogation to the other statutes in force and as such the petition filed by the complainant is a consumer dispute and this District Commission can entertain the said petition.
it is held and reported in SCC 1994 (1) page No. 243 in the case of Lucknow Development authority Vrs. M.K.Gupta where in the Hon’ble Apex Court observed “Consumer and Service under the C.P. Act, 1986 that the provisions of the Act must be liberally interpreted in favour of the consumers as the enactment in question was beneficial piece of legislation while examining the meaning of the term Consumer and service.”
It is the settled principle of law that the statutory authority should act under the provisions of the relevant statute and if they do not act accordingly, Consumer Commission have the jurisdiction because not acting under the provisions of the statute/Act and it amounts to deficiency of service.
Further if any authority is not acting under the provisions of the Act or is acting beyond the scope of the Act, then certainly that will be deficiency of service.
The complainant during the course of hearing submitted that the O.P had done extra works of residential building but no labour payment has been paid to the complainant inspite of repeated contact to the O.Ps.
That for failure to act properly by the O.P. the complainant should not be deprived of his benefits legitmate entitlement. It is to be ensured that the benefits to which the complainant is eligible are entitled to enjoy it and it should not became a distant dream.
As this is a welfare legislation this district commission feel it justifiable if the O.P. to consider for payment of balance outstanding amount to the complainant if any. In our considered opinion to avoid misunderstanding between the parties this District Commission instructed they should sit together in friendly and befitting manner and to discuss about if any lapses or hindrances are there, that should be amicable settled and to settle the final account towards extra works done by the complainant for construction of residential house of the O.Ps.
To meet the ends of justice the following order is passed.
ORDER.
In resultant the complaint petition is allowed in part
The O.P. is directed to settle the account matter of the complainant and if any amount is entitle be paid to the complainant and compliance report be submitted to this Commission within 15 days from the date of receipt of this order. Parties are left to bear their own cost.
Copies be served on the parties as per rule.
Dictated and corrected by me.
Pronounced on this 10th. Day of December, 2021.
Member. President
:-
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.