Assam

Cachar

CC/35/2020

Sri Promotesh Dey - Complainant(s)

Versus

Sri Niloy Paul, Siclhar - Opp.Party(s)

Sri Debabrata Deb

21 Mar 2023

ORDER

Heading1
Heading2
 
Complaint Case No. CC/35/2020
( Date of Filing : 17 Nov 2020 )
 
1. Sri Promotesh Dey
Ambicapatty, Silchar
Cachar
Assam
...........Complainant(s)
Versus
1. Sri Niloy Paul, Siclhar
N.S Avenue, Silchar
Cachar
Assam
2. Sri Amal Mazumder
Badarpur
Karimganj
Assam
3. Smt. Swapna Majumder
Ambicapatty, Silchar
Cachar
Assam
............Opp.Party(s)
 
BEFORE: 
 HON'BLE MR. JUSTICE Sri Samarjit Dey PRESIDENT
  Kamal Kumar Sarda MEMBER
  Deepanita Goswami MEMBER
 
PRESENT:Sri Debabrata Deb, Advocate for the Complainant 1
 
Dated : 21 Mar 2023
Final Order / Judgement

CONSUMER  CASE  No.- 35/2020

JUDGMENT   AND   ORDER 

                                         

                                           The case of complainant  Sri  Promotesh  Dey, in brief, is that  the Proforma   O.P.  No. 2 namely Sri Amal Mazumder  and O.P. no.-3 Smt. Swapna  Mazumder  are the absolute owner in possession in respect  of a plot of land  measuring 07 kata 13 chatak covered by 2nd  R.S.  Patta  No.463,  Dag no. 3494,  Mouza-  Silchar town, pargona- Barakpar  situated at  Kurmi Bungalow Road,  Ambicapatty,  Silchar.  On the said plot of land   Principal   O.P.  No.-1 namely  Sri  Niloy Paul  as promoter/builder   by virtue of power of Attorney   constructed  residential apartment  flats   and the same was named as  ‘  PEARL  HEIGHTS’ . The complainant purchased a residential flat  measuring  more or less 850  sq. ft.   inclusive of  152  sq. ft. common area services  etc. being flat no.- 3-C  in the  3rd  floor of  the  aforesaid  ‘PEARL  HEIGHTS’.   Apartment   with proportionate share of land  249.75  sq.  ft. out of schedule-1  land   by a registered sale deed no.-5219 dated  24/09/2019  by paying consideration amount of Rs.8,50,000/-  only.  That as per  terms and conditions of  the  agreement for sale executed on  18/04/2018  between the complainant and  Principal  Opposite Party  No.-1  Sri  Niloy Paul  , the  O.P.  No.-1 has agreed to provide  all common facilities  i.e.,  generator, transformer, lift, staircase, passage, drainage etc. and undertook to complete the building construction by using and fitting good quality products and in standard manner.  But  , it has been alleged by the complainant  that,  the construction works of the flat/apartment  have been done  in non-standard manner with several defects violating the terms and conditions  of  agreement.   As a result, according to the complainant,  they have been suffering  various problems and also they have occurred huge financial  loss.  It has been further alleged  that  due to non-standard works  of the  construction of  building the wall plaster in both inside and outside of the flat, and also ceiling plaster have  become cracked.   That the sanitary tank in the basement of the apartment was made without provision of soak pit and sanitary tank pipe is connected with open drain  causing  bad smelling and unhygenic  condition.  Further allegation of the complainant is that  due to  non-construction of western side wall of the basement  area  rain water frequently enters in the parking area and  common  passage.  That the common entrance path  of the apartment does not remain fit for use in the rainy days.  There is also  no proper ventilation system in the car parking/ basement area.  That the  roof of the lift is also  not covered by quality  CI   sheet.  According to the complainant,    though several times they requested the  O.P.  No.-1  and issued notice  but the  O.P.  No.-1  neglected to provide the required facilities as per agreed terms  thus causing disservice  towards  them.  Under the circumstances, the complainant has prayed for   directing  the  O.P.  No.-1  to repair  all broken/cracked walls  of the complainant’s  flat  both outside and inside and to paint the same,  to rectify all  electrical faulty works  of the apartment of the complainant by  replacing all defective electric fittings,  to remove the deficiencies whatsoever by making common drainage system so that the complainant and other occupants  may not face any difficulties for stagnant water,  to install a common generator,  to construct a soak- pit  and connect the sanitary tank’s pipe with the soak-pit to stop bad smell,  to provide a  RCC  hume pipe measuring 12’  diameter in the approach,  to provide  CC  Block in the approach of the apartment,  to cover the  roof of the lift  by   quality  CI  sheet,  to  construct   the western side  wall  in order to stop the passage of outside water in the basement area,  to  provide  proper ventilation in basement/ car parking space.  In addition the complainant has prayed for awarding compensation against the  O.P.  No.-1  including  compensation of Rs. 1,80,000/-  only  for deficiency in service,  compensation of Rs. 80,000/- only for mental harassment and anxieties,  compensation of an amount of Rs. 40,000/-  towards  legal expenses  etc.                                               

                                                The  Principal  Opposite Party No.-1  Sri  Niloy Paul  has submitted written statement stating , interalia, that there is no reason or justification   to file this case, that the complaint is not maintainable, that the complaint is barred by limitation   etc. etc.  The answering  O.P.  has denied all the allegations levelled against him.  The case of  Principal  O.P.  no.-1  is that  the  O.P.  No.-1 is engaged in the business of promotion and development of land by construction  of  building.  That  the answering  O.P. no.-1  entered into an agreement registered vide no. 3767 dated  06-08-2014/12-08-2014  for construction of multistoried building over a plot of land  measuring  07 katha  13  chatak  bearing  holding  no. 249 of ward  no.- 25  of Silchar  Municipal  Board.  In accordance with the agreement  the  proforma  O.P. executed the power of Attorney  empowering  the  answering  O.P.  No.-1 to construct the building.  The answering  O.P.  obtained construction permission  from  SDA, Silchar and accordingly constructed the building  and  the building was named as  ‘ PEARL  HEIGHTS’ .  It is stated  that the  complainant  offered to purchase  one  flat measuring 852  sq.  ft (approx)  inclusive of  152  sq.  ft. common  area  services  etc.  being flat no.- C  in the third floor of the  ‘ PEARL  HEIGHTS’   with proportionate share of land for consideration amount of Rs.8,50,000/- .  According to the answering  O.P. ,   on being satisfied with the construction,  facilities provided in  the building including the drainage system,  septic tank, soak pit, pipe line, common corridors and other facility  the complainant  purchased the concerned flat.  It  has been further  stated that  the generator  could not be provided as all the occupants of the building have not made any payment for the generator.   Further version of  the answering  O.P.  is  that  the  complainant  having purchased the flat  happily residing there  by maintaining  the  common services   alongwith other occupants of the building.  As such  it is stated that the  answering  O.P.  no.-1  has not caused any disservice  to the complainant.   The complainant   and  other  occupants are  actually responsible  for any damage if at all has occurred  regarding    common  areas and services of the building.  Under the circumstances  it is prayed for dismissal of the complaint .

                                                    In support of the case  complainant  Sri  Promotesh  Dey  submitted  his  evidence on affidavit  as  PW-1    and  exhibited some documents.   On  the other hand,  from the side of  Opposite  Party  No.-1   evidence on affidavit  of  Sri  Niloy  Paul   has  been  submitted   as  DW-1 and  also some documents have been exhibited.    Thereafter  both  sides  have also submitted written argument in addition of oral argument put forward at length by the learned counsels of  the  respective  parties.  Perused  the  entire evidence on record.  Let us  now appreciate the evidence below.

                                                   In his evidence as PW-1  the complainant has  reiterated the same facts as stated in the complaint petition.  It has been stated by  PW-1  that  the  the Proforma  O.P.  Nos. 2 &  3   are  absolute owner  of a plot of land  measuring 07 kata 13 chatak covered by 2nd  R.S.  Patta  No.463,  Dag no. 3494,  Mouza-  Silchar town, pargona- Barakpar  situated at  Kurmi Bungalow Road,  Ambicapatty,  Silchar.  On the said plot of land  the  Principal  O.P.  No.-1  Sri  Niloy Paul  as promoter   constructed  residential apartment  flats   and the same was named as  ‘  PEARL  HEIGHTS’ .  Further version of PW-1  is that  he purchased a residential flat from  O.P.  No.-1  measuring  850  sq. ft.   inclusive of 152 sq. ft. common  area  services  etc. being flat no.- 3-C  in the  3rd  floor  of  aforesaid  ‘PEARL  HEIGHTS’   apartment   with proportionate share of land 249.75  sq.  ft.    out of  schedule-1  land  by a registered sale deed no.-5219  dated  24/09/2019  by  paying consideration amount of Rs.8,50,000/-  only.   According to PW-1,   as per  terms and conditions of the  agreement for sale executed between  himself  and  O.P.  No.-1  Sri  Niloy Paul  , the  Principal  O.P.  No.-1 has agreed to provide  all common facilities  i.e.,  generator, transformer, lift, staircase, passage, drainage etc. and undertook to complete the building construction by using and fitting good quality products and in standard manner.  But  , it has been alleged by  PW-1  that,  the construction works of the flat/apartment  have been done  in non-standard manner with several defects violating the terms and conditions  of  the  agreement.   As a result, according to the complainant,  they have been suffering  various problems and also they have incurred huge financial loss.  That  the wall plaster in both inside and outside of the flat, and also ceiling plaster have  become cracked,   the sanitary tank in the basement of the apartment was made without provision of soak pit and sanitary tank pipe is connected with open drain  causing  bad smelling and unhygenic  condition.  Further allegation of  PW-1  is that  due to  non-construction of western side wall of the basement  area  rain water frequently enters in the parking area and  common  passage.  That the common entrance path  of the apartment does not remain fit for use in the rainy days.  There is no provision  to pass water  from the basement area   and  also  there is no proper ventilation system in the car parking/ basement area.  That the  roof of the lift is   not covered by quality  CI   sheet.    According to  PW-1,  though several times they requested the  O.P.  No.-1  and issued notice  but the  O.P.  No.-1  neglected to provide the required facilities as per agreed terms  thus causing disservice  towards  them. 

                                                   On the other hand,  from the evidence of DW-1  i.e.,  the Principal  O.P.  No.-1  it reveals that  it is not in dispute that the  O.P.  No.-1  as promoter of the land constructed  the  alleged  building  ‘PEARL  HIGHTS’  and   a flat  no.-3-C   in the 3rd floor of the said building measuring  852 sq. ft.(approx) inclusive of  152  sq. ft. common area services  was purchased by the complainant  by a registered sale deed.    According to DW-1, the complainant purchased the flat on being satisfied with the construction,  facilities provided in  the building including the drainage system,  septic tank, soak pit, pipe line, common corridors and other facility.  After the flat was handed over the complainant and other occupants have been maintaining the common services in the  building.  It is stated that the  generator could not be provided as all the occupants of the building did not make payment for the  same.

                                            PW-1  has averred that  due to non-standard works of the building the wall plaster both inside and outside of his flat and also ceiling plaster have become cracked.  The   sanitary tank in the basement of the apartment was made without provision of soak-pit and sanitary tank pipe is connected with open drain causing foul and bad smell as well as creating  unhygenic condition.  PW-1  has further alleged that  in the basement  due  to  non-construction of  western side wall by the  Principal  O.P.  No.-1  rain water enters in the basement and car parking areas causing problem.   Further allegation of PW-1  is that  there is no proper ventilation system in the car parking/ basement area. But the  submission  of  DW-1  is that   the complainant  i.e.,  PW-1  purchased his flat on being satisfied with the construction and facilities provided in the  flat  as well as in the common areas including the drainage system, septic tank, soak pit, pipe line  etc.  It reveals from the case record that  the concerned flat was purchased by the complainant on 23rd day of  September’2019  and the instant case was filed by the complainant  in the month of  November’2020.  So  the  appearance  of crack  in the wall plaster of the flat of the complainant within this short period clearly shows the fact that  some works  of the flat were below standard and for that, according to  us,  the  O.P.  No-1  is bound to compensate.  It  may be mentioned here that  three other flat owners of the same building lodged complaints alleging in respect of the concerned flat  as well as  complaints in respect of the common areas facilities of the building.  The   xerox copy of the photo of the drain   of the building shows  its horrible condition.There is no ground for us to disbelieve the   allegation that  the   sanitary tank in the basement of the apartment was made without provision of soak-pit and  the open drain causing  of the building causing bad smell as well as unhygienic condition.  Both the allegations appear to be serious since  those are  polluting the environment of the  Apartment and its adjoining areas  and on the other hand  these are making the Apartment/building  inhabitable.   Another allegation  is that  due  to  non-construction of  western side wall by the  Principal  O.P.  No.-1  rain water enters in the basement and car parking areas causing problem.   During the course of argument it has been admitted  by the  O.P.  side that  construction of western side wall is pending.  Another allegation of PW-1  is that  there is no proper ventilation system in the car parking/ basement area.   There is also no specific denial of this fact  by the   O.P.    So  we are of the clear opinion that the Principal O.P.  i.e., the Promoter who sold the  flats to the Purchasers  is  bound to   meet  up the  allegations/demands  of  the  complainant. 

                                  In his evidence  PW-1   has  further contended that   the O.P.  no.-1  agreed to provide  generator for the use of flat owners.  But  the version of  DW-1 is that  as all the occupants of the building did not make payment for the generator so the  generator  could not be provided.  On the other hand    Ext. -1,  the copy  of  sale deed of the flat of the complainant  contains  no  whisper in  respect of  any  generator  the  builder  agreed to provide in the building for common use.  There is also no evidence in the case  from the side of the complainant  that   he  and other flat owners  paid their  respective contribution for the generator.    

                                             PW-1  has further alleged that  the roof of the lift is not covered  by quality  C.I.  sheet  and the common entrance path of the apartment is also not fit for use in rainy days.  Though the   O.P.  No.-1   has  denied the said facts  but    the  case  record shows that   the Society of the building  i.e.,  ‘Pearl  Heights’  in their  meeting held on  02/08/2020  took resolution  regarding  such  drawbacks/faulty works  in the  building and flats .  It also  has been submitted by the complainant that   the president of the  Society  of  the  apartment/building   sent the demand to the  Promoter for rectification of faulty works but the promoter  did not comply.  There is also no grounds in the case to disbelieve the allegations made by the complainant.  As  such  the activities of the promoter  i.e  the principal   O.P.  No.-2  constitute negligence and disservice  towards the complainant. The  promoter  is liable to  provide essential  basic  facilities in the building and the quality of works  should not be such that within   few years  it will start deteriorating.

                                     Under the circumstances, according to  us,  the complainant  is entitled to get reliefs  in the case. However  it  may be mentioned here that  the  promoter   is not liable to  provide generator to the complainant’s  building. As  most of the allegations   regarding faulty works etc.  in the building  are for common use by all the  flat owners,  so, according to us,  it will be appropriate  to  give  reliefs  for those matters  jointly. Also  it  will  not be  out of place to mention here that  there is  reason  for filing this case  and also there is no defect  or impediment  in the case for granting reliefs

                                         Accordingly,  it is ordered that   the  principal  O.P.  No.-1  Sri  Niloy  Paul  shall   pay  to the complainant  an amount of Rs. 40,000/- ( Rupees  forty  thousand )  only  towards compensation for damages in the plaster of walls  of his flat etc.  The complainant shall utilize  the said amount  for repairing of wall plasters, for painting  and for electric repairing .  The  Principal  O.P.  No.-1 shall  further  pay an amount of Rs. 5,000/-  ( Rs. five   thousand  )  only towards cost of litigation.  The entire amount  as directed for payment  shall be payable within a period of  next  90(ninety) days else  interest @ 10% per annum would  accrue  on the entire amount from the date of judgment till realisation of the amount.  For  construction of western side boundary wall , repairing  of drains, septic tank, pipe line,  entrance path of the building, for ventilation work of the basement  etc.  related to common areas of the building  order   has been passed in    Consumer Case  No.-  34/2020.  As such, in this case no separate order has been passed  regarding construction of wall and compensation  for repairing in the common areas.

                                With the above the case stands allowed on contest  against  the principal  O.P.  No.-1  Sri  Niloy  Paul.  The judgment is pronounced  on this 21st day of  March’ 2023  under our seal and  signature.

 
 
[HON'BLE MR. JUSTICE Sri Samarjit Dey]
PRESIDENT
 
 
[ Kamal Kumar Sarda]
MEMBER
 
 
[ Deepanita Goswami]
MEMBER
 

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.