Assam

Cachar

CC/34/2020

Smti. Kabita Bahttacharjee - Complainant(s)

Versus

Sri Niloy Paul, Siclhar - Opp.Party(s)

Adv. Debabrata Deb

21 Mar 2023

ORDER

Heading1
Heading2
 
Complaint Case No. CC/34/2020
( Date of Filing : 17 Nov 2020 )
 
1. Smti. Kabita Bahttacharjee
Ambicapatty, Silchar
Cachar
Assam
...........Complainant(s)
Versus
1. Sri Niloy Paul, Siclhar
N.S.Avenue,Silchar
Cachar
Assam
2. Sri Amal Mazumder
Badarpur
Karimganj
Assam
3. Smt. Swapna Majumder
Ambicapatty, Silchar
Cachar
Assam
............Opp.Party(s)
 
BEFORE: 
 HON'BLE MR. JUSTICE Sri Samarjit Dey PRESIDENT
  Kamal Kumar Sarda MEMBER
  Deepanita Goswami MEMBER
 
PRESENT:
 
Dated : 21 Mar 2023
Final Order / Judgement

CONSUMER  CASE  No.- 34/2020

  JUDGMENT   AND   ORDER 

                                         

                                           The case of complainant Smt.  Kabita  Bhattacharjee, in brief, is that  the Proforma  O.P.  No. 2 namely Sri  Amal  Mazumder  and O.P. no.-3  Smt. Swapna  Mazumder  are the absolute owner in possession in respect  of a plot of land  measuring 07 kata 13 chatak covered by 2nd  R.S.  Patta  No.463,  Dag no. 3494,  Mouza-  Silchar town, pargona- Barakpar  situated at  Kurmi Bungalow Road,  Ambicapatty,  Silchar.  On the said plot of land   Principal  O.P.  No.-1 namely  Sri  Niloy Paul  as promoter/builder   by virtue of power of Attorney   constructed  residential apartment  flats   and the same was named as  ‘  PEARL  HEIGHTS’ .The complainant purchased a residential flat  measuring  996  sq. ft. (approx)  inclusive of 166 sq. ft. common  area  services  etc. being flat no.- 2(A) in the 2nd floor of  aforesaid  ‘PEARL  HEIGHTS’.   Apartment   with proportionate share of land 249.75  sq.  ft.   i.e.,  5(five) chatak,  11 (eleven )  Gonda  by a registered sale deed no.-140 dated  11/01/2019 by paying consideration amount of Rs.15,00,000/-  only.  That as per  terms and conditions of agreement for sale executed between the complainant and  Opposite Party  No.-1  Sri  Niloy Paul  , the  O.P.  No.-1 has agreed to provide  all common facilities  i.e.,  generator, transformer, lift, staircase, passage, drainage etc. and undertook to complete the building construction by using and fitting good quality products and in standard  manner.  But  , it has been alleged by the complainant  that,  the construction works of the flat/apartment  have been done  in non-standard manner with several defects violating the terms and conditions  of  agreement.   As a result, according to the complainant,  they have been suffering  various problems and also they have  incurred huge financial loss.  It has been further alleged  that  due to non-standard works  of the  construction of  building the wall plaster in both inside and outside of the flat, and also ceiling plaster have  become cracked.   That the sanitary tank in the basement of the apartment was made without provision of soak pit and sanitary tank pipe is connected with open drain  causing  bad smell and unhygenic  condition.  Further allegation of the complainant is that  due to  non-construction of western side wall of the basement  area  rain water frequently enters in the parking area and  common  passage.  That the common entrance path  of the apartment is not fit for use in the rainy days.  There  is  also  no proper ventilation system in the car parking/ basement area.  That the  roof of the lift is also  not covered by quality  CI   sheet.  According to the complainant  though several times they requested the  O.P.  No.-1  and issued notice  but the  O.P.  No.-1  neglected to provide the required facilities as per agreed terms  thus causing disservice  towards  them.  Under the circumstances, the complainant has prayed for   directing the  O.P.  No.-1  to repair  all broken/cracked walls  of the complainant’s  flat  both outside and inside and to paint the same,  to rectify all  electrical faulty works  of the apartment of the complainant by  replacing all defective electric fittings,  to remove the deficiencies whatsoever by making common drainage  system so that the complainant and other occupants  may not face any difficulties for stagnant water,  to install a common generator,  to construct a soak- pit  and connect the sanitary tank’s pipe with the soak-pit to stop bad smell,  to provide a  RCC  hume pipe measuring 12’  diameter in the approach,  to provide  CC  Block in the approach of the apartment,  to cover the  roof of the lift  by   quality  CI  sheet,  to  construct the western side  wall  in order to stop the passage of outside water in the basement area,  to  provide  proper ventilation in basement/ car parking space.  In addition the complainant has prayed for awarding compensation against the  O.P.  No.-1  including  compensation of Rs. 2,00,000/-  only  for deficiency in service,  compensation of Rs.25,000/- only   for late instalment of lift service,  compensation of Rs. 80,000/- only for mental harassment and anxieties  and   further  amount of Rs. 40,000/-  towards  legal expenses.

                                               The  Principal  opposite Party No.-1  Sri  Niloy Paul  has submitted written statement stating , interalia, that there is no reason or cause to file this case, that the complaint is not maintainable  etc. etc.  The answering  O.P.  has denied all the allegations levelled against him.The case of O.P.  no.-1  is that  the  O.P.  No.-1 is engaged in the business of promotion and development of land by constructing building.  The answering  O.P. no.-1  entered into an agreement registered vide no. 3767 dated  06-08-2014/12-08-2014 for construction of multistoried building over a plot of land  measuring  07 katha  13  chatak  bearing  holding  no. 249 of ward  no.- 25  of Silchar  Municipal  Board.  In accordance with the agreement  the  proforma  O.P. executed the power of Attorney  empowering  the  answering  O.P.  No.-1 to construct the building.  The answering  O.P.  obtained construction permission  from  SDA, Silchar and accordingly constructed the building  and  the building was named as  ‘ PEARL  HEIGHTS’ .  The  complainant  offered to purchase  one  flat measuring 996  sq.  ft  inclusive of  166  sq.  ft. common area services  etc.  being flat no.-2 (A) in the third floor of the  ‘ PEARL  HEIGHTS’   for consideration amount of Rs.15,00,000/- .  According to the answering  O.P. ,   on being satisfied with the construction,  facilities provided in  the building including the drainage system,  septic tank, soak pit, pipe line, common corridors and other facility  the complainant  purchased the concerned flat.  It  has been stated that  the generator  could not be provided as all the occupants of the building have not make any payment for the generator.   It has been stated by the answering  O.P.  that  the  complainant  having purchased the flat  happily residing there  by maintaining  the  common services   alongwith other occupants of the building.  As such  it is stated that the  answering  O.P.  no.-1  has not caused any disservice  to the complainant.   The complainant   and  other  occupants are  actually responsible  for any damage if at all has occurred  regarding  common  areas and services of the building.  Under the circumstances it is prayed for dismissal of the complaint .

                                                        In support of the case  complainant  Smti  Kabita  Bhattacharjee  submitted  her  evidence on affidavit  as  PW-1    and  exhibited some documents.   On  the other hand,  from the side of  Opposite  Party  No.-1   evidence on affidavit  of  Sri  Niloy  Paul   has  been  submitted   as  DW-1 and  also some documents have been exhibited.    Thereafter  both  sides  have also submitted written argument in addition of oral argument put forward at length by the learned counsels of  the  respective  parties.  Perused  the  entire evidence on record.  Let us  now appreciate the evidence below.

                                                   In her evidence as PW-1  the complainant has  reiterated the same facts as stated in the complaint petition.  It has been stated by  PW-1  that  the  the Proforma  O.P.  Nos. 2 &  3   are the absolute owner  of a plot of land  measuring 07 kata 13 chatak covered by 2nd  R.S.  Patta  No.463,  Dag no. 3494,  Mouza-  Silchar town, pargona- Barakpar  situated at  Kurmi Bungalow Road,  Ambicapatty,  Silchar.  On the said plot of land  the O.P.  No.-1  Sri  Niloy Paul  as promoter   constructed  residential apartment   and the same was named as  ‘  PEARL  HEIGHTS’ .  Further version of PW-1  is that  she purchased a residential flat from  O.P.  No.-1  measuring  996  sq. ft. (approx)  inclusive of 166 sq. ft. common area services etc. being flat no.- 2(A)  in  the 2nd floor of  aforesaid  ‘PEARL  HEIGHTS’   apartment   with proportionate share of land 249.75  sq.  ft.   i.e.,  5(five) chatak,  11 (eleven )  Gonda  by a registered sale deed no.-140 dated  11/01/2019 by paying consideration amount of Rs.15,00,000/-  only.  According to PW-1   as per  terms and conditions of agreement for sale executed between  herself  and  O.P.  No.-1  Sri  Niloy Paul  , the  O.P.  No.-1 has agreed to provide  all common facilities  i.e.,  generator, transformer, lift, staircase, passage, drainage etc. and undertook to complete the building construction by using and fitting good quality products and in standard manner.  But  , it has been alleged by  PW-1  that,  the construction works of the flat/apartment  have been done  in non-standard manner with several defects violating the terms and conditions  of  agreement.   As a result, according to the complainant,  they have been suffering  various problems and also they have occurred huge financial loss.  That  the wall plaster in both inside and outside of the flat, and also ceiling plaster have  become cracked,   the sanitary tank in the basement of the apartment was made without provision of soak pit and sanitary tank pipe is connected with open drain  causing  bad smelling and unhygenic  condition.  Further allegation of  PW-1  is that  due to  non-construction of western side wall of the basement  area  rain water frequently enters in the parking area and  common  passage.  That the common entrance path  of the apartment is not fit for use in the rainy days.  There is no provision  to pass water  from the basement area   and  also  there is no proper ventilation system in the car parking/ basement area.  That the  roof of the lift is   not covered by quality  CI   sheet.    According to  PW-1,  though several times they requested the  O.P.  No.-1  and issued notice  but the  O.P.  No.-1  neglected to provide the required facilities as per agreed terms  thus causing disservice  towards  them. 

                                    On the other hand,  from the evidence of DW-1  i.e.,  the O.P.  No.-1  it reveals that  it is not in dispute that the  O.P.  No.-1  as promoter of the land constructed  the  alleged  building  ‘PEARL  HIGHTS’  and   a flat  no.- 2 (A)  in the third floor of the said building measuring 996  sq. ft. inclusive of  166  sq. ft. common area services  was purchased by the complainant  by a registered sale deed.    According to DW-1, the complainant purchased the flat on being satisfied with the construction,  facilities provided in  the building including the drainage system,  septic tank, soak pit, pipe line, common corridors and other facility.  After the flat was handed over the complainant and other occupants have been maintaining the common services in the  building.  It is stated that the  generator could not be provided as all the occupants of the building did not make payment for the  same. 

                                                  It is the evidence  of  PW-1 that due to non-standard works of the building by the builder the wall plaster both inside and outside of his flat and also ceiling plaster have become cracked.  The   sanitary tank in the basement of the apartment was made without provision of soak-pit and sanitary tank pipe is connected with open drain causing foul and bad smell as well as creating  unhygenic condition.  PW-1  has further alleged that  in the basement  due  to  non-construction of  western side wall by the  Principal  O.P.  No.-1  rain water frequently enters in the basement and car parking areas causing problem.   Further allegation of PW-1  is that  there is no proper ventilation system in the car parking/ basement area. But in this respect the submission of  DW-1   is that   the complainant  i.e.,  PW-1  purchased his flat on being satisfied with the construction and facilities provided in the  flat  as well as in the common areas including the drainage system, septic tank, soak pit, pipe line  etc.  It reveals from the case record that  the concerned flat was purchased by the complainant on 10th day of  January’2019  and the instant case was filed by the complainant  in the month of  November’2020.  So  the  appearance  of crack  in the wall plaster of the flat of the complainant within this short period clearly shows the fact that  some works  of the flat were below standard and for that, according to  us,  the  O.P.  No-1  is bound to compensate.  It  may be mentioned here that  three other flat owners of the same building lodged complaints alleging in respect of the concerned flat  as well as  complaints in respect of the common areas facilities of the building.  The   xerox copy of the photo of the drain   of the building shows  its horrible condition.There is no ground for us to disbelieve the   allegation that  the   sanitary tank in the basement of the apartment was made without provision of soak-pit and  the open drain   of the building causing bad smell as well as unhygienic condition.  Both the allegations appear to be serious since  those are  polluting the environment of the  Apartment and its adjoining areas  and on the other hand  these things are making the Apartment/building  inhabitable.   Another allegation  is that  due  to  non-construction of  western side wall by the  Principal  O.P.  No.-1  rain water enters in the basement and car parking areas causing problem.   During the course of argument it has been admitted  by the  O.P.  side that  construction of western side wall is pending.  Another allegation of PW-1  is that  there is no proper ventilation system in the car parking/ basement area.   There is also no  specific denial of this fact  by the   O.P.    So  we are of the clear opinion that the Principal O.P.  i.e., the Promoter who sold the  flats to the Purchasers  is  bound to   meet  up the demands as alleged by   the  complainant. 

                                   PW-1   has  further contended that   the O.P.  no.-1  agreed to provide  generator for the use of flat owners.  But  the version of  DW-1 is that  as all the occupants of the building did not make payment for the generator so the  generator  could not be provided. There is  also no evidence in the case  from the side of the complainant  that   he  and other flat owners  paid their  respective contribution for the generator.     On the other hand    Ext. -1,  the copy  of  sale deed of the flat of the complainant  contains  no  whisper in  respect of  any  generator  the  builder  agreed to provide in the building for common use.  Exhibit-4  is the  copy of  registered  agreement  executed between  the complainant  and  the  builder  at the time of booking of the   flat by the  complainant.   In  schedule –IV  of  the  said copy of agreement  it has been mentioned  regarding  Generator  for all residents’ common use.  But  printing in the schedule-IV  page  of the said agreement  does not appear to be clear and moreover regarding providing of generator in another agreement  executed by the promoter in respect of another flat owner of the same  building  it  speaks otherwise.  As  such, it can not be  taken  that  the promoter agreed to provide   generator in the building  for common  use.

                                             PW-1  has further alleged that  the roof of the lift is not covered  by quality  C.I.  sheet  and the common entrance path of the apartment is also not fit for use in rainy days.  Though the   O.P.  No.-1   has  denied the said facts but the  case  record shows that   the Society of the building  i.e.,  ‘Pearl  Heights’  in their  meeting held on  02/08/2020  took resolution  regarding  the  said  drawbacks/ faulty works  in the  building and also in the flats .  It also  has been submitted by the complainant that   the president of the  Society  of  the  apartment/building   sent the demand to the  Promoter for rectification of faulty works but the promoter  did not comply.   There is also no grounds to disbelieve the allegations of the complainant.  As  such  the activities of the promoter  i.e  the principal   O.P.  No.-2  constitute  negligence and disservice  towards the complainant. The  promoter  is liable to  provide essential  basic  facilities in the building and the quality of works  should not be such that within few years  it will start deteriorating.

                                                Under the circumstances, according to  us,  the complainant  is entitled to get reliefs  in the case. However  it  may be mentioned here that  the  promoter   is not liable to  provide generator to the complainant’s  building. As  most of the allegations   regarding faulty works etc.  in the building  are for common use by all the  flat owners,  so, according to us,  it will be appropriate  to  give  reliefs  for those matters  jointly. Also  it  will  not be  out of place to mention here that  there is  reason  for filing this case  and also there is no defect  or impediment  in the case for granting reliefs

                                                  Accordingly,  it is ordered that   the  principal  O.P.  No.-1  Sri  Niloy  Paul  shall  construct  pucca wall on the  western side  boundary of the land of the building  ‘  Pearl  Heights’   by  using  quality materials  within  a  period of next six months .    The  principal  O.P.  No.-1 shall pay  to the complainant  an amount of Rs. 40,000/- ( Rupees  forty  thousand )  only  towards compensation for damages in the plaster  of walls  of her flat etc.  The complainant shall utilize  the said amount  for repairing of wall plasters, for painting  and for electric repairing .  The  Principal  O.P.  No.-1 shall  also pay an amount of Rs. 5,000/-  ( Rs. five  thousand  )  only towards cost of litigation.  In addition,  the Principal  O.P.  No.-1  shall  pay  lumpsum amount of Rs.1,50,000/-  (  Rupees  one lakh  fifty thousand) only  to the Society  of the building  of the  complainant  namely ‘  Pearl  Heights’  for  repairing of faulty works  in the common  areas    including the drainage system, septic tank, soak pit, pipe line ,  proper ventilation system in the car parking/ basement area , for repairing of the entrance path of the building, to cover the roof of the lift  etc.  The entire amount  as directed for payment  shall be payable within a period of  next  90(ninety) days else  interest @ 10% per annum would  accrue  on the entire amount from the date of judgment till realisation of the amount.

                                 With the above the case stands allowed on contest  against  the principal  O.P.  No.-1  Sri  Niloy  Paul.  The judgment is pronounced  on this 21st day of  March’ 2023  under our seal and  signature.

 

 
 
[HON'BLE MR. JUSTICE Sri Samarjit Dey]
PRESIDENT
 
 
[ Kamal Kumar Sarda]
MEMBER
 
 
[ Deepanita Goswami]
MEMBER
 

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.