DATE OF FILING : 27/02/2014
DATE OF S/R : 26/03/2014
DATE OF FINAL ORDER : 11/09/2014
SMT. PRATIMA KAR
wife of Sri Subhendu Kar, 51/9/1, Naskara para Lane,
P.S. Shibpur, P.O. B. Garden,
Howrah - 3------------------------------------------------- COMPLAINANT.
- Versus -
1) SRI NANDADULA KAR
S/O late Chandi Charan Kar,
51/9/1, Naskar para Lane P.S. Shibpur,
Howrah
2) Smt. Dobashroo Kar,
D/O Sri Nandadulal Kar,
51/9/1 Naskar Para Lane, P.S. Shibpur,
Howrah
3) CESC Ltd.
Dist Engineer,
433/1, G.T. Road, (N) (Regional Office),
Howrah - -------------------------------------------------OPPOSITE PARTIES.
P R E S E N T
President : Shri T.K. Bhattacharya, M.A. LL.B. WBHJS.
Member : Shri P.K. Chatterjee.
Member : Smt. Jhumki Saha.
F I N A L O R D E R
1. The instant case was filed by complainant U/S 12 of the C.P. Act, 1986,
as amended against the O.P. no. 3 alleging deficiency in service U/S 2( 1 )( g ), 2( 1 )( o ) of the C.P. Act, 1986 wherein the complainant has prayed for passing necessary directives upon the O.P. no. 3 CESC Authority for immediate installation of new meter (loop) at the complainant’s desired premises being no. 51/9/1, Naskara para Lane,P.S. Shibpur, P.O. B. Garden,Howrah - 3 and to restrain o.p. nos. 1 & 2 from raising any obstruction against such installation.
2. The o.p. no. 3, CESC Authority stated in their written version that
the complainant paid MASD Bill of Rs. 1,130- and that to attempts were made for effecting new electric connection (loop) through meter at the premises 51/9/1, Naskara para Lane,P.S. Shibpur, P.O. B. Garden,Howrah - 3. The job could not be completed for forcible and unauthorized objection raised at the site by o.p. nos. 1 & 2 . They have no objection for installing the same if free access is available.
3. Notices were served upon the o.p. nos. 1 & 2. And the same are returned
back ‘unclaimed’. o.p. nos. 1 & 2 did not appear nor they filed any written version. So the case was heard ex parte against them.
4. Upon pleadings of parties two points arose for determination :
i) Is there any deficiency in service on the part of the O.P. no. 3 i.e.,CESC Ltd. ?
ii) Whether the complainant is entitled to get any relief as prayed for ?
DECISION WITH REASONS :
5. Both the points are taken up together for active consideration. It is admitted facts that the complainant complied with all necessary technical formalities together with depositing necessary quotational money to the o.p. no. 3, CESC Authority at the schedule premises. It appears that the o.p. no. 3 being public utility concern is eager to cater the service to the intending consumer i.e. complainant at his schedule premises. There is no deficiency in service on their part and nor did they commit any unfair trade practice. Their inability to install the meter was due to the objection raised by the o.p. nos. 1 & 2. But the fact remains is that as the present situation, the consumer cannot be deprived from electricity, nor can be forced to live in darkness when all the formalities including MASD Bill paid by him. The objection raised by the o.p. no. 3 cannot be sustained at the present situation on some fictitious ground considering electricity is a need based requirement of a civilized person.
6. Considering the above we have our considered opinion that the o.p. no. 3, CESC Authority has no latches and negligence in installing the meter in question ( loop ) and that to they are ready to complete the job if free access is available at the proposed premises where quotational money was deposited by the complainant .
Therefore, we are of the view that this is a fit case where prayer of the complainant shall be allowed.
Points under consideration are accordingly decided.
Hence,
O R D E R E D
That the C. C. Case No. 106 of 2014 ( HDF 106 of 2014 ) be allowed on contest without costs against O.P. no. 3, CESC Authority and ex parte without cost against o.p. nos. 1 & 2 .
The O.P. no. 3, CESC Authority be directed to provide new electric connection through separate meter to the complainant at 51/9/1, Naskara para Lane,P.S. Shibpur, P.O. B. Garden,Howrah - 3, where quotation amount was deposited within 30 days from the date of this order.
The o.p. nos. 1 & 2 are hereby restrained from causing any disturbance during installation of the meter.
In case of any illegal objection raised by any person, complainant and o.p. no. 3 , CESC Authority shall approach to the local police station for help.
No order as to compensation.
The complainant is at liberty to put the decree into execution after expiry of the appeal period.
Supply the copies of the order to the parties, as per rule.
DICTATED & CORRECTED
BY ME.
( P. K. Chatterjee )
Member, C.D.R.F.,Howrah.