Andhra Pradesh

StateCommission

CC/31/09

M/S UDAYANANDAN RESIDENCY DEVI TOWERS RESIDENTS/FLAT OWNERS ASSOCIATION - Complainant(s)

Versus

SMT.M.SUNITHA W/O SRI RAMU - Opp.Party(s)

M/S V.GOURI SANKARA RAO

24 Nov 2010

ORDER

 
Complaint Case No. CC/31/09
 
1. M/S UDAYANANDAN RESIDENCY DEVI TOWERS RESIDENTS/FLAT OWNERS ASSOCIATION
REP.BY ITS PRESIDENT P.YADAGIRI REDDY, D.NO.5-5-702, CHINTALKUNTA, L.B.NAGAR RANGA REDDY DIST.
...........Complainant(s)
Versus
1. SMT.M.SUNITHA W/O SRI RAMU
R/O H.NO.5-11-568, OPP.KUC ROAD, HANAMKONDA, WARANGAL DIST.
2. SMT.G.RAJITHA W/O L.MOHAN
R/O H.NO.14-347, GDK MAIN ROAD, GANDHINAGAR, RK-6, SRIRAMPUR, MANCHERIYAL
ADILABAD
ANDHRA PRADESH
3. M/S DEVI CONSTRUCTIONS REP.BY ITS MP SRI.N.SUDHAKAR
R/O PLOT NO.139, DURGA VIHAR THIRUMALGERRY,
SECUNDERABAD
ANDHRA PRADESH
............Opp.Party(s)
 
BEFORE: 
 HONABLE MR. JUSTICE HON'BLE SRI JUSTICE D. APPA RAO PRESIDENT
 HON'ABLE MS. M.SHREESHA Member
 HONABLE MR. SRI R. LAXMI NARASIMHA RAO Member
 
PRESENT:
 
ORDER

BEFORE THE A.P. STATE CONSUMER DISPUTES REDRESSAL COMMISSION

AT HYDERABAD.

 

C. C. 31/2009

Between:

Udayanandan Residency

Devi Towers Residents/Flat Owners Association

(Regn. No. 452/08), D.No. 5-5-702

Chintalakunta,  L.B. Nagar

Rep. by is President

P. Yadagiri Reddy.                                       ***                         Complainant

 

                                                                   And

1.  Smt. M. Sunitha, W/o. Sri Ramu

H.No. 5-11-568, Opp. KUC Road

Hanumakonda, Warangal Dist.

 

2.  Smt. G. Rajitha, W/o. L. Mohan

R/o. 14-347, GDK Main Road

Gandhinagar, RK6- Srirampur

Mancheriyal, Adilabad Dist.

 

3.  M/s. Devi Constructions

R/o. Plot No. 139, Durga Vihar

Thirumalgherry, Secunderabad

Rep. by its Managing Partner

N. Sudhakar.                                              ***                         Opposite Parties   

 

 

Counsel for the  Complainant:                    M/s.  V. Gourisankara Rao

Counsel for the OPs:                                   M/s. Gulam Asghar Hussain Khan (R1& R2)

M/s.  Srinivasa Rao Pachwa (R3)

CORAM:                  

 

   HON’BLE SRI JUSTICE D. APPA RAO, PRESIDENT        

                                      SMT. M. SHREESHA, MEMBER

                                                                    &

                                      SRI R. L. NARASIMHA RAO, MEMBER

                                        

WEDNESAY, THE TWENTY FOURTH DAY OF NOVEMBER TWO THOUSAND TEN

 

Oral Order: (Per Hon’ble Justice D. Appa Rao, President)

 

                                                          ***

 

 

 

1)                This is a complaint filed by the flat owners association against the owners opposite parties 1 & 2,   and the builder opposite part No. 3,   for various omissions and commission pertaining to the flats  together with claim a of compensation of Rs. 10,000/- to each of the flat owner and costs.

 

 

2)                The case of the complainant in brief is that  Ops 1 & 2  owners of the plot entered into development agreement  with  Op3  a builder having got the approval  of residential complex  vide permit dt. 1.7.2005 from HUDA.   Accordingly Op3  constructed residential complex consisting of  cellar, stilt + 5 upper floors each floor consisting of  five flats.    The flat owners purchased respective flats  under various agreements of sale followed by sale deeds.    They had agreed to provide various amenities  as per the specifications  made in the agreements of sale, however did not provide as promised.    The possessions was  given  from January, 2008 onwards till May, 2008.    Several works were unfinished  and unattended  and some were in semi-finished stage.  On that they got the estimation of the value of the pending works through a civil contractor  M/s. K. K. Associates   who estimated the value of pending works at Rs. 37,52,500/-.    Despite their notice  to get the deficiencies  rectified they did neither rectify nor   give any reply  and therefore they prayed that the opposite parties be directed

a.    To provide new drinking water sump to store the drinking water in the

cellar.  

b.    Construct steps/staircase from cellar  to the upper floors

c.    To provide protection measures for the safety of the residents to prevent

People entering from adjacent  apartments. 

d.    To provide fire fighting  equipment to the apartments

e.    To properly level the corridor for preventing the water stagnation.

f.     To furnish  original title deeds and link documents in respect of the flats.

g.    To provide outlets for rain water.

h.   To replace the defective lift

i.     To provide generator.

j.     To hand over the room constructed near the gate to the association.

k.    To reimburse BRS amount to all the flat owners. 

l.     To regularize the cellar which was constructed unauthorizedly  

and illegally.

 

m.  To provide access from main high way to the residential complex

n.   To rectify the leaking drainage pipes which are emanating foul smell.

o.    To provide separate pipe lines for rain water.

p.    To replace PVC pipelines for supply of  water instead of GI pipes.

q.    To provide plastic or cement sheets roof on the stair case.

r.    To replace the main gates of the ground floor and cellar.

 

together with compensation of Rs. 10,000/- to each of the flat owner and costs of Rs. 25,000/-.

 

 

 

 

3)            Opposite Party No. 1 filed counter  adopted by Op2  denying various averments made in the complaint.   They have nothing to do with the reliefs claimed.  They have erroneously  impleaded them.    The remedy available for them was to sue for specific performance.    By simply constituting themselves as  an association  without even  obtaining their consent, it  would not authorize them for filing the complaint.    If there is deficiency in construction  it was  Op3 that was accountable.    Clauses 5 to 12 establish that  it was Op3  who was liable  and accountable for all the defects in the construction, and compensate for any alleged deficiencies  in construction.  Out of 25 flats  they have sold three flats which fact was suppressed by the complainant.    The complaint was speculative in nature.   When  the complainants themselves  have purchased the un-finished or semi-finished  flats from Op3 they cannot  turn round and accuse them for any deficiencies.  The complaint was bad for mis-joinder of parties and  therefore prayed for dismissal of the complaint with exemplary costs. 

 

4)                     Opposite party No. 3 equally resisted the case.    He denied each and very fact alleged in the complaint.  While  admitting that he had entered into development agreement  with the Ops 1 & 2  for construction of 25 flats  in an extent of  660 sq.yds under development agreement dt. 2.3.2007, he stated that   after  completion of  construction  he sold 15 flats to various purchasers  who  purchased after satisfying  with the construction.    Most of the flat owners had  committed default  in payment of the amounts towards amenities.  They had to pay Rs. 26,11,593/-.    Ops 1 & 2  had sold  the very same flats to different  persons under different sale deeds.    In fact they executed  agreement of sale in favour of one  Sri Krishna Mohan  for 10 flats on 2. 3.2007 .   Again they executed  another agreement of sale  in favour of one  Sri A. Prashantha Reddy on 17.9.2007.  Again they sold three flats to three persons  due to which   there was lot of law and order problem and various civil and criminal cases in various courts were filed and they are pending.    When he received  a letter from the complainant on  30.5.2008 he  visited the apartments on 2.6.2008,   called for meeting of all the members  and discussed various issues raised by the complainant.   Except  for installation of standby generator  the remaining deficiencies pointed  out by  them were settled.  He did not commit various deficiencies  pointed out in the complaint.   

5)                He gave explanation to various deficiencies pointed out by the complainant as follows :

 

a)                    Water connection was provided in the year 2009 after obtaining permission  on  27.6.2007  since there were no  municipal water pipelines  in the locality and in the process there was delay.

 

b)                   He  also provided concrete water proof cement water sump.

 

c)                    He arranged water tankers  every day at his  own cost.

 

d)                   He had provided spiral staircase made of steel  as advised by  architect  as the cement stair case  would obstruct  the drive way  in the cellar. 

 

e)                    He  had provided safety grills way back in the year 2008.

 

f)                     As per law  he had provided two fire extinguishers  and four sand filled buckets.

 

g)                    The cellar, ground floor and roof top was plastered  with cement work as per the practice in vogue.  

 

h)                   He had allotted parking area and earmarked parking slots.

 

i)                     He had provided rain water outlets and  it was for the complainants to maintain it properly.

 

j)                     He had provided branded 6 passengers Orion lift  in the year 2007 and it was  for the complainants to maintain the lift  properly.

 

k)                   He is ready to provide a standby generator subject to payment of payment of dues.

 

l)                     He had constructed a room near the gate for the office of the complainant association but the same was occupied by the watchman.

 

m)                  The flats owners purchased the flats  only  after verification of documents, sanction plan  etc.  for a lesser price  and they have to bear the costs and consequences if any.

 

n)                   He had provided proper flooring with cement  and also provided motor for the purpose of pumping the stagnated water. 

 

 

 

 

 

o)                    He had provided access to the main road high way but the flat owners blocked by constructing  stair case despite objection. 

 

p)                   Leakage in drainage pipelines and emanating foul smell was due to improper maintenance.

 

q)                    He had provided the rain harvesting pit  and the same was closed  since the entire locality was water logging area.

 

r)                    He had  provided PPR pipes not PVC pipes as alleged by the complainant and they  were superior in quality.

 

s)                    He had  provided PVC sheet roof top  and the same was got damaged by the complainants.  It is for them to safeguard and maintain properly.

 

t)                     He had provided sufficient gates  in the year 2007 itself.  There was no need to replace the same.

 

u)                   In order evade payments due to him the complainant filed this complaint to black-mail.     The estimation filed by the complainant is baseless without any reasoning.

 

 

There was no deficiency in service on his  part and therefore prayed for dismissal of the complaint with exemplary costs.

 

6)                The complainants  in proof of their case filed the affidavit evidence of   P. Yadagiri Reddy, President of the complainant association and got Exs. A1 to A8 marked.   Op1 filed her affidavit evidence  while Managing Director of OP3 filed his affidavit evidence and  Exs. B1 to B8  were marked  on behalf of opposite parties.   

 

7)                The points that arise for consideration are :

                     i.        Whether  the complainant association is entitled to any of the reliefs claimed  or  providing various deficiencies pointed out in the complaint?

                   ii.        Whether the complainant is entitled to any compensation?

                  iii.        If so to what relief?

 

 

 

 

 

 

 

 

 

 

 

 

 

 

8)                It is an undisputed fact that Ops 1 & 2  are owners of  660 sq.yds of site which was given under development agreement   Ex. A1 dt. 2.3.2007 for construction of 25 flats  where-under Ops 1 & 2  are entitled to 10 flats and  Op3 builder was entitled to 15 flats.    Op3 builder had sold the flats by executing sale deeds in favour of various persons  who in turn formed  complainant association.    Pursuant to the  said agreement  possession was admittedly delivered by May, 2008.    It may be stated herein that  even before  the development agreement  Ops 1 & 2  had obtained approval from the Municipal Corporation  for construction of flats on 1.7.2005 itself.    It is not known whether properties sold by  Ops 1 & 2  to various persons  were also members of the  complainant association.   OP3 alleges that various  defects  pointed out in the construction were not true.   They were neither defective nor deficient.    The complainant association could not give the names of the members, and the  deviations that were pointed out by them  were made by Op3 and in fact the purchasers knowing full well about those deviations  purchased the flats with an understanding that  they would alone be  responsible for any consequences, and that they had agreed to pay  various amounts towards  amenities.   However, they did not pay the same.    In regard to 25 flats  OP3 gave a list mentioning  the amounts due by  each of the flat owners/land owner amounting to Rs. 26,11,593/-. 

 

9)                 The complainant association in order to prove that  that  there was deficiency in construction got estimated the value  of pending works through M/s.  K. K. Associates  which estimated at Rs. 37,52,500/- and the report is marked Ex. A5.   An advocate commissioner was appointed  to verify the deficiencies  whatsoever pointed out by the complainant association in its complaint and  he with the assistance of  Sri  K. M. Ravi Kumar, Structural Engineer  visited the premises and filed his report  which is assigned as Ex. A8.    The  commissioner in his report  noted the status of each of the construction  alleged by the complainant.    

They are as follows :  

a)    Existing sump is there in that 2’-3”  height of water appeared in the sump.  The sump measurements are: inside  clear 4’-3” x 14 x 4-1/2 depth.  There is 1-1/2 HP capacity motor  is connected to the said sump.

 

b)    Iron  round staircase  in the cellar with 5’-5” dia with 3” vertical  pipe and railing  10 mm  square rod  with top 40 mm x 5 mm patti.  Treads with 18 mm x 3 mm  patti with angular frame

 

c)    The gap between the two buildings is 2’-6” total parapet wall completed, terrace flooring completed, staircase mid-landing edge 3’ height wall completed.   In between the two buildings the iron frame work is completed and plastic sheets were broken.   

 

d)    Fire fighting equipment is not provided.

 

e)    In ground floor plastering work is completed and in the cellar ceiling and beams 1st coat plastering is 90% completed.  In the cellar coloumns and outside wall plastering are not completed.

 

f)     Earmarking completed in parking slots in the cellar and ground floor.

 

g)    In corridors flooring level maintained at zero level.

 

h)   Rain water pipes  provided and it is connected to drainage, to make it function, the arrangement of rain water facility should be provided.

 

i)     Lift is properly functioning and it is make of Orien  company of six passengers capacity.

 

j)     No generator is provided.

 

k)    In the ground floor, the custody of office room is with the petitioner/complainant viz., welfare association.  The room size is 16 x 10  and outside common toilet  3’-4”  x  7’

 

l)     25 flats are in finished condition, outside some paint patch works are pending.

 

m)  No access from highway main road to the subject residential complex.

 

n)   No leakage is observed at the time of inspection, however in some of the flats situated at top floors, the dampness marks are observed in the walls.

 

o)    Rain water pipes were provided.

 

p)    The G.I. pipes are not in existence, the UPVC pipes are provided for the water lines and they are working in good condition.

 

q)    Staircase head room provided with slab, remaining ducts closed with iron  frames with plastic sheets, however, some sheets at some places were broken at one place backside of staircase, plastic sheet totally broken.

 

r)    Since the existing gates are serving well, there is no need to replace the existing gates but it is necessary to provide fiber sheets to both the gates  for security purposes. 

 

He made the following suggestions.

  1. In the cellar for lifting of excess water, one motor needs to be provided.
  2. Transformer iron girder support is provided.  It is sufficient.
  3. Ground to first floor staircase left side at the first flight railing is to be provided.
  4. Cement flooring was not done  in ground floor of outside, at backside of lift and staircase.

 

10)              This report is by an  expert.    The complainant did not dispute the observations noted  by the commissioner in regard to   the facts  noted  except alleging that the advocate commissioner failed to note that the existing sump was leaking and the complainant put 1000 liters  Syntex tank on the sump.   The complainant association by spending Rs. 8,000/- installed a grilled door on the terrace and also provided pipe line for lifting  water from the bore well to the overhead tank by spending  Rs. 30,000/-.    When Op3 contended that he had to get  Rs. 26,11,593/-  for providing various amenities  and the complainants did not pay  the said amount,  a curious contention was taken,  that if there were dues,   Op3 as well could recover the amounts  and on that ground,  he cannot deny the amenities.   

 

11)              In the light of the report of the commissioner, it could be said beyond doubt that Op3  builder had complied with  most of the deficiencies pointed out those were either incorrect or   even  for small  minor  deficiencies the complainant intend to get it rectified by  filing a complaint  hiking the amounts obviously  in order to attract jurisdiction of this Commission.   When the commissioner against whom nothing could be said, based  on  export  report  had mentioned that Op3  had completed the most of the  defects or deficiencies  pointed out.      We do not see any merits pertaining to most of the deficiencies pointed out.   The complainant  ought not to have rushed by filing a complaint,  when in their own complaint  they mentioned that  when they have issued notice  under Ex. A3  on 30.5.2008   Op3 visited the apartments on 2.6.2008, called for meeting of all the members available  and discussed various issues raised by the complainant.    He admits that  except for installation of standby generator, he had completed all the constructions barring some minor works like  i)  in the cellar for lifting of excess water one motor needs to be provided ii)   Ground to first floor staircase  left side  at the first flight railing is  to be provided.   iii)   Cement flooring was not done in ground  floor outside and at back side of lift and staircase. 

 

 

12)              The deficiencies so called pointed out by the complainant in its  complaint  ‘A to S’   were all answered  independently  mentioning that most of them were either rectified  or the problem  that the complainant was pointing out  was not existing. 

 

13)              At the cost of repetition, we may state that we fail to understand  why the complainant association has been un-necessarily complaining despite the fact that they have no complaint as recorded by the  commissioner -  for example:  In the ground floor the custody of office room is with the petitioner/complainant viz., welfare association.  The room size  is 16’ x 10’  and out-side common toilet is 3’-4” x 7’ still they have complained that it was not handed over. 

 

14)              When they have contended that the flats were un-finished the  commissioner has  pointed out that 25 flats are in finished condition and outside,  some paint  and patch works are  only pending. 

 

15)              In regard to  lift they want a lift of OTIS  company  while  Op3 provided  Orien company.   When the commissioner went and inspected the premises  he found that “lift is properly functioning  and it is make of ‘Orien company of 6 passengers capacity.”

 

16)              While the complainant alleges that there  is hardly a gap of 1-1/2 feet between the residential complex and the  adjacent commercial complex making third parties to enter into their residential complex,    the commissioner who visited the premises had found the distance  of  2’-6”.    There is no reason why the complainant was giving wrong picture  even in regard to measurements. 

 

 

 

 

 

17)              The complainant even seeks fire fighting equipment for their complex.  Op3 contends as per A.P. Apartments  Act  since the complex is below 18 meters in height  he installed fire extinguishers and sand filled buckets.  The said fact was not disputed.   

 

18)              OP3 builder had complained that the complaint was engineered  at the instance of Ops 1& 2 in view of the dispute between them.   He alleged that Ops 1 & 2 executed registered and unregistered documents  in favour of third parties  by selling the same flats twice.    They have also  executed registered agreement of sale in favour of one Krishna Mohan on 2.3.2007 for 10 flats of their share.   Again they also executed  another agreement of sale in favour of one A. Prashantha Reddy on 17.9.2007.  Again they sold three flats  in favour of  Vijay Kumar, P. Srinivasa Prasad and M. Haridhar.  Now both were claiming flats and in this regard various civil and criminal cases  were  pending in various courts.    They have also cancelled the  GPA  issued  in his favour by issuing letter dt. 2.11.2007. 

 

19)              The complainant complains that  there was no passage from residential complex to main highway on the northern side.    Ops 1 & 2 had categorically stated that they had handed over the passage to Op3 on 2.3.2007  from National Highway to residential apartment.  Since the buyers of respective flat owners have been using  which is more than sufficient for their ingress and egress, there is no need to give any direction in this regard.

 

20)              The complainant has filed an estimation prepared by  M/s. K. K. Associates  marked as Ex. A5  at Rs. 37,52,500/- for repairs.   Op3 claimed  that an amount of  Rs. 26,11,593/-  had to be paid  by the flat owners.    As we have earlier pointed out  the complainant did not  dispute, however, maintains that  Op3 can as well file a suit and recover the amounts.    Unfortunately the parties did not evince any  interest by filing  documents in order to substantiate the claims made  by each of them.   M/s. K. K. Associates   which the complainant  had requested  to estimate amounts, without furnishing  any details as to  how it could estimate said structures,  estimated  Rs. 6 lakhs for providing lift of  OTIS make, Rs. 2,50,000/- to  arrest leakages in the bathrooms of the apartments, Rs. 1 lakh towards  balconies repairs,  Rs. 1.00 lakh towards total leakages on the terrace,  Rs. 4 lakhs  towards fire fighting equipment etc.    As we have already pointed out he gave explanation to various  deficiencies pointed out  by the complainant, and the  Commission in his report made  the following suggestions.   

             i.        In the cellar for lifting of excess water, one motor needs to be provided.

           ii.        Transformer iron girder support is provided.  It is sufficient.

          iii.        Ground to first floor staircase left side at the first flight railing is to be provided.

          iv.        Cement flooring was not done  in ground floor of outside, at backside of lift and staircase.

 

The opposite party being a builder  obviously a partnership  firm must have  maintained the accounts and could have filed  the statement showing the dues  of each flat owner in order to direct them to pay the same. 

 

 

21)               The complainant alleged that  there were deviations  in the constructions  and therefore they were directed to  pay  BRS charges  evidenced from Ex. A4 notice issued by the Municipal authorities  u/s 452(2)  & 636 of HMC Act, 1955.    Op3 had stated that  Ops 1 & 2 had taken approval  for construction of apartments vide HUDA permission No. 1882/P4/P18/HUDA/2005  dt. 1.7.2005.    Op3 contended that the purchasers  after satisfying with the construction, took possession of the flats and they have been enjoying the same.    They  were well aware of the deviations.   The fact that  there were deviations  cannot be gleaned from the evidence placed on record.    However they were made to pay  the amounts mentioned in the memo filed by the  counsel for the complainant  viz.,  Rs. 33,000/-  in respect of  17 members of complainant association. 

 

 

 

22)               In the result the complaint is allowed in part directing  the  builder opposite party No. 3   (i) to  provide motor for lifting water from the cellar, (ii)  railing to first floor stair case, and (iii)  cement flooring  in ground floor at the back side of lift and staircase, and  further directed to  refund Rs. 33,000/- which was paid  to MCH towards  deviation charges.    The complaint against Ops 1 & 2 is dismissed.  However, in the circumstances each party to bear its own costs.   Time for compliance   three months. 

 

 

1)      _______________________________

PRESIDENT                 

 

 

2)      ________________________________

 MEMBER           

 

 

 

3)      ________________________________

 MEMBER           

  

 

APPENDIX OF EVIDENCE

WITNESSES EXAMINED FOR

 

 

COMPLAINANTS:                                                 OPPOSITE PARTIES

 

          None                                                                     None.

 

Documents marked for complainant:

 

Ex A-1                   Development Agreement Cum GPAH dated : 2.3.2007

Ex A-2                  Agreement of Sale of Semi Finished Flat  Feb, 2006

Ex A-3                  Letter dt : 30-5-2008

Ex A-4                  GHMC Notice dt : 12-2-2008

Ex A-5                  Detailed Estimate for repair of the  Apts. Dt : 25.4.2009

Ex A-6                  Legal notice dt : 13-10-2008

Ex A-7                  Postal & Acknowledgements .

Ex. A8                   Commissioner’s report.

 

 

 

 

 

Documents marked for Opposite Parties:

 

Ex B-1                  copy of GPA dt : 2.3.2007

Ex B-2                  copy of Sale Deed dt :2-6-2007

Ex B-3                  copy of Sale Deed dt :28-01-2008

Ex B-4                  copy of agreement of sale of semi finished flat dt : 4.2.2008

Ex B-5                  copy of Water supply and Sewerage Board dt : 27-6-2007

Ex B-6                  copy Photos (24)  

Ex. B7                  Development agreement-cum-GPA dt. 2.3.2007

Ex. B8                  Receipt dt. 14.6.2010 issued by photo studio.

 

1)      _______________________________

PRESIDENT                 

 

 

2)      ________________________________

 MEMBER           

 

 

 

3)      ________________________________

 MEMBER           

   Dt.  24. 11. 2010.  

*pnr

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

“UP LOAD – O.K.”

 
 
[HONABLE MR. JUSTICE HON'BLE SRI JUSTICE D. APPA RAO]
PRESIDENT
 
[HON'ABLE MS. M.SHREESHA]
Member
 
[HONABLE MR. SRI R. LAXMI NARASIMHA RAO]
Member

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.