Orissa

StateCommission

A/342/2007

CESCO by its Manager Electrical Division - Complainant(s)

Versus

Smt. Kadambari Acharya, - Opp.Party(s)

M/s. D. Ray & Assoc.

27 Mar 2023

ORDER

IN THE STATE CONSUMER DISPUTES REDRESSAL COMMISSION
ODISHA, CUTTACK
 
First Appeal No. A/342/2007
( Date of Filing : 27 Apr 2007 )
(Arisen out of Order Dated 13/03/2007 in Case No. CD/91/2006 of District Dhenkanal)
 
1. CESCO by its Manager Electrical Division
Dhenkanal.
...........Appellant(s)
Versus
1. Smt. Kadambari Acharya,
Dhenkanal.
...........Respondent(s)
 
BEFORE: 
 HON'BLE MR. JUSTICE Dr. D.P. Choudhury PRESIDENT
 HON'BLE MR. Pramode Kumar Prusty. MEMBER
 HON'BLE MS. Sudhiralaxmi Pattnaik MEMBER
 
PRESENT:M/s. D. Ray & Assoc., Advocate for the Appellant 1
 
Dated : 27 Mar 2023
Final Order / Judgement

                  Heard learned counsel for  the appellant. None appears for the respondent.

2.              This appeal is  filed  U/S-15 of erstwhile  Consumer Protection Act,1986(herein-after called the Act). Hereinafter, the parties to this appeal shall be referred to  with reference to their respective status before the learned District Forum.

3.                   The case   of the complainant,  in nutshell is that the  complainant was a consumer under the OP having connected load of 1 KW. The OP was issuing energy bills since 1986.  But on 0.12.2002 the  OP installed a meter  and enhanced  the connected load from 1 KW to 3.5 KW. Again   the new meter was installed  on 03.06.2006. Inspite of request of the complainant the Op never revised the energy bill  after reducing  3.5 KW to 1 KW. So, the complaint was filed.

4.                  The OP     filed  written version stating that the bill was  prepared  @ 1.5 KW on load factor basis till October,2001 but subsequently it was prepared basing on 3.5 KW  till 09.10.2002. According to them the meter was installed on 10.10.2002 and bills were issued on actual consumption basis. However, till February,2006 no revision took place. It is averred that  the power supply was disconnected from March,2005  and energy bills were revised till July,2004 with an average meter advance of 90 units per month. Therefore, they have no deficiency in service  on their part.  

5.                       After hearing both the parties, learned District Forum   passed the following order:-

               Xxxx              xxxx              xxxx

                    “ That, the complaint petition is allowed on contest without cost. The OP is directed to reduce the connected load from 3.5 KW to 1.5 KW till availability of report of the electical  inspector. The OP is to pay compensation of Rs.20,000/- (Rupees twenty  thousand) only to the complainant and n the meantime if disconnection is continuing they are to give  the power supply for the use of the consumer.”

6.                  Learned counsel   for the appellant  submitted that    learned District Forum  has committed error in  law by not considering  the written version filed by them with proper perspectives. According to them  the bill has been already revised  after the request of the complainant is made. It was Rs.66,969.60 till  March 2006 and  it was revised  but complainant  has failed  to pay same. Learned District Forum ought to have considered all the facts and law involved in this case before passing the impugned order. So, he submitted to  set-aside the impugned order by allowing the appeal.

  7.               Considered the submission of learned counsel for the appellant, perused the DFR and impugned order.

8.                     It is admitted fact that  a meter was installed in December,2002 From 2002 to 2006  the meter ready was taken up. It is also not in dispute that the meter was  checked by the Op and revision has already  been made. When  the revision has already been made, the question of revision of bill does not arise. It is not brought out in record, when 3.5 KW was revised to 1.5 KW  as enjoyed by the complainant from 2002. So, non-consideration of the request of the complainant is also deficiency in service on the part of the OP. However,  a revision of bill has already done, the question of payment of compensation of Rs.20,000/- is not required. But at the same time the OP is found to obey the impugned order for reduction of the connected load from 3.5 KW to 1 KW subject to observance of the procedure  for reduction of the connected load. The entire exercise   would be completed within a period of 30 days from the date of the order.

              The appeal is disposed of accordingly. No cost.

              Free copy of the order be supplied to the respective parties or they may download same from the confonet  or webtsite of this  Commission to treat same as copy of order received from this Commission.  

               DFR be sent back forthwith.

               Statutory amount be refunded.

 

 
 
[HON'BLE MR. JUSTICE Dr. D.P. Choudhury]
PRESIDENT
 
 
[HON'BLE MR. Pramode Kumar Prusty.]
MEMBER
 
 
[HON'BLE MS. Sudhiralaxmi Pattnaik]
MEMBER
 

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.