RP/2485/2016

DIVISION RAILWAY MANAGER & 2 ORS. - Complainant(s)

Versus

SANJAY KUMAR SINGH - Opp.Party(s)

DR. SARABJIT SHARMA

09 Sep 2016

ORDER

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION
NEW DELHI
 
REVISION PETITION NO. 2485 OF 2016
 
(Against the Order dated 09/03/2016 in Appeal No. 374/2013 of the State Commission Bihar)
1. DIVISION RAILWAY MANAGER & 2 ORS.
EAST-CENTRAL RAILWAY,
SAMASTIPUR
BIHAR
2. CHIEF COMMERCIAL MANAGER,
EAST CENTRAL RAILWAY,
HAJIPUR
BIHAR
3. STATION MANAGER,
EAST CENTRAL RAILWAY
DISTRICT-SAMASTIPUR
BIHAR
...........Petitioner(s)
Versus 
1. SANJAY KUMAR SINGH
S/O. SHRI DEVAKAR PRASAD SINGH, MOHOLLA BARAH PATTHAR WARD NO. 14 (CHAURI KINARE) PS AND
DISTRICT-SAMASTIPUR
BIHAR
...........Respondent(s)

BEFORE: 
 HON'BLE MR. JUSTICE AJIT BHARIHOKE,PRESIDING MEMBER
 HON'BLE DR. S.M. KANTIKAR,MEMBER

For the Petitioner :
Mr. Sumit Sharma, Advocate
For the Respondent :

Dated : 09 Sep 2016
ORDER

JUSTICE AJIT BHARIHOKE, PRESIDINGE MEMBER (ORAL)

1.      This revision petition is directed against the order of the State Commission, Bihar dated 09-01-2016 whereby the State Commission dismissed the appeal preferred by the petitioners against the order of the District Forum concerned. The stake involved is only a sum of Rs.2,768/-. The revision petition, however, has been filed after the expiry of the period of limitation with a delay of 70 days as per the petitioners (72 days as per calculation done by the Registry). Therefore, an application for condonation of delay has also been moved.

2.      Learned counsel for the petitioner submits that the delay in filing of the revision petition is unintentional. Actually, it occurred because of the delay caused due to the bureaucratic procedure in getting the permission to file the revision petition against the impugned order.

3.      The law relating to the condonation of delay is well settled. Recently, Hon’ble Supreme Court in Post Master General and others vs. Living Media India Ltd. and another (2012) 3 Supreme Court Cases 563 has held:

“24. After referring various earlier decisions, taking very lenient view in condoning the delay, particularly, on the part of the Government and Government Undertaking, this Court observed as under;

29. It needs no restatement at our hands that the object for fixing time-limit for litigation is based on public policy fixing a lifespan for legal remedy for the purpose of general welfare. They are meant to see that the parties do not resort to dilatory tactics but avail their legal remedies promptly. Salmond in his Jurisprudence states that the laws come to the assistance of the vigilant and not of the sleepy.

30. Public interest undoubtedly is a paramount consideration in exercising the courts' discretion wherever conferred upon it by the relevant statutes. Pursuing stale claims and multiplicity of proceedings in no manner subserves public interest. Prompt and timely payment of compensation to the landlosers facilitating their rehabilitation /resettlement is equally an integral part of public policy. Public interest demands that the State or the beneficiary of acquisition, as the case may be, should not be allowed to indulge in any act to unsettle the settled legal rights accrued in law by resorting to avoidable litigation unless the claimants are guilty of deriving benefit to which they are otherwise not entitled, in any fraudulent manner. One should not forget the basic fact that what is acquired is not the land but the livelihood of the landlosers. These public interest parameters ought to be kept in mind by the courts while exercising the discretion dealing with the application filed under Section 5 of the Limitation Act.Dragging the landlosers to courts of law years after the termination of legal proceedings would not serve any public interest. Settled rights cannot be lightly interfered with by condoning inordinate delay without there being any proper explanation of such delay on the ground of involvement of public revenue. It serves no public interest.”

                 The Court further observed:

“27. It is not in dispute that the person(s) concerned were well aware or conversant with the issues involved including the prescribed period of limitation for taking up the matter by way of filing a special leave petition in this Court. They cannot claim that they have a separate period of limitation when the Department was possessed with competent persons familiar with court proceedings. In the absence of plausible and acceptable explanation, we are posing a question why the delay is to be condoned mechanically merely because the Government or a wing of the Government is a party before us.

28. Though we are conscious of the fact that in a matter of condonation of delay when there was no gross negligence or deliberate inaction or lack of bonafide, a liberal concession has to be adopted to advance substantial justice, we are of the view that in the facts and circumstances, the Department cannot take advantage of various earlier decisions. The claim on account of impersonal machinery and inherited bureaucratic methodology of making several notes cannot be accepted in view of the modern technologies being used and available. The law of limitation undoubtedly binds everybody including the Government.

29.  In our view, it is the right time to inform all the government bodies, their agencies and instrumentalities that unless they have reasonable and acceptable explanation for the delay and there was bonafide effort, there is no need to accept the usual explanation that the file was kept pending for several months/years due to considerable degree of procedural red-tape in the process. The government departments are under a special obligation to ensure that they perform their duties with diligence and commitment. Condonation of delay is an exception and should not be used as an anticipated benefit for government departments. The law shelters everyone under the same light and should not be swirled for the benefit of a few.

30. Considering the fact that there was no proper explanation offered by the Department for the delay except mentioning of various dates, according to us, the Department has miserably failed to give any acceptable and cogent reasons sufficient to condone such a huge delay.

31. In view of our conclusion on Issue (a), there is no need to go into the merits of Issues (b) and (c). The question of law raised is left open to be decided in an appropriate case.  

32.  In the light of the above discussion, the appeals fail and are dismissed on the ground of delay. No order as to costs.”

4.      Hon’ble Supreme Court in Anshul Aggarwal vs. New Okhla Industrial Development Authority, IV (2011) CPJ 63 (SC) observed as under:

“It is also apposite to observe that while deciding an application filed in such cases for condonation of delay, the Court has to keep in mind that the special period of limitation has been prescribed under the  Consumer Protection Act, 1986 for filing appeals and revisions in consumer matters and the object of expeditious adjudication of the consumer disputes will get defeated if this court was to entertain highly belated petitions filed against the orders of the consumer foras.” 

 

5.      In Ram Lal and Ors. Vs. Rewa Coalfields Ltd. AIR 1962 Supreme Court 361, it has been observed as under: -

“It is, however, necessary to emphasize that even after sufficient cause has been shown a party is not entitled to the condonation of delay in question as a matter of right. The proof of a sufficient cause is a discretionary jurisdiction vested in the Court by S.5. If sufficient cause is not proved nothing further has to be done; the application for condonation has to be dismissed on that ground alone. If sufficient cause is shown then the Court has to enquire whether in its discretion it should condone the delay. This aspect of the matter naturally introduces the consideration of all relevant facts and it is at this stage that diligence of the party or its bona fides may fall for consideration; but the scope of the enquiry while exercising the discretionary power after sufficient cause is shown would naturally be limited only to such facts as the Court may regard as relevant”.

6.      In R.B. Ramlingam Vs. R.B. Bhavaneshwari, 2009 (2) Scale 108 Apex Court has observed as follows:

“We hold that in each and every case the Court has to examine whether delay in filing the special appeal leave petitions stands properly explained. This is the basic test which needs to be applied. The true guide is whether the petitioner has acted with reasonable diligence in the prosecution of his appeal/petition.

7.      In view of the aforesaid position in law it is clear that a government department cannot be treated differently from the ordinary litigant. The bureaucratic delay, in our opinion, cannot be made a reason for condonation of delay. Otherwise also, the revision petition pertains to a meager amount of Rs.2,768/-. Therefore, under the circumstances, we do not find any reason to condone the delay or to interfere in the concurrent findings of the fora below. The application for condonation of delay is dismissed. As a consequence, the revision petition is also dismissed.

 
......................J
AJIT BHARIHOKE
PRESIDING MEMBER
......................
DR. S.M. KANTIKAR
MEMBER

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.