Complaint presented on : 12.07.2013
Order pronounced on : 30.01.2015
DISTRICT CONSUMER DISPUTE REDRESSAL FORUM, CHENNAI (NORTH)
2nd Floor, Frazer Bridge Road, V.O.C.Nagar, Park Town, Chennai-3
PRESENT: THIRU.K.JAYABALAN, B.Sc., B.L., : PRESIDENT
TMT.T.KALAIYARASI, B.A.B.L., : MEMBER II
FRIDAY THE 30th DAY OF JANUARY 2015
C.C.NO.44/2014
G.Sridhar,
S/o. Gopalakrishnan,
No.68B Karpagam Nagar, Ponniammanmedu,
Chennai – 110. … Complainant
-Vs-S
S.Ravinchandran,
Sole Proprietor,
M/s. Kasthuri Constructions,
No.
Thirumangalam Road, Anna Nagar West,
Chennai -40. …Opposite party
Date of complaint : 12.07.2013
For Complainant : Mr. Syed Ismail, Advocate
For Opposite party : Exparte
O R D E R
THIRU.K.JAYABALAN, PRESIDENT
Complaint filed under section 12 of the Consumer Protection Act 1986 for a direction to the opposite party to pay the sum of Rs.7,51,108/- to him towards the damages and loss sustained with costs of the complaint.
1. The case of the complainant is briefly as follows:
The complainant is the owner of the house and premises bearing no.68B, Karpagam Nagar, Ponniamman Medu, Chennai 110 having building 800 sq.ft in the ground floor and 400sq.ft in the 1st floor. The complainant wanted to put up additional construction in the ground floor for 145 sq.ft and in the 1st floor 435sq.ft and to execute the additional construction work he entered into an agreement dated 10.09.2010 with the opposite party fixing cost of construction of Rs.6,23,250/- . The opposite party commenced the work on 21.10.2010 and he received the payments periodically by making endorsement on the reverse page of the agreement and he totally received a sum of Rs. 8,50,000/- which is more than the agreed amount. However the opposite party abruptly stopped the work and inspite of several request made by the complainant to complete the work the opposite party failed to complete the same and thereby the opposite party committed deficiency in service. The complainant completed the left over construction on 05.03.2012 at a cost of Rs. 2,51,108/-. Thereafter the complainant caused a legal notice dated 04.04.2013 and for which the opposite party did not reply even after receiving the same on 08.04.2013. Hence the complainant filed this complaint for claiming a sum of Rs.7,51,108/- as damages for the loss sustained to him with cost.
2. Though the opposite party appeared through counsel he had not filed the written version inspite of sufficient time given and hence the opposite party was set exparte on 14.09.2014 for non filing of written version.
3. The Complainant had filed proof affidavit and documents Ex.A1 to Ex.A5 were marked on the side of the complainant. The opposite party remained exparte.
4. POINTS FOR CONSIDERATION:
1) Whether the opposite party committed deficiency in service?
2) To what relief the complainant is entitled in this complaint?
5. POINT NO: 1
The complainant is the owner of the house and premises bearing no.68B, Karpagam Nagar, Ponniamman Medu, Chennai 110 and the existing house 800sq.ft in the ground floor,400sq.ft in the 1st floor, the complainant wanted to put up additional construction of 145 sq.ft in the ground floor and 435sq.ft in the 1st floor and to execute the additional construction he entered into an Ex.A1 agreement with the opposite party at construction costs, of Rs.6,23,250/- including material costs the opposite party commenced the work on 21.10.2010 and after periodically receiving payment totaling to Rs.8,50,000/- and thereafter he abruptly stopped the work from 08.05.2011 inspite of several requests the opposite party not turned up to complete the work.
6. Ex.A1 is the agreement entered between the complainant and the opposite party. In the said agreement it is mentioned that the construction has to be completed within 4 to 5 months from the date of commencing the work. The work was started on 21.10.2010. The opposite party received the periodical amounts by making necessary entries on the reverse pages of the Ex.A1 and accordingly he received the last payment on 08.05.2011. As agreed the opposite party had not completed the work within 4 to 5 months and also failed to complete the work even after request made by the complainant and therefore it is held that the opposite party committed deficiency in service.
7. POINT NO: 2
According to the complainant he engaged a private contractor and completed the left over work by the opposite party by spending a sum of Rs.1,88,188/- as material costs and Rs.62,920/- towards labour charges. Ex.A2 series is the bills for purchase of the materials and as per the bills the material costs comes to Rs.1,11,728/-. Ex.A3 series is the receipts for payment of labour which comes to Rs.76,420/-. The complainant claimed for mental torture Rs.5,00,000/- and in all claimed total damages for a sum of Rs.7,51,108/-. The opposite party entered the agreement to complete the additional construction at a cost of Rs.6,23,250/- as per Ex.A1 agreement. In the very same agreement after endorsing several dates he received a total sum of Rs. 8,50,000/- towards construction. The opposite party actually received excess amount a sum of Rs.2,33,250/- besides agreed amount of Rs.6,23,250/-in Ex.A1. Further the opposite party have not completed the construction as per agreement Ex.A1 even after receipt of excess amount. The excess amount paid is Rs.2,33,250/-, material costs of Rs.1,11,728/- as per Ex.A2 and labour charges of Rs.76,420/- as per Ex.A3 i.e. totaling the amount comes to a sum of Rs.4,21,398/- is a loss to the complainant. Apart from that the opposite party also have not completed the construction within the agreed period and for which the complainant as suffered with mental agony and pain for which he is entitled for compensation and such a compensation can be fixed a sum of Rs.1 lakh. So in all it would be appropriate to order a sum of Rs.5,21,398/- as compensation to the complainant in all respects as stated above payable by the opposite party would meet ends of justice and accordingly this points is answered.
8. In the result, the complaint is allowed in part and the opposite party is directed to pay a sum of Rs.5,21,398/- (Rs. Five lakhs twenty one thousand three ninety eight only) as compensation to the complainant and also to pay a sum of Rs. 2,000/- (Rs. Two thousand only) as cost of the complaint. The opposite party is directed to pay the above amounts within 6 weeks from the date of receipt of copy of the order, failing which the compensation amount shall carry with interest at the rate of 9% per annum till the date of payment.
Dictated to the steno-typist transcribed and typed by her corrected and pronounced by us on this 30th day of January 2015.
MEMBER-II PRESIDENT
COMPLAINANT SIDE DOCUMENTS:
Ex.A1 | : | 10.09.2010 | Agreement executed by the complainant and the opposite party and the endorsement made thereon at the back of the said agreement |
Ex.A2 | : | 28.04.2011 to 09.02.2012 | Copy of cash bills |
Ex.A3 | : | 02.05.2011 to 11.02.2012 | Copy of Receipts obtained from the workers individually and their endorsements |
Ex.A4 | : | 04.04.2013 | Legal notice sent to the opposite party by the complainant’s counsel |
Ex.A5 | : | 04.04.2013 | Copy of complainant’s counsel |
Ex.A6 | : | 08.04.2013 | Copy of Acknowledgment of the opposite party |
OPPOSITE PARTY SIDE DOCUMENT:
- NIL -
MEMBER-II PRESIDENT