SMT. RAVI SUSHA : PRESIDENT
Complainant filed this complaint U/S 12 of Consumer Protection Act 1986 for getting an order directing opposite parties to pay Rs.20,00,000/- together with cost of proceedings of this case.
In brief the facts of the case are that the 1st complainant is the brother of 2nd complainant. 2nd complainant is the owner of 4.11 areas of property in Chembilodu having Re.SyNo.23/3. As the 2nd complainant’s husband is working at Bangalore, she had entrusted 1st complainant to make arrangement for the construction of new house for the residential purpose. Thus 1st complainant entered in to an agreement with 2nd OP on 10/12/2014 for the construction of the house of 2nd complainant and the total cost agreed for the construction was Rs.2225000/-. But OPs received Rs.24,10,000/- in different dates for the construction. Thus the OPs received Rs.185000/- in excess from the agreed amount. In addition to that OPs received Rs.38000/- for purchasing door, Rs.37000/- for the materials of stair case, for purchase tiles Rs.33000/- Rs.24000/- for plumbing materials, Rs.26000/- for electric items, Rs.46,000/- for tiles laying expense, Rs.23000/- for painting work and Rs.25000/- for labour expense to Excavator . OPs assured to get the construction completed within a period of 8 months. The OPs failed to complete the construction within the stipulated time and the materials used for construction was of very poor quality instead of good quality . According to complainant, the work, as mentioned in para 3 of the complaint has been incompletely by the OP. Since complainant observed that the OPs are not taking interest in the construction work, he was compelled to arrange another contractor for the balance construction. Thus he had to spend Rs.2,00,000/- in the new contractor for the work. According to complaints OPs have received Rs.437,000/- an excess amount from them. The complainant, therefore, filed this complaint alleging deficiency in service on the part of the OPs.
After receiving notice OPs filed version denying the entire allegations raised by the complainant against him. OPs contended that he had constructed the house by using materials as per the terms in the agreement. He denied the averment of complainant about using poor quality materials for the construction work. OPs further contended that as per the agreement conditions, complainant should have paid additional amount than the amount agreed in the agreement for the additional construction work. He has stated that though an additional work amounts to Rs.437000/- had been done by him, the complainant had paid only Rs.1,85,000/-. The complainant had not paid the balance amount to him. OPs denied the allegation of complainant about the balance work as stated in para 3 of the complaint. OPs pleaded that he had completed the construction within the stipulated time as stated in agreement and also used materials for construction as per the agreement. OPs alleged that complainant has filed this complaint when OP insisted for paying the balance amount Rs.2,52,000/- to him. According to OPs in order to avoid the said payment to him, complainant has filed this complaint. It is stated that there is no deficiency in service on their part and prayed for the dismissal of the complaint.
Complainant No.2 has filed his chief affidavit and documents. He has been examined as PW1 and marked Exts.A1 to A4 and Ext.C1. Ext.C1 is the expert commissioner’s report prepared as per the direction of this commission on the basis of the application of the complainant. On the side of OPs , 2nd OP filed his chief affidavit and was examined as DW1. Both witnesses were subjected to cross-examined for the other party.
We have considered the rival contentions of the parties as well as the affidavits, including documents. Complainant alleged deficiency in service on the reason of construction made by OPs by using low quality materials, work done was defective, not complete the work within the period agreed, so he had to arrange another person for the balance work and had to pay Rs.2,00,000/- for that work and also the OP has received excess amount from the complainant.
In order to prove the allegations, complainant submitted agreement executed between parties 1st complainant and 1st OP, which was marked as Ext.A1. In which it is seen that the consideration of the work was 22,25000/- and also the contractor shall complete the construction of the building for eight months time from the date of advance payment and the total area of construction will be 1550Sq.ft. It is also stated in Ext.A1 that if any suggestion is put forward by the owner for major additions in the construction of the said building within the so agreed plan, then the contractor shall be under obligation to carry out such additions at the cost of the owner. In Ext.A1 it is seen that OP has received in total Rs.24,10,000/- on different dates and put signature in each payment. The said fact is not denied by the OPs.
Here for proving the quality of materials said to have been used, resulting repairs, requiring rectification etc, complainant has taken steps to appoint an expert commissioner. As per the application Mr.Sreekumar.K(Regd.Engineer-A) has been appointed as Expert commissioner to note down the defects and has filed a detailed report with photos after inspection of the premises. On perusing the Ext.C1, expert commissioner’s report, it is clearly evident that the defect mentioned by the complainant in Para 3 of the complaint are correct. OP has not led any expert evidence.
The complainant alleged that in addition to the amount of Rs.2,41,000/-, he had paid about Rs.2,50,000/- to OPs on different head as stated in page 3 of complaint for purchasing materials and for the work. On the other hand OP claimed that complainant has to pay Rs.2,52,000/- in account of additional work he had done.
For substantiating the rival contentions, both parties failed to bring evidence before us. Though during cross-examination, Pw1 has deposed that the purchase bills are with her, those are not produced before the commission. With regard to OP, he has not taken any steps for realizing the alleged amount from the complainant. Under the said circumstance, we cannot come to a point with regard to the additional amount. Further complainant’s failed to substantiate the contention that they had arranged another contractor and completed the construction work by paying Rs.2,00,000/-. Without any evidence to corroborate the contentions` we cannot come to a conclusion that complainant had spent the additional amount as mentioned above, due to the deficiency in service of OPs. Since OPs opposed the said facts, complainants should have proved her contention by substantial evidence.
On the facts and in the circumstances of the case, and in the absence of any evidence to rebut the expert commissioner’s report(Ext.C1) we are of the view that there is no reason to disbelieve the defects noted by the Expert in the Ext.C1 report. From the Ext.C1 report it is clearly evident that there is defects as stated in it in the construction of OPs. Hence there is deficiency in service on the part of OPs.
In the result complaint is allowed in part. Opposite parties are directed to pay Rs.2,00,000/- to the complainant No.2 for rectifying the defects as noted in Ext.C1 report together with compensation for the mental agony happened to complainant No.2. Opposite parties are further directed to pay Rs.10,000/- as litigation expense to the complainant No.2. Opposite parties shall comply the order within one month from the date of receipt of this order. Failing which the amount Rs.2,00,000/- carries interest @7% per annum from the date of order till realization . Complainant is at liberty to execute the order by filing execution application against opposite parties as per provisions stated in Consumer Protection Act 2019.
Exts:
A1- copy of construction agreement(subject proof)
A2-Copy of the title document(subject proof)
A3-Building tax receipt
A4- copy of marriage certificate
C1-Expert commission report
PW1-Shehira.C.V-2nd complainant
DW1-R.Vijayan-2nd OP
Sd/ Sd/ Sd/
PRESIDENT MEMBER MEMBER
Ravi Susha Molykutty Mathew Sajeesh K.P
eva
/Forwarded by Order/
ASSISTANT REGISTRAR