View 108 Cases Against Raheja Developers
Balraj Singh Mejie filed a consumer case on 21 Feb 2022 against Raheja Developers Ltd. in the StateCommission Consumer Court. The case no is CC/1/2021 and the judgment uploaded on 08 Mar 2022.
STATE CONSUMER DISPUTES REDRESSAL COMMISSION,
U.T., CHANDIGARH
Complaint case No. | : | 01 of 2021 |
Date of Institution | : | 18.12.2020 |
Date of Decision | : | 21.02.2022 |
Balraj Singh Mejie S/o Sh.Hardarshan Singh Mejie, R/o H.No.3153, Sector 21-D, Chandigarh-160022.
…… Complainant
Registered office:- W4D, 204/5, Keshav Kunj, Cariappa Marg, Sainik Farms, New Delhi-110080.
Present Address:- Landmark, Race Course Circle, Vadodara-390007, Gujrat.
…..Opposite parties
============================================================
Complaint case No. | : | 02 of 2021 |
Date of Institution | : | 18.12.2020 |
Date of Decision | : | 21.02.2022 |
Manjit Kaur Mejie W/o Sh. Balraj Singh Mejie, R/o H.No.3153, Sector 21-D, Chandigarh-160022.
…… Complainant
Registered office:- W4D, 204/5, Keshav Kunj, Cariappa Marg, Sainik Farms, New Delhi-110080.
Present Address:- Landmark, Race Course Circle, Vadodara-390007, Gujrat.
…..Opposite parties
============================================================
BEFORE: JUSTICE RAJ SHEKHAR ATTRI, PRESIDENT.
MRS.PADMA PANDEY, MEMBER
MR. RAJESH K. ARYA, MEMBER.
Present through Video Conferencing (In both complaints):-
Sh.Himanshu Raj, Advocate for the complainants (physically).
Sh.Kamal Dhaiya, Advocate for opposite party no.1.
Er.Sandeep Suri, Advocate for opposite party no.2.
JUSTICE RAJ SHEKHAR ATTRI, PRESIDENT
By this order, we propose to dispose of the aforesaid two consumer complaints. Since, the issues involved in these complaints, except minor variations, here and there, of law and facts are the same, therefore, we are of the opinion that the same can be disposed of, by passing a consolidated order.
CC No. | 01 of 2021 | 02 of 2021 |
Project | Raheja’s Revanta, Sector 78, Shikohpur, Gurgaon | Raheja’s Revanta, Sector 78, Shikohpur, Gurgaon |
Unit booked on | 23.07.2014 | 23.07.2014 |
Allotment made on | 20.09.2014 (C-3) | 20.09.2014 (C-3) |
Unit No. | C-022, 2nd Floor, Tower No.C | C-012, 1st Floor, Tower No.C |
Area of the unit | 2225.90 square feet | 2225.90 square feet |
Total cost | 2,07,62,658.00 | 2,11,26,841.00 |
Amount paid | 2,13,25,900.00 | 2,00,89,129.00 |
Agreement to sell | 20.09.2014 (C-4) | 20.09.2014 (C-4) |
Tripartite agreement dated | 27.08.2014 (C-2) | 27.08.2014 (C-2) |
Payment plan | Subvention | Subvention |
Due date of possession | 19.03.2019 (as per clause 4.2 of the agreement i.e. 48 + 6 months grace period total 54 months) | 19.03.2019 (as per clause 4.2 of the agreement i.e. 48 + 6 months grace period total 54 months) |
Possession offered or not | Not offered | Not offered |
Delay in years | More than 2 ½ years from the committed date | More than 2 ½ years from the committed date |
Allottee | Original allottee | Original allottee |
To defeat the claim of the complainants, Counsel for the developer placed reliance on condition no.15.1 of the respective buyer’s agreement to say that only the courts at Gurgaon and Punjab and Haryana High Court, at Chandigarh, have jurisdiction to entertain these complaints. We have considered this contention but it carries no weight. It is an undisputed fact that this Commission at Chandigarh has jurisdiction to entertain and decide these complaints in view of the provisions of Section 47 (4) (d) above. Therefore, the above said condition contained in the agreements does not bar the jurisdiction of this Commission. The above fact alone cannot suffice to oust the territorial jurisdiction of this Commission to adjudicate upon the complaint, in view of the specific provisions of the CPA 2019 provisions of which have been discussed above. To emphasize, the clause/conditioin relating to jurisdiction of courts in the agreement between the parties, cannot by itself over-ride the statutory right of the complainants, conferred by the above-mentioned provisions of the CPA 2019 and in the failure to adopt the same, will defeat the purpose and object of the Act, 2019, under which these consumer complaints have been filed by the complainants. Our this view is supported by the observations made by the Hon’ble National Commission in the case of Neha Singhal Vs. Unitech Limited and Abhishek Singhal vs. Unitech Limited, II (2011) CPJ 88 (NC), relevant part whereof is reproduced hereunder:-
" 3. ….In a similar case (FA No. 425 of 2010 Munish Sahgal vs DLF Home Developers Limited), the State Commission had taken the same view. The above-mentioned appeal was allowed by this Commission, vide order dated 9th February 2011, based on the decision dated 11th April 2002 of a 3 Member Bench of this Commission in FA No. 142 of 2001 (Smt Shanti vs M/s. Ansal Housing and Construction Ltd.) The only point of some relevance in this case is that the housing property in question is located in NOIDA, Gautam Buddha Nagar, Uttar Pradesh. However, that fact alone cannot suffice to oust the territorial jurisdiction of the (Delhi) State Commission to adjudicate upon the complaint, in view of the specific provisions of section 11 (2) (b) of the Consumer Protection Act, 1986 (the Act). To emphasise, the clause relating to jurisdiction of courts in the agreement between the parties cannot by itself over-ride the statutory right of the appellant/ complainant conferred by the above-mentioned provision of the Act that would defeat the purpose and object of the Act. This view is also in accord with the provisions of section 28 of the Indian Contract Act, 1872 (as amended with effect from 8th January 1997).
Further, in Ethiopian Airlines Vs Ganesh Narain Saboo, IV (2011) CPJ 43 (SC)=VII (2011) SLT 371, the principle of law laid down was that the restriction of jurisdiction to a particular Court need not be given any importance in the facts and circumstances of the case.
In Cosmos Infra Engineering India Ltd. Vs Sameer Saksena & another I (2013) CPJ31 (NC) and Radiant Infosystem Pvt. Ltd. & Others Vs D. Adhilakshmi & Anr I (2013) CPJ 169 (NC) the agreements were executed, between the parties, incorporating therein, a condition, excluding the jurisdiction of any other Court/Forum, in case of dispute, arising under the same, and limiting the jurisdiction of the Courts/Forums at Delhi and Hyderabad. The Hon’ble National Commission in the aforesaid cases held that such a condition incorporated in the agreements, executed between the parties, excluding the jurisdiction of a particular Court/Forum and limiting the jurisdiction of a particular Court/Forum, could not be given any importance and the complaint could be filed, at a place, where a part of cause of action arose, according to Sections of the Consumer Protection Act. As such, in this view of the matter, objection raised by the developer in this regard stands rejected.
“……….D- Delay due to non-performance by Govt. Agencies: The specific factors for delay which were beyond the control of the respondent are:
(1) Delay in acquisition of land for development of roads and infrastructure.
(2) Delay by government in construction of the Dwarka Expressway and allied roads.
(3) Oversupply of the residential units in the NCR region, operated to non-completion of project within stipulated period.
(4) The Government agencies have failed miserably to provide essential basic infrastructure facilities despite collecting the charges for same purposes from various Builders and Real Estate Companies by HSVP and HUDA.
(5) The opposite party faced cost escalations due to default of the concerned government agencies. The fixtures, apparatus, equipment, gadget and devices installed in the project/units gets detroit and diminishes the value and effectiveness of such items, also their warranty will lapse without its usage.
E- State Government Agencies are contributory to delay:
(1) The respondent no.1 filed RTI Application for seeking information about the status of basic services such as Road, sewerage, Water and electricity. The copy of such RTI Application dated 22.05.2018 is annexed herewith as Annexure W-2. Thereafter, the respondent no.1 received the reply of such application from HSVP where it is clearly stated that no external infrastructure facilities were laid down by the concerned Govt. Agency/Department. The copies of replies for the RTI Application dated 15.06.2018, 02.07.2018 and 11.07.2018 are annexed herewith and marked as Annexure W-3 (Colly).
(2) Recently the Hon'ble Competition Commission of India, (hereinafter referred as "CCI") has held in its order dated 01.08.2018 that Government Authorities i.e. Directorate of Town and Country Planning, Haryana and Haryana Urban Development Authority (HUDA) whose name is rechristened as Haryana Shehri Vikas Pradhikaran (HSVP) has not developed and laid down the essential basic infrastructure i.e. External Development Work despite collecting the charges for same purposes from various Builders and Real Estate Companies. Due to such apathy and discriminatory practices and standards adopted by such govt. agencies, majority of the builders, including but not limited to the answering respondent, was not able to develop the project within stipulated time period. Furthermore, it has been observed that HSVP and DGTCP may initiate external development works and for that purpose may start acquisition of land for lying of roads, electricity etc. The copy of order of CCI is annexed herewith and marked as Annexure W-4.
(3) It is pertinent to mention that without basic external infrastructure facilities such as hygienic water, roads, sewerage, allottees will suffer more if they take the possession of the apartment. The government agencies have failed miserably to provide essential basic infrastructure facilities, due to which answering respondents has been struck in situation, where delay in completing and handing over the project is causing force majeure where default/delay of possession the terms of agreement becomes unintentional, qua delay in offer of possession. Rather the respondents including developer are forced to bear the brunt of non-performance by the concerned Government Department. It is pain to customers but we too have to suffer by cost escalations. It is pertinent to mention that due to default of the concerned government agencies, the fixtures, apparatus, equipment, gadget and devices installed in the project/units gets detroit and diminishes the value and effectiveness of such items, also their warranty will lapse without its usage.
(4) Two High Tension(HT) cables lines that were passing through the project site were required to be removed and relocate the overhead HT wires to underground and hence the opposite party no.1 submitted building plan to DTCP, Haryana for approval, which was approved by the DTCP, Haryana. The revised and approved Zoning plan of the area falling under HT Lines is annexed herewith as Annexure W-5. The respondent requested to M/s KEI Industries Ltd for shifting of the 66 KV S/C Gurgaon to Manesar Line from overhead to underground Revanta Project Gurgaon vide letter dated 01.10.2013 which is annexed herewith as Annexure W-6. The HVPNL took more than one year in giving the approvals and commissioning of shifting of both the 66KV HT Lines. Thereafter, HVPNL, Gurgaon issued the performance certificate for the same to the Opposite party dated 14.06.2017 which is Annexure W-7.
(7) That Opposite Party got the overhead wires shifted underground at its own cost and only after adopting all necessary processes and procedures and handed over the same to the HVPNL and the same was brought to the notice of District Town Planner vide letter dated 28.10.2014 requesting to apprise DGTCP, Haryana for the same. The copy of said letter is annexed herewith as Annexure W-8.
(8) During such time when all such procedure and process were taking place, concurrently some amendments took place in Haryana Fire Safety Act, 2009 due to which it was further technically advised and mandated to have additional service floors/fire refuge area in the high rise tower as additional safety norms, to which the Opposite party no.1 complied in letters and spirit.
(9) After revision of zoning plan, the respondent applied for revision of Building plan incorporating all the advised changes vide application dated 14.01.2016 to DTCP, Haryana with as per initiated committed project layout and design only, pursuant to which the DTCP, Haryana was pleased to revise the Building plan in conformity with revised Zoning Plan. The copy of such Approved & Revised Building Plan 24.04.2017 are annexed herewith as Annexure W-9.
(10) It is humbly submitted that the respondent is a law abiding person and is making all the efforts to complete said Project within shortest time period. The Complainant's unit falls in Surya Tower which is expected to complete by end of 2020 post which is expected and subject to good developing infrastructure such as sector road and laying providing basic external infrastructure such as water, sewer, electricity etc. as per terms of the application and agreement to sell executed. The handover formalities shall be initiated possession shall be offered once the basic infrastructure facilities will be provided by the State Government. It is further submitted that the said Project is on full swing but due to exceptional circumstances the respondent is forced to delay timing of possession of the said unit awaiting infrastructure. The copy of HUDA Service lay plans is annexed herewith and marked as Annexure W-10 (colly).
E- External development work not provided by concerned authorities despite payment of substantial amount: Despite payment of huge amount of Rs. 40.75 Cr. Against EDC and 5.76 Cr. Against IDC, the external development works have not been provided by the concerned authorities. The respondent sent another request letter dated 18.06.2019 to the DTCP to provide and lay the basic services to enable the respondent to deliver the possession to the allottees at the earliest possible time. The copy of letter dated 18th June 2019 is annexed herewith as Annexure W-11.
F- Another request for provision of EDC/IDC to CEO, Gurugram Metropolitan Development Authority: The respondent sent another letter dated 30.12.2019 to the CEO, Gurugram Metropolitan Development Authority requesting them to provide basic infrastructure services on priority after acquisition of planned/sector roads. The copy of said letter is Annexure W-12………...”
We have considered the contention raised by Counsel for the developer and found that the same does not carry any weight. Firstly the RTI information aforesaid, pertains to the year 2018 i.e. more than 3 years back. In the documents referred to above, it has been found that approval for removal of high tension wires passing through the project land was not taken by the developer, before launching the said project; HVPNL Gurgaon issued performance certificate for commissioning of shifting of 66KV HT Lines only on 14.06.2017; revision of building plans were submitted to the DTCP, Haryana, vide application dated 14.01.2016, which was approved only on 24.04.2017; acquisition of land for development of roads and infrastructure had not been done by the Government Authorities concerned. Thus, when it was in the knowledge of the developer that the aforesaid permissions/approvals with regard to layout plans, shifting of high tension wires passing the project land, etc. was still not given by the Government Authorities and also even the land for development of roads and infrastructure had not been acquired, then it has not been clarified by the developer, as to why it was in a hurry to launch and sell the units/plots in the project in question. The consumers cannot be made to wait for completion of work, arising out from the defects of the developer/builder. Furthermore, we did not find any clause in the respective buyers’ agreements, which says that possession of the respective units will be delivered to the complainants after construction of external infrastructure by the HUDA/Govt. Department. Furthermore, there is nothing on record that after 2018, any progress with regard to development and construction activities, in the project site or external infrastructure have been carried out by the developer or by the State Government. Under above circumstances, we are of the considered view that the complainants cannot be made to wait for an indefinite period at the whims and fancies of the developer/builder.
“……3. It is hereby agreed by the parties that the Purchaser/investor within a time frame of 33 months to 36 months from the date of booking, shall be entitled to call upon the Developer in writing, to cancel the aforesaid booking at a guaranteed premium compensation of Rs.1400/- per square feet and in such a case the Developer/its nominee shall cancel the said booking within 60 days of expiry of 36 months from the date of booking. It is hereby clarified that the Developer shall over and above the guaranteed premium compensation amount shall also be liable for refund of the entire amount paid by the Purchaser along with service tax so recovered from the Purchaser till date by the Developer. The Purchaser will execute the necessary documents to surrender/cancel the allotted units upon receipt of payment. The Purchaser shall execute such necessary deeds, documents in favour of Developer for the surrender of the said Apartment by the Purchaser to Developer and the payment of guaranteed premium compensation shall be subject to applicable tax laws. In case of delay in making the payment by the Developer to the Purchaser beyond 60 days, the Developer shall be liable to pay Interest @ 18% per annum for the period of delay on the total price payable to the Purchaser. It is hereby clarified that till the time the price is fully paid by the Developer to the Purchaser, the Developer shall also be liable to pay to the Bank all installments/ Pre possession EMIs, Interest to the bank directly and keep the Purchaser fully Indemnified in this regard……”
It is also coming out from the record that the complainants in both the complaints opted for the said option of buy-back available to them under condition no.8 of the respective MOUs, by way of writing emails dated 12.04.2017 (in CC No.01 of 2021 and 02 of 2021). The developer vide emails dated 13.04.2017, in both these complaints acknowledged receipt of request for buyback and informed that the cases of the complainants shall be processed as per terms and conditions of the agreement and that no other documents were required at their end. However, there is nothing on record that thereafter, the developer made payment to the complainants, under the buyback scheme, as a result whereof, the complainants wrote letter dated 30.06.2017, Annexure C-6 (in CC No.01 of 2021 and 02 of 2021) in the matter but to no avail. When the developer did not make payments, the complainants wrote number of emails for the period from June 2017 to April 2018.
However, thereafter, vide respective emails dated 07.04.2018, Annexure C-8, (in CC No.01 of 2021 and 02 of 2021), the developer showed his inability to honour the buyback proposal on the ground that after registration of the project under RERA, 70% of the amount received from the complainants, in each complaint, stood deposited in the escrow account. In this manner, despite the fact that a clear-cut commitment was made by the developer vide condition no.8 of the MOUs, extracted above, and also the complainants in both the complaints have timely opted for buyback against their respective units, the developer failed to honour the same, which act amounts to deficiency in providing service, negligence and adoption of unfair trade practice. In this manner, the complainants, in both the complaints, were left in lurch.
In consumer complaint bearing No.01 of 2021 the developer/ opposite party no.1 is directed as under:-
It is made clear that in case any amount stood refunded to the complainant out of the aforesaid amount of Rs.2,13,25,900/- and guaranteed premium compensation, the same shall be deducted accordingly, by the developer.
It is also made clear that the developer-opposite party no.1 shall repay the entire pending/future EMIs alongwith taxes/miscellaneous charges, of the loan amount, to opposite party no.2-ICICI Bank, alongwith up-to-date interest on the loan account and keep the complainant fully indemnified in this regard, till the time refund of the aforesaid amount is made to the complainant.
In consumer complaint bearing No.02 of 2021 the developer/opposite party no.1 is directed as under:-
It is made clear that in case any amount stood refunded to the complainant out of the aforesaid amount of Rs.2,00,89,129/- and guaranteed premium compensation, the same shall be deducted accordingly, by the developer.
It is also made clear that the developer-opposite party no.1 shall repay the entire pending/future EMIs alongwith taxes/miscellaneous charges, of the loan amount, to opposite party no.2-ICICI Bank, alongwith up-to-date interest on the loan account and keep the complainant fully indemnified in this regard, till the time refund of the aforesaid amount is made to the complainant.
Pronounced
21.02.2022
Sd/-
[JUSTICE RAJ SHEKHAR ATTRI]
PRESIDENT
Sd/-
(PADMA PANDEY)
MEMBER
Sd/-
(RAJESH K. ARYA)
MEMBER
Rg
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.