Orissa

Kendrapara

CC/56/2019

Ajaya Kumar Rout - Complainant(s)

Versus

Project Manager, - Opp.Party(s)

Sri Ranjan Kumar Rout

29 Jan 2021

ORDER

OFFICE OF THE DISTRICT CONSUMER DISPUTES REDRESSAL COMMISSION,
KENDRAPARA, ODISHA
 
Complaint Case No. CC/56/2019
( Date of Filing : 30 Oct 2019 )
 
1. Ajaya Kumar Rout
S/o- Late Kinei Rout At- Radia Po- Malianch Ps- Tantiapal Marine
Kendrapra
Odisha
...........Complainant(s)
Versus
1. Project Manager,
Enzene Global Solution Pvt.Ltd. At-Garapur Po-Kapaleswar
Kendrpara
Odisha
2. Executive Engineer (CESU),
Kendrapara Electrical Division No.2 At/Po/Dist-Kendrapara
Odisha
3. S.D.O., Enzen,
Electrical Sub-Division, Mahakalpada At/Po-Mahakalpada
Kendrapra
Odisha
4. Junior Engineer, (Elect.)
At/Po-Babar Ps-Tantiapal Marine
Kendrapra
Odisha
............Opp.Party(s)
 
BEFORE: 
 HON'BLE MR. Pitabasa Mohanty PRESIDING MEMBER
 HON'BLE MRS. Rajashree Agarawalla MEMBER
 
PRESENT:Sri Ranjan Kumar Rout, Advocate for the Complainant 1
 Sri P.K.Samal & Associates, Advocate for the Opp. Party 1
Dated : 29 Jan 2021
Final Order / Judgement

SHRI   PITABAS  MOHANTY ,  I/C  PRESIDENT -      

                The petitioner has filed the present dispute against the O.Ps alleging deficiency in service as well as unfair trade practice.

            The facts shortly as per complaint petition as stated by the petitioner are that the petitioner is a domestic consumer under the O.Ps  who is availing power supply for his domestic  purpose  .It is alleged by the petitioner that as per his actual consumption of electricity he has received the electricity bill for the month of August-2019,September-19 and October-2019  Rs.210/-, Rs.168/-  and Rs.14,333/- respectively  as well as has paid the same but in the month of October-2019 he has received the electricity  bill amounting to Rs.14,333.08 paisa which is a defective bill. Accordingly the petitioner has filed the present dispute with the prayer to direct the O.Ps to revise the disputed electricity bill amounting to Rs.14,333.08  paisa in average basis as well as award Rs.50,000/-  for mental agony.

            After appearance / the O.Ps  have  filed the written version  denying the allegation of the petitioner . The main plea which has been taken by the O.Ps  in the written version is that on 17.10.2019 , the OPs have conducted meter verification and after verification it is observed that the meter status and service wire are OK. The electricity bill for the month of October-2019 has been assessed as per actual meter reading. The meter verification report was sent to the petitioner by Regd.post as the petitioner refused to sign in the verification report dt. 17.10.19 . Further it is stated by the O.ps that as per observation of Hon’ble National Commission  reported in 2012(1) CPR-76-N.C  and section 56 of Electricity Act ,the dispute cannot be adjudicated by this commission in summery procedure and it is opened to the petitioner to approach the Electrical  Inspector to challenge the correctness of bill raised by the Ops on the meter reading . As such there is no deficiency in service or unfair Trade Practice for which the dispute is liable to be dismissed  with cost.

            On the date of hearing both side of the learned advocate are present.  We heard the argument and perused the pleadings. After perusal of the record we are inclined to dispose of the present dispute as per our observation below -

            1. Admittedly the petitioner is a consumer under the O.Ps bearing consumer No. 02582651 who is entitled to maintain the dispute in this commission.

            2. It is alleged by the petitioner that though he has received the electricity bill for the month of August-2019, September-2019 and October-2019 for Rs.210/-, Rs.168/- and Rs.14,333/- respectively but in the month of October-2019 . The O.Ps have assessed the electricity bill against the petitioner amounting to Rs.14,333.08 paisa which is a erroneous / defective bill.

            As against such allegation of the petitioner, the O.Ps  have  stated in the written version that as per inspection dt.17.10.2019 by the O.Ps the meter and service wire of the petitioner are OK  and as the petitioner refused to sign in the inspection report dt.17.10.2010  the said inspection report has been sent to petitioner by Regd. Post . As against such plea from the side of the O.Ps.

            a. The O.Ps  have  not filed the registered receipt in support of their  stand that the inspection report has been sent to the petitioner by R.P .

            b. The O.Ps  have  failed to follow the  subsequent proper procedure in case the petitioner refused to sign in the inspection report .

            c. The O.Ps  have  not conducted the verification / inspection in presence of two local independent witness as per section 100(4) of the code of Criminal Procedure  1973.

            d. The O.Ps  have  not filed the copy of the meter reading register as per regulation -60 of OERC Distribution ( Condition of Supply) code-2004  in support of raising the electricity bill against the petitioner .

            e. The O.Ps also filed the ledger copy of the alleged consumer number wherein the monthly electricity unit consumption entire  year of 2019 from January to December as 50,20,20,50,50,35,25,50,60,2485,20,35 units which established that the monthly actual unit consumed by the petitioner from 20 to 50 units except the month of October-2019 as 2485.

            As regards jurisdiction of the Commission to decide the present dispute we are in the opinion that the citation / decision 2012(1) CPR-76- N.C as cited by O.P is distinguishable and not applicable to the present dispute on the ground  the cited decision relates to a case where meter seal has been broken but in the present case the O.P himself admits that the meter and service wire of the petitioner are OK.

            As regards jurisdiction even if this commission is deciding the disputes in summary procedure still then the commission is empowered to decide the complicated dispute in view of the observation of Hon’ble Supreme Court reported in 2003(1) CLT-127-SC vide para-12 and 13 ( Dr.J.J merchant and others vrs. Srinath Chaturvedi).

            In the sake of argument if the stand taken by the O.Ps  taken into consideration then  the O.Ps himself admit  that as per the MRT verification report dt.17/10/19 it is found that-

“ there was no anomaly in the meter so also in the service wire and everything are OK”. Hence it is presumed that as per O.Ps version there is no unauthorised use or unauthorised  connecting load in the premises of the petitioner and the petitioner contract load / demand load  is 0. 5 K.W as per agreement. If the petitioner use whole time( 24 hour) in a day with full contract load the maximum units he was used  12 unit per day for which in the month of  October-2019   (12x31)=372 units or less but it is not understood how  the O.P calculated much more than the  above calculation in the above month .

            The above observation clearly go to establish that the O.Ps  have  committed patent  deficiency in service  for which we quashed the bill for the October-2019 amounting to Rs.14,333.08 paisa as well as direct the O.ps to revised  the electricity bill for the month of October-2019 on average basis taking six months meter reading i.e ( 3 months prior to October-2019 and 3 months after October-2019) within one month after receipt of this order, failing which the O.Ps shall be liable to pay Rs.2,000/- ( two thousand) as compensation.

                                                                                     O R D E R

            The dispute is disposed of as per direction cited above. In case the order is not complied within the stipulated period  the petitioner is at liberty to proceed as per law. No cost.

            This order is pronounced in the open Commission on this the 29th day of  January ,2021. Under my hand and seal of the Commission.                                                                                          

                                                                                                                                                        Sd/-

               Sd/-                                                                                                                        (Shri Pitabas Mohanty) 

(Mrs  Rajashree Agrawala)                                                                                                 President  I/C

    Lady Member.                                                                                           Typed to my dictation & corrected by me 

                                                                                                                                                         Sd/- 

                                                                                                                                          (Shri Pitabas Mohanty)

                                                                                                                                                  President  I/C.

 
 
[HON'BLE MR. Pitabasa Mohanty]
PRESIDING MEMBER
 
 
[HON'BLE MRS. Rajashree Agarawalla]
MEMBER
 

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.