Haryana

StateCommission

A/439/2015

DHBVNL - Complainant(s)

Versus

PREM KUMAR - Opp.Party(s)

B.D.BHATIA

17 Feb 2016

ORDER

STATE CONSUMER DISPUTES REDRESSAL COMMISSION HARYANA, PANCHKULA

 

First Appeal No  :      439 of 2015

Date of Institution:      13.05.2015

Date of Decision :       17.02.2016

 

1.     Sub Divisional Officer (OP), Sub Division, Dakshin Haryana Bijli Vitran Nigam Limited, Jui, Tehsil and District Bhiwani.

 

2.     The Manager Director, Dakshin Haryana Bijli Vitran Nigam Limited, having its Head Office at Vidhyut Nagar, Hisar.

 

3.     Executive Engineer, Dakshin Haryana Bijli Vitran Nigam Limited, Bhiwani.

                                      Appellants-Opposite Parties

Versus

 

 

Prem Kumar s/o Sh. Madan Lal, Resident of Village Lohani, Tehsil and District Bhiwani.  

                             Respondent-Complainant

 

CORAM:             Hon’ble Mr. Justice Nawab Singh, President.

                             Shri B.M. Bedi, Judicial Member.

                                                         

 

Present:               Shri B.D. Bhatia, Advocate for appellants.

Shri Ajit Sihag, Advocate for respondent.

 

                                                   O R D E R

 

NAWAB SINGH J.(ORAL)

 

Sub Divisional Officer (Op), Sub Division, Dakshin Haryana Bijli Vitran Nigam Limited (for short ‘DHBVNL’) and others-Opposite Parties, are in appeal against the order dated February 9th, 2015, passed by District Consumer Disputes Redressal Forum, Bhiwani (for short District Forum), whereby notice bearing Memo No.CE-4 dated November 4th, 2013 (Annexure C-2), issued by DHBVNL to Prem Kumar-complainant/respondent, was declared null and void and the DHBVNL was directed to release the tubewell connection to the complainant, under A.P. category, on the basis of old Sales Circular NoD-80/2001. The complainant was also granted Rs.2200/- cost of litigation.

2.      The complainant applied for electric connection of his tubewell vide application dated February 24th, 2011. He deposited Rs.22,750/- vide receipt Annexure C-1. His name was in the seniority list for releasing connection. In the meanwhile, the DHBVNL issued Sales Circular No.D-12/2012 (Annexure-A) whereby the consumers desirous of seeking tubewell connections were given options given below:-

“1.     All the farmers/agriculturists who have deposited the full amount i.e., Rs.20,000/- plus span charges after issue of Demand notice; the connection shall be released at the old policy i.e. as per SC No.D-80/2001 on LT/HT as per the site conditions.

2.      All the farmers/agriculturists who have deposited only Rs.20,000/-, the connection shall be released on LT/HT as per the site conditions after getting the span charges deposited @ 12,500/- per span. However the release of connection to such applicants will be regulated as per old policy i.e., SC No.D-80/2001.

3.      The charges to be deposited by the farmers who have applied for connection on or after 01.01.2011 (or who have not deposited any amount except ACD) shall be i.e., Rs.30,000/- + Rs.12,500/- per span and the release of connection to such applicants will be regulated as per the guidelines given at Sr.No.5.

4.      The transformer installed under HVDS can also be augmented while releasing the above connections.

5.      The additional Guidelines for the consumers covered under Sr.no.3 & 4.

a.      If on a new T/F the number of connections to be released is exactly 3, then the consumers will be asked to pay Rs.30,000/- and Rs.12500/- per span each.

b.      If on a new T/F the number of connections to be released is exactly 2, then both the consumers will be asked to share equally the total cost incurred for release of connections.

c.       Single connection per transformer where the consumer meets the full cost of release of the connection i.e., the line & T/F cost.

d.      In case where spare capacity is available on the existing transformer and:-

i.        Only cable upto 20 mtr is required then the consumer shall pay Rs.20,000 or 30,000 as applicable.

ii.       In case additional poles are required for LT Line then Rs.12500/- per span shall be payable in addition to Rs.20,000/- or 30,000/- as applicable.

e.      In case where spare capacity is not available on the existing transformer and augmentation of the T/F is required he will be covered in the categories detailed above as per d(i) & d(ii).

f.       In case where on account of theft/damage of T/Fs installed under HVDS/Self Execution Scheme were replaced by utility with higher capacity T/F, such T/F shall be augmented as per clause ‘e’ for releasing the new connections.”

 

3.      As per the guidelines of Sales Circular No.D-12/2012 (Annexure-A), mentioned above, the farmers who had applied for connections on or after January 1st, 2011 (or who had not deposited any amount except ACD), were required to deposit Rs.30,000/- + 12500/- per span and electric connections to them were to be regulated as per the guidelines given at Sr. No.5.

4.      Indisputably, the complainant had applied on February 24th, 2011, that is, after January 1st, 2011. So, he was entitled to get connection as per Sales Circular No.D-12/2012 (Annexure-A).  Accordingly, a revised estimate was prepared. The complainant was required to pay Rs.1,08,204/-, out of which he had paid Rs.22,750/-. Thus, a sum of Rs.88,204/- was required to be deposited by the complainant. The DHBVNL issued Demand Notice bearing Memo NoCE-4 dated November 4th, 2013 (Annexure C-2), whereby he was asked to pay the balance amount of Rs.88,204/-. 

5.      Since the complainant was liable to pay the balance amount of Rs.88,204/- as per the new Sales Circular, therefore, he cannot derive the benefit of the old Sales Circular. The demand of Rs.88,204/- raised by the DHBVNL cannot be termed as deficiency in service.  This being so, the District Forum fell in error in allowing the complaint and as such the impugned order cannot sustain.

6.      In view of the above, the appeal is accepted, the impugned order is set aside and the complaint is dismissed.

7.      The statutory amount of Rs.1100/- deposited at the time of filing the appeal be refunded to the appellants-opposite parties against proper receipt and identification in accordance with rules, after the expiry of period of appeal/revision, if any.

 

 

Announced

17.02.2016

 

B.M. Bedi

Judicial Member

Nawab Singh

President

 

CL

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.