BEFORE THE CONSUMER DISPUTES REDRESSAL FORUM
ERNAKULAM
 
Complaint Case No. CC/11/485
 
1. SHYBY
W/O EDWIN JOE, SOPHIA SUNSHINE VILLA, SASTHAMUGAL, VARIKOLI P.O, ERNAKULAM DIST. 682 308
...........Complainant(s)
Versus
1. PRAVEEN PALATHINGAL
ALAPPAT DESIGN, MATHER NAGAR, PATHADIPPALAM, KALAMASSERY 683 104
............Opp.Party(s)
 
BEFORE: 
 HONORABLE MR. A.RAJESH PRESIDENT
 HONORABLE MRS. C.K.LEKHAMMA Member
 HONORABLE MR. PROF:PAUL GOMEZ Member
 
PRESENT:
 
ORDER

PBEFORE THE CONSUMER DISPUTES REDRESSAL FORUM, ERNAKULAM.

                       Dated this the 27th day of August 2012

                                                                                 Filed on : 12/09/2011

Present :

          Shri. A  Rajesh,                                                     President.

Shri. Paul Gomez,                                                 Member.

Smt. C.K. Lekhamma,                                           Member

C.C. No. 485/2011

     Between

Shyby,                                               :        Complainant

W/o. Edwin Joe,                                          (By Adv. Tom Jose, Court road,

Sophia Sunshine Villa,                                Muvattupuzha)

Sasthamugal, Varikoli P.O.,

Ernakulam-682 308.

 

 

                                                And

 

Praveen Palathingal,                       :         Opposite party

Alapatt Design, Mather Nagar,        (By Adv. Roy Varghese,

Pathadippalam,                                 Olimolath house, Pancode P.O.,

Kalamassery-683 104.                              Pin-682 310)

                                               

                                          O R D E R

A  Rajesh, President.

          Shortly stated, the case of the complainant is as follows:

          The complainant entered into an agreement with the opposite party for the installation of semi modular Kitchen, in her house on 20-08-2010.  The opposite party had agreed to complete the work within 60 days.  He collected Rs. 70,000/- as advance.           The opposite party had installed only the box inside the kitchen.  The cost of the said work is below Rs. 40,000/- as per the rate quoted by them.  Thereafter, in spite of the repeated requests made by the complainant nobody came to complete the work.  The opposite party had also shifted his office without giving any information.  The new office was located after thorough  enquiry.  But the opposite party had not taken  any steps to complete the work.  The said act of the opposite party amounts to deficiency in service.  The complainant is entitled to get refund of Rs. 30,000/- excessively collected from her  along with interest at the rate of 15% per annum from the date of receipt of the amount till realization together with cost of this proceedings. This complaint hence.

 

          2. The version of the opposite party is as follows:

 

          The opposite party had completed the major  portions of the works for the semi-modular kitchen.  He had used marine plywood for the construction of the kitchen cabinets  and it was installed after assembling.  Water paper, putty and primer were applied and the same was painted.  The opposite party incurred a total sum of Rs. 71,960/- for the works done.   The only work remaining is the installation of the  cabinet doors.   The works could not be completed owing to the non-payment of the balance amount due to the opposite party  as per the agreement.  There is no deficiency in service on the part of the opposite party.  The complainant is not entitled to get any of the reliefs as prayed for.

 

          3. No oral evidence was adduced by the complainant.  Exts. A1  and  A2 were marked.  Neither oral nor documentary evidence was adduced by the opposite party.   The expert commissioner’s report was marked as Ext. C1.  Heard the learned counsel for the parties.

 

          4. The only point that came up for consider is whether the complainant is entitled to get refund of Rs. 30,000/- with interest together with costs of the proceedings.

 

          5. The complainant and the opposite party entered into Ext. A1 agreement dated 20-06-2010 for supply and installation of the kitchen cabinet and works mentioned therein for a total amount of Rs. 1,49,000/-. Ext. A2 series (2 in numbers) would   show that the opposite party received a sum of Rs. 30,000/- on 21-08-2010 and Rs. 40,000/- on 06-09-2010. Though the opposite party carried out a portion of the work he refrain from completing the work for his own reasons not substantiated.

 

          6.  At the instance of the complainant vide order in I.A. dated 23-01-2012 an expert  commissioner was appointed by this Forum.  The report of the expert commissioner was marked as Ext. C1 with out demur.  The learned expert commissioner in Ext. C1 stated that the opposite party had expended Rs. 37,600/- to carry out the work as completed .  Since the opposite party has not competed the work fully the complainant is before us  seeking refund of Rs. 30,000/- and costs of the proceedings.  The non-performance of Ext. A1 agreement by the opposite party calls for explanation which is not forthcoming.

 

          7.  In the light of the above we are only to allow the complaint and direct  the opposite party  to refund Rs. 30,000/- to the complainant with interest @ 12% p.a. from the date of receipt till realization.  The costs is fixed at Rs.  5,000/-.  Ordered accordingly.

          The above said order shall be complied with within a period of one month from the date of receipt of a copy of the order.             

        Pronounced in the open Forum on this the 27th day of August 2012.

 

                                                                               Sd/- A Rajesh, President.

                                                                   Sd/- Paul Gomez, Member

                                                                   Sd/- C.K. Lekhamma, Member.

 

                                                                   Forwarded/By Order,

 

 

 

                                                                   Senior Superintendent.

 

 

 

 

 

                                       


 

                                                  Appendix

 

Complainant’s exhibits :

 

                             Ext.   A1               :         Copy of agreement dt. 20-08-2010

                                      A2 series   :         Copies of two receipts         

 

                                      C1              :         Commission report                        

 

 Opposite party’s Exhibits :        :         Nil

 

 

 

 
 
[HONORABLE MR. A.RAJESH]
PRESIDENT
 
[HONORABLE MRS. C.K.LEKHAMMA]
Member
 
[HONORABLE MR. PROF:PAUL GOMEZ]
Member

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties