Jasvir Kaur filed a consumer case on 26 Apr 2023 against Patiala Urban Planning & Development Authority in the Patiala Consumer Court. The case no is CC/20/25 and the judgment uploaded on 02 Jun 2023.
Punjab
Patiala
CC/20/25
Jasvir Kaur - Complainant(s)
Versus
Patiala Urban Planning & Development Authority - Opp.Party(s)
Sh J.S Jindu
26 Apr 2023
ORDER
DISTRICT CONSUMER DISPUTES REDRESSAL COMMISSION
PATIALA.
Consumer Complaint No.
:
CC/ 25/2020
Date of Institution
:
24.1.2020
Date of Decision
:
26.4.2023
Jasvir Kaur wd/o Late Sh.Harpreet Singh S/oSh.Gurvinder Singh r/o V.P.O. Sherpur, Tehsil Dhuri, District Sangrur.
…………...Complainant
Versus
Patiala Urban Planning and Development Authority (PDA) through its Estate officer, PDA Office (Patiala) PUDA Bhawan, Urban Estate, Phase-II, Patiala.
The Omaxe Ltd. through its Chief Managing Director, registered office Shop No.19-B, First Floor, Omaxe Celebration Mall, Sohna Road, Gurgaon, Haryana – 122001.
…………Opposite Parties
Complaint under the Consumer Protection Act
QUORUM
Hon’ble Mr.S.K.Aggarwal, President
Hon’ble Mr.G.S.Nagi,Member
PRESENT: Sh.J.S.Jindu, counsel for complainant.
Smt.Kusum Sood, counsel for OP no.1.
Sh.S.S.Sahni, counsel for OP No.2.
ORDER
The instant complaint is filed by Jasvir Kaur wd/o Late Sh.Harpreet Singh (hereinafter referred to as the complainant) against Patiala Urban Planning and Development Authority (PDA) and another (hereinafter referred to as the OP/s) under the Consumer Protection Act ( for short the Act).
The averments of the complainant are as follows:
That Patiala Urban Planning and Development Authority i.e. OP No.1 advertised a scheme namely PDA Omaxe City, Patiala whereby a self sufficient township of 336.5 Acres consisting of plots of various sizes, IT and BIO-Tech parts, Shopping malls etc. were to be built up and entered into joint development agreement for development of this integrated township with Oxaxe Ltd. i.e. OP No.2.
In pursuance of said agreement,PDA-Omaxe invited applications for allotment of triple storey G+2 (EWS) houses in this project. Husband of the complainant submitted application for allotment of the flat of 350.30Sq.fit alongwith earnest amount of Rs.31702/- which was registered vide No.108111 dated 26.5.2010. In the draw held on 28.7.2010 husband of the complainant got flat No.SF-4/514 and allotment letter was issued by the OPs vide memo No.3128 dated 29.12.2010 and flat No. SF 4 at second floor, measuring Super Area Approx.350.30 sq. ft, in Block Marigold, Cluster 1, was allotted to the husband of the complainant. The total tentative price of this flat was Rs.3,10,016/- and an amount of Rs.45802/- was to be paid within (60 days from the date of issue of allotment letter) i.e. upto 26.2.20211. Husband of the complainant deposited all the installments as per schedule given in the allotment letter. As per clause 6 of the allotment letter possession of the flat was to be given within three years from the date of allotment Allotment letter was issued to the complainant on 29.12.2010 and as such possession of the flat was required to be given upto 29.12.2013 but the same has not been given after lapse of near about 6 years rather OPS wrote letter memo No.PDA-M.A.-Patiala-2014/19211 dated 10.9.2014 for the deposit of Rs.30,250/- because of enhancement of compensation which was deposited vide letter dated 10.9.2014.
On 12.1.2015,husband of the complainant expired.Thereafter, complainant submitted application for transfer of ownership of the flat in question in the name of legal heirs which was transferred by Estate Officer, PDA, Patiala vide letter memo No.P.D.A./M.A./2016/331 dated 6.1.2017.
Vide letter dated 18.7.2019/13.8.2019, OPs again raised demand of Rs.48943/- as recovery of additional price without giving possession of the flat, which amounts to unfair trade practice on their part. Consequently, prayer has been made for acceptance of complaint.
Upon notice, OPs appeared through counsel and filed written statements having contested the complaint.
In the written statement filed by OP No.1, it raised certain preliminary objections. It is submitted that as per the scheme OP No.1 had only 15% share of the total consideration of the project pertaining to the construction of flats, whereas M/s Omaxe had a shre of 85% in the same. All the development of the project was to be undertaken by M/s Omaxe and no by OP No.1. Thus OP No.1 is not liable in any way for any alleged deficiency.On merits, averments of the complainant are stated to be matter of record. However, it is averred that OP No.1 is not involved in the development of the project or construction of the flats and the liability to construct the flat as per the stipulation has been that of OP No.2. Possession of the flats was required to be given to the allottees by OP No.2. OP No.1 authorized OP No.2 to develop the project of EWS flats. There is no deficiency of OP No.1. After denying all other averments, OP No.1 prayed for dismissal of complaint.
In the written statement filed by OP no.2 it also raised various preliminary objections. It is pleaded that the complainant has concealed the factum of pendency of CWP No.8100 of 2011 titled as Harbhajan Singh and Ors. Vs. State of Punjab and ors, and the development of the entire project was stalled as Status Quo was ordered by the Hon’ble Punjab & Haryana High Court vide its order dated 29.7.2011 and the same was vacated only upon dismissal of writ petition on, 26.9.2013. It is further pleaded that M/s Omaxe Ltd. has been in Joint Development Agreement with PDA as it was highest bidder so the development rights were allotted in favour of it. No direct payment had even been made to Omaxe by the complainants and the payments were made by complainants directly to OP No.1.Further as there was status quo order passed by the Hon’ble Punjab and Haryana High Court, hence the allotees were given rebate / extension fee w. e. f. 29.7.2011 to 28.9.2013 i.e. the period of operation of status quo.
OP No.1 wrongly terminated JDA (Joint development agreement) vide Memo No.3861-62 dated 20.6.2011. Said notice was duly replied by OP No.2 but termination notice was never withdrawn. After disposal of writ petition No.8100 of 2011, OP No.2 (Omaxe Ltd.) has been continuously following PDA to allow it to commence the development. However, till date PDA has not taken any decision and still the negotiations with PDA are in progress.
During the pendency of another CWP, before the Hon’ble Punjab & Haryana High Court, OP No.1 further floated fresh tenders for the completion of the work for common area i.e. roads, water supply, electricity services etc. at OMAXE City. OP No.2 also participated in the said tender and same was granted to OP no.2on fresh contract and the said work is in progress.
PDA Residents Welfare Association has also preferred CWP No.14348 of 2016, and the said writ petition is pending subjudice before the Hon’ble High Court. Vide order dated 1.8.2017, the Hon’ble High Court has directed PDA to seek instruction as to whether they want to carry on development themselves or through OP NO.2(Omaxe Ltd.) and through any third party. On the adjourned date, counsel for PDA made a statement that inter-se dispute of PDA and Omaxe Ltd. is pending before Special Committee constituted for looking into such matter headed by Chief Secretary, Govt. of Punjab and on his request, the matter was adjourned and thereafter, till date no decision has been taken by the Special Committee and the said CWP is pendingbefore the Hon’ble Punjab & Haryana High Court. Thus the non development of the project is on account of the facts beyond the control of OP No.2.
On merits, it is submitted that Op No.2 is ready to do the rest of development work at the site but OP No.1 is not permitting it to carry out the same. It is submitted that 81% of the total residential area work has already been completed. It is admitted that PDA has entered into joint development agreement for development of the integrated township with Omaxe Ltd. and invited applications for allotment of triple storey G+2 houses in the project. It is submitted that complainant had paid all the stated amounts to OP No.1 who had never settled accounts with OP No.2. It is submitted that development of entire project was stalled, as Status Quo was orderedby the Hon’ble Punjab & Haryana High Court, in CWP No.8100 of 2011 on 29.7.2011. Stay was vacated only upon dismissal of writ petition on 26.9.2013. Possession could not be delivered due to force majeure conditions of stay orders and on account of termination of JDA by OP No.1. It is submitted that delay is not on the part of OP No.2. Also there is no deficiency in service on the part of OP No.2.After denying all other averments OP No.2 prayed for dismissal of complaint.
In evidence, ld. counsel for complainant tendered affidavit of complainant,Ex.CA, copy of application,Ex.C1, copy of liability affidavit, Ex.C2, copies of receipts, Exs.C3 to C20, copy of acknowledgment for the amount of Rs.31702/-,Ex.C21, copies of letters, Exs.C22 to C27, copy of public notice,Ex.C28, copies of Aadhar cards, Exs.C29 and C30, copies of letters, Exs.C31 to C36 and closed evidence.
Ld. counsel for OP No.1 has tendered in evidence, Ex. OPA, affidavit of Manjit Singh Cheema, Estate officer alongwith documents, Exs.OP1 to OP4 and closed evidence.
Ld. counsel for OP No.2 has tendered in evidence, Ex.OPB, affidavit of Vishal Chawla, Authorized signature of OMAXE alongwith documents, Exs.OP5 to OP 28 and closed evidence.
We have heard ld. counsel for the parties and have also gone through the record of the case, carefully.
The OPs had given a wide publicity for construction of flats for economically weaker section in their development scheme under the name of PDA Omaxe City Patiala.
The husband of the complainant approached to the OPs for the allotment of EWS house (economic weaker section) in PDA-OMAXE CITY, Patiala. Vide allotment letter, Ex.C5. Flat No.SF4, at second floor measuring super area approx.350.30, in Block Marrigold, Cluster 1, was allotted to him. An amount of Rs.31702/-was deposited alongwith application No.108111 as per acknowledgment Ex.C21 .
The tentative price of the said flat was Rs.3,10,016/-.An amount of Rs.45802/- was to be deposited after allotment letter by 26.2.2011, which was deposited by the complainant on 25.2.2011 vide, Ex.C20. Certain other amounts were also deposited by the complainant as per schedule given in the allotment letter vide receipts, Exs.C6 to C18. Possession of the flat was to be given within 3 years from the date of allotment, as per clause 6 of the allotment letter dated 29.12.2010,Ex.C5 subject to any unforeseen circumstances and force majeure conditions such as act of God, Fire, Floods, Explosion, War, Riots, Terrorist attacks or Sabotage. Husband of the complainant expired on 12.1.2015.Thereafter, flat in question was got transferred in the name of his legal heirs. OPs instead of giving possession of flat had demanded various amounts from the complainant as enhancements etc. All the installments/enhancements were paid by the complainant as per various receipts brought on record by the complainant. Moreover, this fact has not been disputed by the OPs. Even the flat has been transferred in the name of the legal heirs of deceased Harpreet Singh which include his wife, the complainant, two minor children and his parents as per transfer letter No.331 dated 6.1.2017, Ex.C31.
OP No.1 in its reply to the complaint has taken the preliminary objection all the development works were to be taken up by OP No.2 who was in possession of the project site and is not liable for the development of the project or construction of the flats and solely shifted the onus on OP No.2 for the delivery of the flats. However, it has not been brought on record by OP No.1 as to when the site was handed over to OP No.2 for development and execution of the project.
OP No.2 in its written statement has submitted that a Civil Writ Petition No.8100 of 2011 by land holders titled as Harbhajan Singh & others Vs. State of Punjab & Others was filed before the Hon’ble Punjab & Haryana High Court. Following order was passed by Hon’ble High Court on 29.7.2011(Ex.OP11) in civil miscellaneous application No.1312 of 2012 in the said CWP:
“Ld. counsel for respondents seek time to file replies.
Ld. counsel for the petitioners says that the land was acquired for public purposes but the same was being used for private purpose. In view of this submission we direct that status- qua be maintained and no construction be raised till further orders” .
As such all the construction activities were stopped on 29.7.2011.
The said order was finally vacated on 26.9.2013, vide order, Ex.OP10, as the petition was dismissed as withdrawn.
Ld. counsel for OP No.2 has argued that PDA Omaxe City was a joint venture of PDA (Patiala Development Authority) and M/s Omaxe Ltd. The work of development and construction was allotted to OP No.2 on the basis of the highest bid having been made by OP No.2 at the time of allotment of work through Open Tender System. Ld. counsel further argued that no payment whatsoever has been paid by the complainant to OP No.2 and all the payments were made to OP NO.1.
Further after the disposal of CWP 8100 of 2011 on 26.9.2013 another CWP 14348 of 2016 was filed by the Welfare Society of plot holders of PDA Omaxe City before the Hon’ble High Court, which is Ex.OP13 and the Hon’ble High Court in its interim order dated 1.8.2017 had held that, “Ld. counsel appearing on behalf of respondent No.1 states that they had issued a notice for termination of the Joint Development Agreement with respondent No.2-private respondent. He seeks time to take instructions as to whether respondent No.1 is agreeable to respondent No.2 carrying out the work so far as it pertains to petitioner or whether respondent No.1 will itself carry out the said work”.
OP No.2 has also placed on record order dated 25.9.2017 against the same CWP (Ex.OP18) vide which State of Punjab was impleaded as a party as disputes inter se between OPs No.1&2 was referred to a committee headed by Chief Secretary Govt. of Punjab and same was allowed. It was also held that the dispute between the parties is no reason for the petitioners being deprived of their entitlement under the agreement entered into by their members with the respondents.
Further vide order dated 16.1.2018 Ex.OP19, Hon’ble High Court in its interim order had held that, “ Ld. counsel for respondent No.2 states that in terms of order dated 25.9.2017 of this Court, the Committee was to convey the decision regarding the meeting to be held between respondent No.1 and respondent No.2.The Committee has to look into the dispute between the petitioner and respondents No.1&2. It was pointed out that the said meeting was held on 1.11.2017 and no decision has been taken so far. The Special Committee is directed to take a decision within next 03 weeks and submit the report to this Court.
From the above, it transpires that OP No.1 had issued a notice of termination to OP No.2. The inter-say dispute between OPs No.1&2 is pending before Special Committee headed by Chief Secretary, Govt. of Punjab and no decision has been taken by the Committee till date and CWP is pending before the Hon’ble Punjab & Haryana High Court from 2016.
The notice of termination issued vide No.3861-62 dated 20.6.2011 is Ex.OP20, which has been issued on the ground that the development works have not been carried out by OP No.2 as per the terms and conditions of Joint Development Agreement, executed between OPs No.1&2. OP No.2 had then given different proposal to OP No.1 for revoking the said termination but the same had not materialized till date, as explained above.
From the above discussion, it transpires that the construction of flats, which was to be started from 30.12.2011 and was to be completed by 29.12.2014 was initially delayed due to the stay granted by the Hon’ble High Court w.e.f. 29.7.2011 to 26.9.2013. Thereafter Joint Development Agreement between OPs no.1&2 was terminated vide letter dated 20.6.2011,Ex.OP20 by OP No.1.From above it transpires that notice for termination of agreement was issued to OP No.2 by OP No.1 on 20.6.2011 well before the date of receipt of application for construction of EWS flats on 30.12.2011.Further all the payments made by the complainant had been received by OP No.1 and are lying with OP No.1.
A perusal of Joint Development Agreement,Ex.OP1/A, indicates that the development period for the project was 48 months from the effective date of starting as per clause 2.2.1.Further in the event of any delay which was attributable to OP No.1, the same was to be extended as per clause 2.2.2. Further as per clause 3.4(f) of the agreement, “Instead of terminating this Agreement as provided in this Article 3.4, the Parties may by mutual agreement extend the time for fulfilling the Conditions Precedent and the term of this Agreement; provided that any extension of time in case of the Developer’s failure to fulfill its Condition Precedent shall be subject to imposition of damages linked to delay on the Developer as determined by the Independent Technical cum Quality Control Consultant, unless the same has been occasioned by default or delay on part of PDA.”
A perusal of the termination notice, Ex.OP20 reveals that the notice for termination was of 20.6.2011 whereas the effective date of handing over the site was 9.8.2007 and as such the notice had been prepared before the completion of 48 months i.e. 8.8.2011. Further as per the said notice 80.61% of the development works had already been completed by OP No.2 as on 30.4.2011 and as per the report of Independent Quality Control Consultant, although there was a provision for imposition of damages linked to delay in the development of the project, yet notice of termination was issued by OPs No.1&2 in the first instance.
As such in view of the stay granted by the Hon’ble Punjab & Haryana High Court w.e.f. 29.7.2011 to 26.9.2013 and termination of agreement on 20.6.2011, well before the date of receipt of application on 30.12.2011 and which is still continuing, OP No.2 was no way free to construct and develop the flats in question within 36 months from 30.12.2011 onwards as per the condition of the allotment letter. It is also surprising to note that although the Joint Development Agreement (JDA) was declared null and void by OP No.1 even then they continued to collect payments interms of installments and enhancement from the complainant from time to time. As such, OP No.1 is fully responsible for not making any alternative arrangements due to cancellation of Joint Development Agreement and for not developing/constructing the flats on their own or through any other agency and are fully liable for the delay caused in this regard. Thus, the argument of OP No.1 that all development/construction work was to be done by OP No.2 does not extend any help to the case of the OP.
OP No.1 during arguments had stated that they are ready to refund the amount deposited by the complainant after making necessary deductions as per the rules of PDA. We are of the opinion that the delay in the delivery of the possession of the flats is entirely on the part of OP No.1 and there appears to be no immediate situation which indicates that the possession of the flats will be offered in near future. The complainant has suffered harassment from the OPs due to non possession of the flats for a long period of 10 years from the date for which delivery was to be given within three years.
Consequently, we partly allow the complaint and direct OP No.1 to release the deposited amount of the complainant alongwith interest @ 1.5% per month + 5% per annum interest(from the date of deposit) for the delayed possession of the flats (which is being charged, as per the policy of OP No.1 for recovery of delayed payments) as per para No.5 of the allotment letter, till realization. OP No.1 is further directed to pay Rs.20,000/-as compensation for causing mental agony and harassment to the complainant alongwith Rs.5000/-as costs of litigation expenses. The amount/compensation be shared between the legal heirs of the deceased as brought out in para 18 of this order. Compliance of the said order be made by OP No.1 within 30 days from the date of receipt of certified copy of this order.
The instant complaint could not be disposed of within stipulated period due to Covid protocol and for want of Quorum from long time.
G.S.Nagi S.K.AGGARWAL
Member President
Consumer Court Lawyer
Best Law Firm for all your Consumer Court related cases.