Chandigarh

StateCommission

CC/11/2011

Perminder Walia - Complainant(s)

Versus

Parsvnath Developers Ltd. - Opp.Party(s)

Sh. Gaurav Bhardwaj, Adv. proxy for Sh. Kulwinder Singh, Adv. for the complainant

08 Nov 2011

ORDER


The State Consumer Disputes Redressal CommissionUnion Territory,Chandigarh ,Plot No 5-B, Sector No 19B,Madhya Marg, Chandigarh-160 019
CONSUMER CASE NO. 11 of 2011
1. Perminder WaliaW/o Gurbachan Singh Walia, Permanent R/o 1605, Union St. Scheneclady, Newyork 12309-6245, USA Locak Correspondence Address # 1033, Sector 69, Mohali ...........Appellant(s)

Vs.
1. Parsvnath Developers Ltd.through its Director, SCO No. 1, First Floor, Madhya Marg, Sector 26, Chandigarh.2. The Director, Parsvanath Developers Ltd.Regd. and Corporate Office, 6th Floor, Arunachal Building, 19 Barakhamba Road, New Delhi-1100013. The Chairman, Chandigarh Housing Board, 8, Jan Marg, Sector 9, Chandigarh ...........Respondent(s)


For the Appellant :Sh. Gaurav Bhardwaj, Adv. proxy for Sh. Kulwinder Singh, Adv. for the complainant, Advocate for
For the Respondent :Sh.Aftab Singh, Adv. proxy for Sh.Ashwani Talwar, Adv. for OPs 1,2. Ms. Smriti Dhir, Adv. for OP No. 3, Advocate

Dated : 08 Nov 2011
ORDER

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.

 

Per Justice Sham Sunder , President
 
              The facts, in brief, are that the complainant applied for the allotment of a  residential flat,  in the project of the OPs namely  “Parsvnath Prideasia” proposed to be constructed, at Chandigarh. The total cost of the flat was Rs.51,43,000/-. The complainant deposited a sum of Rs.2,57,000/- alongwith the application form and the balance price of the flat, was to be deposited as per ‘time linked payment  plan’ in installments. In the draw of lots, held by OP No.3, the complainant was allotted one bedroom flat bearing No.E1-208, in Parsvanath Prideasia, Rajiv Gandhi Chandigarh Technology Park,  Chandigarh, having 740 sq.ft. super area, vide allotment letter dated 11.6.2008 annexure C1. The complainant paid all the instalments, as per schedule. Flat buyer  agreement  dated 10.6.2008, copy whereof is C2, was executed amongst the complainant and the OPs, mentioning therein that the construction of the flat was to be completed within 36 months  from 6.10.2006. It was stated that the complainant deposited total amount of Rs.41,42,000/-, as per the  time linked payment plan. However, subsequently, the complainant moved an application on 2.2.2009, copy whereof is C6, requesting the OPs to change the plan of payment from ‘Time Linked’ to ‘Construction Linked’. Accordingly, the OPs refunded Rs.25,57,000/- due to change in the payment plan. It was further stated that the complainant, who is an NRI, when visited the spot, found that even the foundation had not been laid at the site and there was no development, as per  the agreement dated 10.6.2008.    It was further stated that when the OPs failed to deliver possession, as per the terms and conditions of the development agreement, the complainant sent  a legal  notice dated 18.1.2011, copy whereof is C4, seeking  refund of the  balance amount, but to no avail.   It was further stated that the OPs were deficient, in rendering service, and also indulged into unfair trade practice.  When the grievance of the complainant, was not redressed, left with no alternative, a complaint under Section 17 of the Consumer Protection Act,1986(hereinafter to be called as the Act only), was filed by her,  claiming interest @ 24% p.a. on the amount of Rs.25,57,000/- which remained deposited with the OPs ; refund of the balance  amount of Rs.15,85,000/-  alongwith interest  @ 24% p.a. and  compensation of Rs.5.00 lacs for harassment and mental agony, besides litigation expenses.
2.         OP Nos.1&2, in their  joint written reply, admitted that the complainant applied for  the allotment of a flat,  in the aforesaid project. It was also admitted that  flat buyer agreement was executed, amongst the complainant, and the OPs.   The change of payment plan is not disputed.  It was  stated that, after the execution of the development agreement dated 6.10.2006, possession of 123.79 acres of land, claimed to be unencumbered, was handed over to OP No.1, by the Chandigarh Housing Board OP No.3. It was further stated that when OP No.1, was fencing the land, possession whereof was delivered to it, for the development of project, a dispute arose, as the Haryana Government claimed ownership, with regard to a part of the same. It was further  stated that when that dispute was resolved, an alternative piece of land, in lieu of the disputed portion of land, was given to OP No.1, but it was discovered to be the land of Forest Department. It was further stated that a period of 36 months, for the completion of project, could only be counted, from the date of delivery of possession of the entire unencumbered land by OP No.3, and not earlier thereto, as per article 2.2.2. of the development agreement.  It was admitted that  the basic price of the flat allotted to the complainant was Rs.51,43,000/-. It was not denied that the complainant deposited Rs.41,42,000/- towards the part price of the flat. It was admitted that a sum of Rs.25,57,000/- was refunded to the complainant. It was further stated that in case of cancellation, 5% amount of the basic price was required to be deducted as per the flat buyer agreement. It was further stated that the remaining amount of Rs.15,85,000/- was, thus, not refunded to the complainant. It was further stated that the  dispute between the OPs inter-se, had already been referred to the arbitrators, and their  decision was awaited and, as such, the jurisdiction of the Consumer Commission  was barred.  It was denied that OP Nos.1&2 were deficient, in rendering service, and indulged into unfair trade practice. The remaining averments, were denied, being wrong.
3.           OP NO.3, Chandigarh Housing Board, in its reply, admitted that the complainant applied for one bedroom flat alongwith the earnest money of Rs.2,57,000/- and she was allotted a flat in the project of the OPs. It was stated that the complainant chose to pay the instalments, in accordance with the time linked payment plan, and later on, shifted the same from ‘time linked’ to ‘construction linked’. It was further stated that, on change of the Payment Plan, the complainant was refunded excess amount of Rs.25,57,000/- on 9.7.2009.   It was further stated  that the developers OP Nos.1 & 2, were to pay the bid price of Rs.821.21 crores, in six quarterly instalments, from the date of signing the development agreement dated 6.10.2006, against which, they deposited only Rs.516,53,37,880/- and the balance bid price of Rs.304,67,83,330/- was due to be deposited. It was further stated that the  developers failed to carry out the development of project, as per the terms and conditions of the development agreement, and stopped all activities at the site.  It was further stated that when the developers were asked to pay the balance bid price, they raised certain issues, for which arbitration proceedings were going on. It was further stated that the developers were solely responsible, for constructing the residential units, within the stipulated period, and delivering possession of the flat, to the complainant. It was admitted that the construction was to be completed within 36 months from 6.10.2006, the date, when the development agreement was executed between the OPs. It was further stated that, in view of the Escrow agreement, executed between the OPs, in case of refund to the buyers, the liability of the Chandigarh Housing Board, was only to the extent of 30% of the total deposited amount by the allottees and 70% amount was to be  paid, by the developers. It was further stated that till date the refund case of the complainant was not received by the Chandigarh Housing Board from the developers. It was denied that OP NO.3, was   deficient, in rendering service, or it indulged into unfair trade practice. The remaining allegations, were denied, being wrong.  
4.         The complainant, in support of her case, led evidence by way of   her own affidavit,  alongwith which, a number of documents were attached.
5.        OP Nos.1&2, led evidence by way of  affidavit of Sh.P.K.Jain , President, M/s Parsvnath Developers Limited, Parsvnath Metro Tower, Delhi,   and also attached a number of documents therewith.
6.           OP No.3, led evidence by way of  affidavit of Sh.M.M. Sabharwal, its Secretary.  
7.         We have heard the Counsel for the parties, and have gone through the evidence and record of the case, carefully. 
8.      The Counsel for the complainant, submitted that the complainant, who is an NRI,  after going through the advertisements of OP Nos.1&2, applied for the allotment of a flat.   He further submitted that, as per  the flat buyer agreement C-2, dated 10.6.2008, the construction of the residential units, was likely to be completed within 36 months of the signing of the development agreement R-1/1 dated 6.10.2006, between the developers and the Chandigarh Housing Board. He further submitted that though a sum of Rs.41,42,000/- was deposited by the complainant, on the basis of time linked payment plan  with the OPs, yet not even foundation  was laid, at the spot, what to speak of construction of flats. Thereafter, the complainant opted for construction linked payment plan and, accordingly, the amount of Rs.25,57,000/- was refunded, being excess deposited. Thus, an amount of Rs.15,85,000/- remained deposited, as per construction linked payment  plan and the same was not refunded. He further submitted that though there was no breach of Clause 5(a) of the agreement dated 10.6.2008, relating to the payment of instalments, on the part of the complainant, yet, she was not given possession of   the flat by the promised date. He further submitted that the complainant, therefore, could not wait for an indefinite period, and was entitled to the refund of amount, deposited by her, with interest, as also compensation for harassment and damages for depriving her of the use of hard earned money.   He further submitted that OP Nos.1 &2 could not deduct 5% of the basic price, from the amount, deposited by the complainant, in the event of refund of the same, as there was no default, in making payment of any instalment, in time, by her. He further submitted that   the complainant was also entitled to compensation of Rs.5.00 lacs on account of mental agony and harassment.   He further submitted that the OPs were certainly deficient, in rendering service, to the complainant, by neither refunding the entire  amount, deposited by her with interest , nor paying her the compensation, and they also indulged into unfair trade practice. 
9.        On the other hand, the Counsel for OP Nos.1&2, submitted that, no doubt, the development agreement R-1/1 dated 6.10.06, was executed between the OPs, as a result whereof, the possession of the  entire unencumbered land, for the project, was to be provided by OP No.3.  He further submitted that since OP No.3, did not hand over the   possession of entire unencumbered chunk of land, required for the development of project, the construction could not be undertaken. He further submitted that there was, thus, dispute between the parties, as a result whereof, the matter was referred to the arbitrators, and their final decision was still awaited and, as such, this Commission has no jurisdiction to entertain and decide the complaint. He further submitted that, in case of cancellation of allotment, the complainant was  only entitled to the refund of amount, after deduction of 5% of the basic price, as per Clause 5(a) of the agreement dated 10.6.2008. He further submitted that though a period of 36 months was provided under article 2.2.1 of the agreement R-1/1 dated 6.10.2006, and under clause 9(a) of the agreement dated 10.6.2008, for the completion of construction, yet the same was to commence, only after the possession of  the entire unencumbered land, had been handed over to OP Nos.1&2 , for the development of project, by OP NO.3, but it (OP NO.3) failed to do so. He further submitted that, under these circumstances, OP Nos.1&2, were not at all deficient, in rendering service, nor they were liable to pay any compensation, nor they indulged into unfair trade practice.
10.        The Counsel for OP No.3, submitted that it was the responsibility of OP Nos.1&2, to complete the construction in 36 months, commencing from 6.10.2006, as per the agreements R-1/1 and C2. She further submitted that the possession of the entire   unencumbered land,   on which, the residential complex, was to be developed, had already been handed over to OP No.1, according to the agreement, executed between the OPs. She further submitted that the construction of the  residential flats, could certainly be started by OP No.1, on that land, but it did not do so intentionally and, as such, it was liable to pay the amount, deposited by the complainant.  
11.       The first question, that arises for consideration, is, as to within which period, the construction of the residential units, was likely to be completed. There is, no dispute, about the factum, that the complainant applied for the allotment of a flat and she was allotted  a flat. She   deposited Rs.41,42,000/-, in instalments, towards the price of flat, according to time linked payment plan, as admitted by the OPs. Subsequently, the complainant opted for construction linked payment plan and excess amount of Rs.25,57,000/- was refunded by the OPs on 9.7.2009. Clause 9(a) of the flat buyer agreement  annexure C2 , referred to above, which is relevant, for answering the question, posed, at the outset of this paragraph, reads as under ; 
“Construction of the residential units is likely to be completed within a period of thirty six (36) months of the signing of the Development Agreement i.e. 06.10.2006 between the Developer and CHB and/or as may be extended in terms of the Development Agreement shall be subject to force majeure and circumstances beyond the control of the Developer, and any restrains, restrictions from any Courts/authorities. The delay in grant of environmental clearances beyond 12 months of the signing of the Development Agreement shall not be counted towards the said period of 36 months.”
12.   The plain reading of Clause 9(a) of the flat buyer agreement, extracted above, clearly goes to reveal, that the construction of the residential units, was to be completed, within a period of thirty six months of the signing of the development agreement dated 06.10.2006 annexure R1/1. The time could be extended, in terms of the development agreement, dated 6.10.2006, subject to force majeure, and the circumstances, beyond the control of the developer. OP Nos.1&2 admitted, in their written reply, that, in the first instance, the possession of the entire project land was handed over to them by OP No.3, which it claimed to be unencumbered, and when the fencing was being done, the Haryana Govt. raised a dispute, with regard to the ownership of a portion of the same. It is the case of OP Nos.1&2, that when that dispute was resolved, and, in lieu of the disputed portion of the land, possession of some other land, was given to them, the same was discovered to be that of the Forest Department. No evidence was, however, produced, by OP Nos.1&2, in this regard. Even if, it is assumed for the sake of arguments, that the ownership of a small portion of the land, was disputed, that did not mean that the construction of residential units, could not be undertaken, on the remaining land, which constituted the major portion of the project land, and with regard whereto, there was no dispute, whatsoever. Therefore, it was not, on account of the circumstances, beyond the control of the developer, that delay was caused, in the construction of residential units. The developer also could not take shelter of force majeure clause. No document was produced by OP Nos.1&2, that any restriction was imposed by any Court or Authority, upon them, as a result whereof, they could not raise construction of  the residential units, in time. Even, it was not proved, that there was delay in the grant of environmental clearance. OP Nos.1&2, without first confirming the clear title of the entire land, over which the project, was to be developed, started booking the flats, and allotting the same, to the prospective buyers, by fleecing them of huge amounts, and making misleading statement, that the construction of   residential units, will be completed within 36 months w.e.f. 6.10.2006. Even, long after the expiry of the stipulated period, not even a brick was laid, at the site, what to speak of raising construction. OP Nos.1&2, thus, indulged into unfair trade practice. It is, therefore, held that the construction of the residential units was to be completed within 36 months from 6.10.2006 i.e. by 5.10.2009. 
 13.         The next question, that arises for consideration, is, as to whether the complainant is entitled to the refund of amount, deposited by her, with interest or not ? Clause 9(d) of the flat buyer agreement, which is relevant, to answer this question, reads as under;
“9(d) If as a result of any rules or directions of the Government or if any competent authority delays, withholds, denies the grant of necessary approvals for the Project, or if due to any force majeure conditions, the Developer is unable to deliver the unit to the Buyer, the Developer and CHB shall be liable to refund to the Buyer the amounts received from the Buyer with interest at the SBI Term Deposit Rate as applicable on the date of refund.” 
14.       The complainant deposited the instalments, in time, with the hope of getting possession of the flat, allotted to her, within a period of 36 months from 10.6.2006, but   by the year 2011, not even a single brick, had been laid, at the spot, what to speak of construction of flats, and delivery of possession thereof, to the buyers. In these circumstances, the complainant could not wait for an indefinite period. The only option with the complainant, in such circumstances, was to ask for the refund of amount. She sent legal notice notices C-4 dated 18.1.2011, for the refund of amount, with interest, but the OPs failed to do so. The plain reading of Clause 9(d) extracted above, reveals that if the developer, for, whatever the reasons may be, fails to deliver the residential unit to the buyer, the developers and the Chandigarh Housing Board, shall be liable to refund the amounts, received from the buyer, with interest, at the SBI Term Deposit Rate, as applicable, on the date of refund.    The OPs were, thus, deficient, in rendering service, by neither delivering the possession of the flat, within the stipulated time, nor refunding the amount with interest, as provided under Clause 9(d) of the agreement, referred to above.   The complainant is, thus, held entitled to the refund of amount of Rs.15,85,000/- with interest at the SBI term deposit rate, as per Clause 9(d) of the agreement, referred to above w.e.f. 9.7.2009, when the remaining amount of Rs.25,57,000/- was refunded to her. The amount of Rs.25,57,000/- also remained deposited with the OPs, till the date of refund i.e.  9.7.2009. The complainant is also held entitled to interest at the SBI term deposit rate on the said amount of Rs.25,57,000/- from the date of deposit, till its refund.
15.       Coming to the submission of the Counsel for OP Nos.1&2, that since there was breach of Clause 5(a) of the flat buyer agreement,   by the complainant, she was only entitled to the refund of the remaining amount, deposited by her, after deduction of 5% of the basic price of the flat, it may be stated here, that such an argument, advanced by the Counsel for OP Nos.1&2, is misconceived. Clause 5(a) of the aforesaid agreement dated 10.6.2008, reads as under ;
“5(a)Timely payment of the instalments/amounts due shall be of the essence of this Agreement. If payment is not made within the period stipulated and/or the Buyer commits breach of any of the terms and conditions of this Agreement, then this Agreement shall be liable to be cancelled. In the eventuality of cancellation, earnest money being 5% of the basic price would be forfeited and the balance, if any, would be refundable without interest. However, the sellers may allow the revival of the allotment of the unit (subject to its availability) in the name of the Buyer on payment of revival charges amounting to 10% of earnest money.”
16.        The plain reading of Clause 5(a) extracted above, clearly goes to show that admittedly payment of the instalments/amounts due, shall be the essence of the agreement, and if the payment, was not made, within the stipulated period or the buyer committed breach of any of the terms and conditions of the agreement, the agreement shall be liable to be cancelled and the amount would be refunded, after deduction of 5% of the basic price. The question arises, as to whether, there was default, in the payment of instalments, or violation of any other term and condition of the agreement, aforesaid, on the part of the complainant, or not ? It was proved, as also admitted by the OPs, that the payment of instalments was made by the complainant, from time to time, as and when the same fell due. There was no delay, in making payment of the price of flat, through instalments, on the part of the complainant. Since, after the expiry of the period of 36 months from 6.10.2006, not even a single brick, had been laid, the complainant had to ask for the refund of the amount. There was also no breach of any other term and condition of the agreement, referred to above, on the part of the complainant. As such, the provisions of Clause 5(a), extracted above, relating to the deduction of 5% amount of the basic price, could not be invoked. The complainant was, thus, entitled to the refund of entire amount, deposited by her, with interest, as held above. The submission of the Counsel for the OPs ,in this regard, being without merit, must fail, and the same stands rejected.
17.       The next question, that arises for consideration, is, as to whether, the complainant is entitled to compensation, for not handing over possession to them, as per the terms and conditions of the agreement C2 dated 10.6.2008, referred to above, and for causing physical harassment and mental agony, or not ? Clause 9 ( C ) of the agreement, referred to above, which is relevant for answering the question, reads as under :
            “9(c) In case of possession of the built up area is not offered to the Buyer within a period of 36 months or extended period as stipulated in sub-clause (a) above the Buyer shall be entitled to receive from Developer compensation @ Rs.107.60 per sq.mtr (Rs.10/- per sq.ft) of the super area of the unit per month and to no other compensation of any kind. In case the Buyer fails to clear his account and take possession of the unit within30 days of offer, the Buyer shall be liable to pay to the Developer holding charges @ 107.60 per sq.mtr. (Rs.10/- per sq.ft) of the super area of the unit per month in addition to the liability to pay interest to the sellers and other consequences of default in payment. ”
 18.        The possession of the flat was not offered, to the buyer, within a period of 36 months from 6.10.2006. As stated above, even till date, not even a single brick, has been laid, at the spot. In these circumstances, as per Clause 9( c) of the aforesaid agreement, the complainant only became entitled to compensation @107.60 per sq.mtr(Rs.10/- per sq.ft. ) of the super area of the unit, per month. The language of Clause 9(c) is unambiguous and clear. The parties executed the agreement, aforesaid, with eyes wide open, and, thus, they are bound by the terms and conditions of the same. No compensation, beyond the terms and conditions, contained in Clause 9    ( C) of the aforesaid agreement, could be claimed by the complainant. It is, thus, held that the complainant is entitled to compensation @ Rs107.60 per sq. mtr (Rs.10/- per sq. ft.) of the super area of unit, per month, from 5.10.2009, the last date of completion of the project, till the actual payment was made to them. In this view of the matter, no further  compensation claimed by the complainant,  for mental agony & physical harassment, can be granted to her.
19.          Coming to the factum, as to whether, the complainant is entitled to interest @ 24% p.a.  claimed by her in the complaint,   it may be stated here, that this relief cannot be granted to her. It has been held in para 14 above, that the OPs are liable to   refund the amount , received from the complainant, with interest, at the SBI Term Deposit Rate, as applicable on the date of refund, in terms of Clause 9(d) of the agreement dated 10.6.2008. No interest, beyond the terms and conditions contained in Clause 9( d) of the aforesaid agreement, could be allowed to the complainant. Since, the complainant has  claimed the   refund of amount deposited, which has been allowed alongwith interest and compensation, as stated above,  therefore, she is  not entitled to    interest @ 24% p.a.
20.      Coming to the submission of the Counsel for OP Nos.1&2, that since the remedy for settlement of dispute, by way of arbitration, has already been availed of by the OPs, in accordance with clause 18 of the Escrow agreement dated 1.6.2007, Annexure R1/3, executed between them, the complaint under Section 17 of the Consumer Protection Act,1986 was barred, it may be stated here, that the same does not merit acceptance. With a view to appreciate the controversy, in   its proper perspective, reference to Section 3 of the Consumer Protection Act,1986, is required to be made, which reads as under ;
            “3.Act not in derogation of any other law.—
           The provisions of this Act shall be in addition to and not in derogation of the provisions of any other law for the time being in force.”
Section 3 of the Act, is worded in widest terms, and leaves no manner of   doubt, that the provisions of the Act, shall be in addition to, and not in derogation of any other law, for the time being, in force. The mere fact that the remedy of arbitration, which was provided, in the agreement dated 1.6.2007 annexure R1/3, has already been availed of, by the OPs, that would not oust the jurisdiction of the Consumer Fora, in view of Section 3 of the Act. Similar principle of law, was laid down in Fair Engg. Pvt. Ltd. & another Vs N.K.Modi (2003)2 SCC412  and  C.C.I Chambers Coop. Housing Society Ltd. Vs Development Credit Bank Ltd. (2006)3 SCC721.  In this view of the matter, the submission of the Counsel for OP No.1, being devoid of merit, must fail, and same stands rejected.
21.       For the reasons, recorded above, the complaint is  partly  accepted  with costs of Rs.5000/- , in the following terms
(i)Parsvnath Developers Limited and the Chandigarh Housing Board are held liable jointly and severally to refund the amount  of Rs.15,85,000/- deposited by the complainant alongwith interest at the SBI Term Deposit rate, as applicable on the date of refund, from 9.7.2009 (when the remaining amount of Rs.25,57,000/- was refunded) till the actual date of  realization, as provided by Clause 9(d) of the flat buyer agreement ;
(ii) Parsvnath Developers Limited and the Chandigarh Housing Board are  also held liable jointly and severally to  pay interest  on the total amount of Rs.41,42,000/- as per clause 9(d) of the agreement dated 10.6.2008 from the respective date(s) of deposits, till 9.7.2009, when the amount of Rs.25,57,000/- was refunded to the complainant.
(iii)Parsvnath Developers Limited shall also pay compensation,   for not offering the built up flat within 36 months @ Rs.107.60 per sq. mtr (Rs.10/- per sq.ft) of the super area of the unit, per month, from 5.10.2009, the last date of completion of the project, till actual payment to the complainant is made, as provided by Clause 9( C) of the flat buyer  agreement.
(iv)The aforesaid directions shall be complied with, by the OPs,   within 30 days, from the date of receipt of a copy of the order, failing which they shall be liable to pay penal interest @ 12% p.a, on the aforesaid payable amounts.
22.        Certified Copies of this order be sent to the parties, free of charge.
23.        The file be consigned to Record Room.
                                              

HON'BLE MRS. NEENA SANDHU, MEMBERHON'BLE MR. JUSTICE SHAM SUNDER, PRESIDENTHON'BLE MR. JAGROOP SINGH MAHAL, MEMBER