View 1147 Cases Against Parsvnath
View 981 Cases Against Parsvnath Developers
AKSHAY VERMA filed a consumer case on 21 Nov 2017 against PARSVNATH DEVELOPERS LTD. in the StateCommission Consumer Court. The case no is CC/11/170 and the judgment uploaded on 19 Dec 2017.
IN THE STATE COMMISSION: DELHI
(Constituted under Section 9 of the Consumer Protection Act, 1986)
Date of Decision: 21.11.2017
Complaint Case No. 170/2011
In the matter of:
Sh. AkshayVerma
S/o Sh. KishanLalVerma
R/o 1704/1, 2nd floor
Bhagirath Palace, Delhi-06 ........Complainant
Versus
M/s Parsvnath Developers Ltd.
Barakhamba Road
New Delhi-110001 ........Opposite Party
CORAM
N P KAUSHIK - Member (Judicial)
1. Whether reporters of local newspaper be allowed to see the judgment? Yes
2. To be referred to the reporter or not? Yes
N P KAUSHIK – MEMBER (JUDICIAL)
JUDGMENT
Defence relating to the global recession and non-availability of building materials was also dealt with by the Hon’ble National Commission in the case of SwarnTalwar and twoOrs.v. Unitech Ltd. (consumer case No. 347 of 2014 decided on 14.08.2015) National Commission noticed the case of Satish Kumar Pandey&Anr.v. Unitech Ltd. (decided on 8.6.15 in CC No.427/14). The relevant portion of the judgment is reproduced below:-
“Neither any new legislation was enacted nor an existing rule, regulation or order was amended stopping suspending or delaying the construction of the complex in which apartments were agreed to be sold to the complainants. There is no allegation of any lock out or strike by the labour at the site of the project. There is no allegation of any slow down having been resorted to by the labourers of the opposite party or the contractors engaged by it at the site of the project. There was no civil commotion, war, enemy action, terrorist action, earthquake or any act of God which could have delayed the completion of the project within the time stipulated in the Buyers Agreement. It was contended by the Counsel for the OP that the expression ‘slow down’ would include economic slow down or recession in the Real Estate sector. I, however, find no merit in this contention. The word ‘slow down’ having been used alongwith the words lock-out and strike, I have to be read ejusdem generis with the words lock-out and strike and therefore, can mean only a slow down if resorted by the labourers engaged in construction of the project.
As regards, alleged shortage of labour, I find that no material has been placed on record by the OP that despite trying, it could not be get labourers to complete the construction of the project within the time stipulated in the Buyers Agreement. It was submitted by the learned counsel for the complainants that ordinarily big builders such as the OP in these cases, are contracting/sub contracting the construction work to the contractors engaged by them, instead of employing their own labourers on a regular basis, the purpose being to ensure that they are not saddled with the wage bill of those regular laboures, in case the opposite party does not have adequate work for them. There is no evidence of the OP having been invited tenders for appointment of contractors/sub contractors for executing the work at the site of those projects and no contractor/sub contractor having come forward to execute the project on the ground that adequate labour was not available in the market. Therefore, it cannot be accepted that the opposite party could not have arranged adequate labor, either directly or through contractors/sub-contractors, for timely completion of the project. As regards the alleged shortage of water, bricks and sand in the market, I find that there is no evidence filed by the OP, to prove that it was unable to procure water, sand and brick in adequate quantity. This is also their case that the notification of the Government, being relied upon by the opposite party, is an old notification, which was in force even at the time of the opposite party promised possession in 36 months. There is no evidence of the opposite party having invited tenders for supply of bricks and water and there being no response to such tenders. In fact, if the work is to be executed through contractors/sub-contractors, the material such as bricks, andand even water will be arranged by the contractors/sub-contractors and not by the opposite party. As noted earlier, there is no evidence of the opposite party having invited tenders after awarding the work of project in question to the contracts/sub-contractors and there being no response to such tenders. Therefore, I find no merit in the plea that the completion of the project was delayed due to non availability of water, sand and bricks in adequate quantity.”
Hon’ble National Commission also had the occasion to deal with the plea of compensation @ Rs. 5 per sq. ft. per month of the super area in the case of SwarnTalwar (supra). Relevant portion of the judgment is given below:
“It is an undisputed proposition of law that ordinarily the parties are bound by the terms and conditions of the contract voluntarily agreed by them and it is not for a Consumer Forum or even a Court to revise the said terms.
However, a term of a contract, in my view will not be final and binding if it is shown that the consent to the said term was not really voluntary but was given under a sort of compulsion on account of the person giving consent being left with no other choice or if the said term amounts to an unfair trade practice. It was submitted that the learned Counsel for the complainants that the terms providing for payment of a nominal compensation such as Rs.5/- per square foot of the super area having become the order of the day in the contracts designed by big builders a person seeking to buy an apartment is left with no option but to sign on the dotted lines since the rejection of such term by him would mean cancellation of the allotment. He further submitted that a person seeking to acquire a built up flat instead of purchasing a plot and then raising construction on it, therefore, is not in a position to protest resist the inclusion of such a term in the Buyer’s Agreement, and has to rely upon the reputation of the builder, particularly if he is a big builder such as Unitech Ltd. He also submitted that the format of the Buyer’s Agreement is never shown to the purchasers at the time of booking the apartment and if he refuses to sign the Buyer’s Agreement on the format provided by the builder, not only will he lose the booking, even the booking amount/earnest money paid by him will be forfeited by the builder. I find merit in the above referred submission of the learned counsel. A person who, for one reason on the other, either cannot or does not want to buy a plot and raise construction of his own, has to necessarily go in for purchase of built up flat. It is only natural and logical for him to look for an apartment in a project being developed by a big builder such as the opposite party in these complaints. Since the contracts of all the big builders contain a term for payment of a specified sum as compensation in the event of default on the part of the builder in handing over possession of the flat to the buyer and the flat compensation offered by all big builders is almost a nominal compensation being less than .25% of the estimated cost of construction er month, the flat buyer is left with no option but to sign the Buyer’s Agreement in the format provided by the builder. No sensible person will volunteer to accept compensation constituting about 2-3% of his investment in case of delay on the part of the contractor, when he is made to pay 18% compound interest if there is delay on his part in making payment.
It can hardly be disputed that a terms of this nature is wholly one sided, unfair and unreasonable. The builder charges compound interest @ 18% per annum in the event of the delay on the part of buyer in making payment to him but seeks to pay less that 3% per annum of the capital investment, in case he does not honour his part of the contract by defaulting in giving timely possession of the flat to the buyer. Such a term in the Buyer’s Agreement also encourages the builder to divert the funds collected by him for one project, to another project being undertaken by him. He thus, is able to finance a new project at the cost of the buyers of the existing project and that too at a very low cost of finance. If the builder is to take loan from Banks or Financial Institutions, it will have to pay the interest which the Banks and Financial Institutions charge on term loan or cash credit facilities etc. The interest being charged by the Banks and Financial Institutions for financing projects of the builders is many times more than the nominal compensation which the builder would pay to the flat buyers in the form of flat compensation. In fact, the opposite party has not even claimed that the entire amount recovered by it from the flat buyers was spent on this very project. This gives credence to the allegation of the complainants that their money has been used elsewhere. Such a practice, in my view, constitutes unfair trade practice within the meaning of Section 2 ® of the Consumer Protection Act, 1986 since it adopts unfair methods or practice for the purpose of selling the Clauses of Section 2 ® (1) of the Act that would be immaterial considering that the unfair trades, methods and practices enumerated in Section 2 9r) (1) of the Act are inclusive and not exhaustive, as would be evident from the use of word “including” before the words “any of the following practices”.
The abovesaid payment shall be made by the OP to the complainant within a period of thirty days from today failing which the amounts shall carry interest @ 24% p.a. Complaint is accordingly disposed of.
(N P KAUSHIK)
MEMBER (JUDICIAL)
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.