Mrs. Preeti Sehgal filed a consumer case on 25 Apr 2018 against Omaxe Chandigarh Extension Developers (P) Ltd. in the StateCommission Consumer Court. The case no is CC/581/2017 and the judgment uploaded on 07 Jun 2018.
STATE CONSUMER DISPUTES REDRESSAL COMMISSION,
U.T., CHANDIGARH
Complaint case No. | : | 581 of 2017 |
Date of Institution | : | 01.08.2017 |
Date of Decision | : | 25.04.2018 |
Mrs.Preeti Sehgal, W/o Mr.Vikrant Sehgal, R/o H.No.3075, Sector 38-D, Chandigarh.
……Complainant
Omaxe Chandigarh Extension Developers (P) Limited, SCO 143-144, Sector 8-C, Chandigarh, through its Managing Director
.... Opposite Party
Complaint under Section 17 of the Consumer Protection Act, 1986.
BEFORE: JUSTICE JASBIR SINGH (RETD.), PRESIDENT.
SH.DEV RAJ, MEMBER
MRS. PADMA PANDEY, MEMBER
Argued by: Sh.Arjun Grover, Advocate for the complainant.
Sh.Ashim Aggarwal, Advocate for the opposite party.
PER JUSTICE JASBIR SINGH (RETD.), PRESIDENT
The facts in brief are that the complainant, for her residential purpose, purchased a flat bearing no.466, Ground Floor, having built-up area of 1725 square feet, for total cost of Rs.55,60,000/- in a project namely “Omaxe Cassia”, at Mullanpur, Punjab, floated by the opposite party, on making payment of Rs.8 lacs, as booking amount. She opted for construction linked payment plan. Second installment to the tune of Rs.8,61,715/- was paid by her, vide cheques dated 26.08.2011 and 03.09.2011 respectively. Provisional allotment in respect of the said unit was issued in favour of the complainant, vide letter dated 23.12.2011. After about nine months of booking, allotment letter/agreement was executed between the parties i.e. on 18.05.2012. Thereafter, she continued to make payment towards price of the said unit, as and when demanded by the opposite party. In response to email dated 01.03.2013 Annexure C-4, she was assured by the opposite party vide letter dated 25.04.2013 Annexure C-5, that possession of the constructed unit will be offered within a period of 24 months starting from the date of allotment i.e. from 23.12.2011. It was stated that committed period to handover possession of the unit had expired and even till the time, when this complaint was filed, the opposite party failed to offer possession, despite making payment of Rs.51,77,732/- by the complainant towards price of the said unit. It was prayed that let directions be issued to the opposite party to hand over possession of the unit, in question, to the complainant, and also to make payment of interest on the deposited amount, @18% p.a., from the respective dates of payment till delivery of possession; pay compensation for mental agony, physical harassment and also litigation expenses.
First coming to the question, as to whether, while computing the above said period of delay in handing over possession of the unit, Sundays, Saturdays, Bank Holidays, etc. are to be taken into account or not, it may be stated here that a similar question came up for consideration before this Commission in Ankur Gupta Vs. Omaxe Chandigarh Extension Developers Pvt. Ltd. and another, Consumer Case No.309 of 2016 decided on 22.11.2016, and when dealing this issue, it was observed by this Commission, as under:-
“We feel that the contention raised is liable to be rejected. In Clause 23(b) of the Agreement, it is stated that possession will be delivered within 24 months, from the date of allotment letter, with six months extension. It is further stated that when computing the said period all Saturdays, Sundays and Bank Holidays will be excluded. A similar issue came up for consideration before this Commission qua another project of the opposite parties, in the case of Dr.Divya Dahiya Vs. M/s Omaxe Chandigarh Extension Developers Private Limited and another, Consumer Complaint No.57 of 2016, decided on 15.07.2016, wherein, it was observed as under:-
“The first question, which falls for consideration, is, as to whether there was delay in offering possession of the plot, in question, and if so, to what extent. The allotment letter for independent floor in Row-Housing Project “Silver Birch” in the project of the Opposite Parties (Annexure C-4) was issued to the complainant on 30.08.2011. As per Clause 31(a) of the allotment letter, the Opposite Parties were to complete the development of the unit within 24 months or within an extended period of six months from the date of start of construction, subject to force majeure conditions. Since allotment letter is dated 30.08.2011, by computing 24 months plus 6 months period, the Opposite Parties were bound to deliver possession of the plot, in question, by 01.03.2014. The Opposite Parties have stated that period was to be computed by excluding Sundays, Bank Holidays, enforced Govt. holidays and the days of cessation of work at site in compliance of order of any Judicial/concerned State Legislative Body. Apparently, for seeking six months extension beyond 24 months or beyond six months extended period, the Opposite Parties owe an explanation, if the delay was on account of force majure conditions but nothing by way of cogent evidence to this effect has been placed on record. Thus, when no explanation for extension of six months period has been furnished, the Opposite Parties at the most could be allowed one out of the two benefits i.e. either six months extension beyond 24 months or period on account of Sundays/Holidays etc. This Commission in Consumer Complaint No.153 of 2015 titled ‘Mr. Madan Lal Taneja and another Vs. M/s Omaxe Chandigarh Extension Developers P. Ltd.’ decided on 03.11.2015, facts of which were almost identical, held that Opposite Parties were to hand over possession within 30 months from the date of start of construction. Thus, the possession of the unit, in question, was to be delivered by 01.03.2014.”
Similar view has also been reiterated by this Commission, in number of cases, thereafter, in respect of the same project. It was specifically held that when there is no explanation of getting extension of 6 months’ period to deliver possession beyond the stipulated date, the benefit of exclusion of Saturdays, Sundays, Bank Holidays etc. cannot be given. Out of the two benefits, only one can be made available to the opposite party. In this view of the matter, the contention raised by Counsel for the opposite party, being devoid of merit, must fail and the same stands rejected.
Now coming to the plea taken by the opposite party to the effect that as per Clause 23 (h) of the Allotment Letter/Agreement, the complainant is entitled to compensation, only @Rs.10/- per square feet per month of the super area of the unit, it may be stated here that the said Clause would be attracted only in a case, in which the delay is for reasonable period and it has occurred because of cogent unfavorable circumstances. This clause would not apply in the cases, where builder after receiving substantial amount against the agreed consideration, deliberately failed to take any steps for completing construction of the units. In the instant case, opposite party has not shown any cogent circumstances or reason, which prevented it to complete construction of the unit and deliver possession thereof within the stipulated period.
What relief can be granted to a consumer, in case of delay, in offering possession of a residential unit purchased, in the absence of any force majeure circumstances having been faced by the builder, also came up for consideration before this Commission in Ankur Gupta`s case (supra), wherein dealing with similar issue, it was observed as under:-
“What relief can be granted to a consumer, in case of delay, in offering possession, came up for consideration before the Hon’ble National Commission, in a case titled as Parsvnath Exotica Ghaziabad Resident's Association Vs. Parsvnath Buildwell Pvt. Ltd. & Anr., consumer complaint no.45/2015, decided by the Hon’ble National Commission, on 06.05.2016, wherein, it was argued by the project proponent that at the maximum, as provided in the Agreement, the consumer will be entitled to claim penalty for delayed compensation @Rs.5/- per square feet, per month. Noting that in case of delay in making payment, the project proponent was charging heavy penal interest, instead of penal amount, the interest on the deposited amount, for the period of delay was granted, by holding as under:-
“Though, the Agreement between the developer and the flat buyers provides for payment of compensation in case of delay @ Rs.5/- per square feet of the super area per month, such clauses have been found to be unfair trade practice and have been consistently rejected by this Commission in several decision, including Consumer Complaint No. 427 of 2014 Satish Kumar Pandey & Ors. Vs. Unitech Ltd. and connected matters decided on 08.6.2015. Therefore, the aforesaid clauses cannot be taken into consideration, while determining the compensation payable to the members of the complainant association for the aforesaid delay in completion of construction.”
Not only this, in another case, titled as Capt. Gurtaj Singh Sahni & anr. Vs Manager, Unitech Limited & anr., consumer complaint bearing no.603/2014, decided on 02.05.2016, the Hon'ble National Commission, directed the opposite party/builder to pay interest on the deposited amount, for the period of delay, till delivery of possession of the unit. Relevant contents of the said order reads thus:-
“8. If the compensation for the delay in construction is restricted to what is stipulated in the Buyers Agreement, there will be no pressure upon the builder to complete the construction since he will be more than happy to keep on paying paltry compensation of about 3% per annum of the capital investment, instead of arranging funds at much higher cost, to complete the construction.
9. xxxxxxxxxxxxx
10. For the reasons stated hereinabove, the complaints are disposed of with the following directions:
(1) xxxxxxxxxxxxxx
(2) The opposite party shall pay compensation in the form of simple interest @ 12% per annum from the expected date of possession till the date on which the possession is actually offered to the complainants after completing the construction in all respects and obtaining the requisite completion certificate.”
Thus, keeping in view the principle of law laid down by the Hon'ble National Commission, in the cases, referred to above, if interest @12% on the deposited amount for the period of delay, till delivery of possession of the unit, is awarded, that would meet the ends of justice.”
Not only as above, in H.P. Housing Board Vs. Janak Gupta [2009] INSC 627 (26 March 2009) (Civil Appeal No. 6346 of 2002), it was clearly held by the Hon’ble Supreme Court of India that in the cases of delay, in delivery of possession, award of interest @ 12% per annum, on the deposited amount, for the period of delay, would meet the ends of justice. Taking note of above said proposition of law, in the present case also, ends of justice would meet, if interest is granted for delayed period, to the complainant whereof 17.11.2014 till 14.01.2018, when possession was delivered to the complainant.
Besides as above, the opposite party is also liable to pay compensation to the complainant, for providing her deficient service and guilty of adoption of unfair trade practice.
Pronounced.
25.04.2018
Sd/-
(JUSTICE JASBIR SINGH (RETD.) PRESIDENT.
Sd/-
(DEV RAJ)
MEMBER
Sd/-
(PADMA PANDEY)
MEMBER
Rg.
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.