MANOHAR INFRASTRUCTURE AND CONSTRUCTIONS PVT. LTD filed a consumer case on 13 Nov 2024 against OM KUMAR in the StateCommission Consumer Court. The case no is A/320/2024 and the judgment uploaded on 14 Nov 2024.
STATE CONSUMER DISPUTES REDRESSAL COMMISSION,
U.T., CHANDIGARH
Appeal No. | : | 320 of 2024 |
Date of Institution | : | 04.09.2024 |
Date of Decision | : | 13.11.2024 |
……Appellants/opposite parties
Both resident of House No.W2-301, Vatika Lifestyle Homes, Sector 83, Gurgaon (Gurugram)-122004.
….Respondents/complainants
BEFORE: MR. RAJESH K. ARYA, PRESIDING MEMBER.
ARGUED BY
Ms. Garima Pandey, Advocate for the appellants.
Sh. Sanjeev Gupta, Advocate for the respondents.
PER RAJESH K. ARYA, PRESIDING MEMBER
In this appeal, the appellants have assailed the order dated 03.11.2023 passed by the District Consumer Disputes Redressal Commission-I, U.T., Chandigarh (in short the District Commission), whereby the consumer complaint bearing no.233 of 2021 filed by them was partly allowed and they were directed as under:-
“…..In the light of the aforesaid discussion, the present consumer complaint succeeds, the same is hereby partly allowed and OPs are directed as under :-
This order be complied with by the OPs within two months from the date of receipt of its certified copy, failing which, the payable amounts, mentioned at Sr.No.(ii) & (iii) above, shall carry interest @ 12% per annum from the date of this order, till realization, apart from compliance of remaining directions..…”
“….It transpires from the allegations as projected in the consumer complaint that on 22.10.2011, the complainants booked a residential plot measuring 200 sq. yards @ ₹18,500/- per sq. yard in the locality namely ‘Palm Garden’ in the project being developed by the OPs in Mullanpur (New Chandigarh), District SAS Nagar, Mohali (hereinafter referred to as “subject plot”). The complainants were assured that the possession of the subject plot would be handed over within two years as most of the approvals and sanctions had already been received. The complainants submitted application (Annexure C-1) to the OPs and paid booking amount of ₹11,10,000/-, being 30% of the total sale consideration i.e. ₹37.00 lacs, and the OPs acknowledged the said amount by putting stamp on application form (Annexure C-1) itself on 24.12.2011. It was also agreed that the total sale consideration excludes EDC and PLC (if any). A copy of payment plan is Annexure C-2. As the complainants were not having any property near Chandigarh, they wanted to shift to Chandigarh and for that purpose they had purchased the subject plot. Thereafter, the complainants visited the office of the OPs in the month of April 2012 for getting the allotment letter and for execution of buyer’s agreement, but, the complainants were assured by the OPs that the same will be executed within six months. After the aforesaid period, when the complainants again approached the OPs, nothing positive was done. Thereafter, in the month of March 2013 when the complainants raised the issue of delay in commencement of the development works at the project with the OPs, no positive response was given by them and only then the complainants came to know that, in fact, OPs were not having even a single approval for the development of the project, which fact was not disclosed by the OPs to the complainants at the time of receiving the huge amount from them. In the month of March 2014, complainants again approached the OPs for getting the allotment letter and execution of buyer’s agreement and at that time, OPs asked the complainants to further deposit 20% of sale consideration for getting the allotment letter and on this again the complainants deposited ₹7,40,000/- with the OPs and in this manner till 22.4.2014, complainants had paid total amount of ₹18,50,000/- i.e. 50% of the total sale consideration. Even after paying the aforesaid amount to the OPs, they could not execute the allotment and buyer’s agreement and when the complainants visited the project site, they were shocked to see that no development activity was there except that some flags were put at the entrance. Even the representatives of the OPs disclosed that now the CLU was received by the OPs and the development work will be started. Vide letter (Annexure C-3), OPs had undertaken that the allotment would be made by December 2014. It is further alleged that instead of issuing the allotment letter, OPs only issued acknowledgement dated 24.6.2014 (Annexure C-5) to the complainants and on seeing the same complainants were shocked that the OPs had arbitrarily incorporated the condition of paying Govt. levies and IDC (Internal Development Charges) which were not even agreed upon between the parties at the time of booking the subject plot, especially when the basic sale price of the subject plot was ₹18,500/- per sq. yards (excluding EDC and PLC charges). Moreover, there was no need to issue the acknowledgement dated 24.6.2014, when the OPs had already acknowledged the receipt of the booking amount of ₹11,10,000/-. In this manner, the aforesaid act of the OPs in incorporating the condition of payment of Govt. levies and IDC by the complainants in the acknowledgment (Annexure C-5) amounts to indulgence in unfair trade practice. Not only this, as the OPs had received a huge amount from the complainants for the sale of the subject plot, knowing fully well that they were not having the requisite approvals from the competent authorities, the aforesaid act of the OPs amounts to deficiency in service and unfair trade practice. Even till the year 2017, there was no development work on the project site and this manner the OPs could not commence the development of the area in order to provide the subject plot to the complainant. As the OPs have been demanding hidden charges and further started demanding ₹2,000/- per sq. yards towards IDC in the year 2018-19, the said act of the OPs amounts to unfair trade practice on their part. Vide email dated 8.2.2021 (Annexure C-9), the complainants again requested the OPs to issue the allotment letter, but, with no result. Since the complainants have been waiting for the possession of the plot for the last more than 8 years, but, all their hopes have been dashed which caused mental and physical harassment to the complainants. Not only this, the OPs have started demanding more money from the complainants in order to execute the buyer’s agreement, which is against the provisions of The Punjab Apartment & Property Regulation Act, 1995 (hereinafter referred to as “PAPRA”) and Real Estate Regulatory Authority (hereinafter referred to as “RERA”). In this manner, the aforesaid acts of the OPs clearly amount to deficiency in service and unfair trade practice. OPs were requested several times to admit the claim, but, with no result. Hence, the present consumer complaint.”
“….OPs resisted the consumer complaint and filed their written version, inter alia, taking preliminary objections of maintainability, concealment of facts, limitation and also that the complainants are not covered under the definition of consumer. It is further alleged that, in fact, the complainants were informed about the project approval and issuance of CLU in favour of the answering OPs and also about the status of the project at the time of expression of interest was executed. The competent authority had granted completion period till 13.6.2018 towards the project of the OPs, which was later on extended upto 31.12.2022 and it was for the complainants to come forward to execute the plot buyer’s agreement and comply with the terms and conditions. Even otherwise also, without prejudice to the defence of the OPs which was taken, no prejudice would be caused to the complainants if at the initial stage OP company was not having permission from the competent authority since a valid title could have been transferred in the name of the complainants after the allotment of the plot. The OP company had also submitted application for extension of the completion of the project as some part of the mega project was yet to be completed whereas the major portion of the project has already been completed and the competent authority had granted extension regarding completion of the project upto 31.7.2019, which was later on extended upto 31.12.2022. The OP company had acquired land for the mega project and in this manner has been exempted from the provisions of the PAPRA, regarding which notification has already been issued on 25.1.2017. The OP company had submitted application for the mega housing project as it was the owner of more than 100 acres of land and the fixed capital investment was also more than 100 crores and the project was later on sanctioned. However, the project of the OP company was approved on 22.3.2013 by the Govt. of Punjab and thereafter formal agreement was signed and executed with the Govt. on 14.6.2013 and after the addition of more land, the mega project for the total area of 234.37 acres with an investment of ₹845 crores was sanctioned and the competent authority had also granted the completion period for the entire project upto 13.6.2018. In this manner, the case of the OPs was under process and there was some procedural delay on the part of the Govt. in issuing the notification in this regard and the delay in completion of the project was only due to the considerable delay in approval by the Govt. for which the answering OPs are not responsible. It is further alleged that the OP company has already allotted plots to the number of customers who have deposited amount as per the schedule and in this manner the complainants have no locus standi or cause of action to file the present consumer complaint. On merits, the facts as stated in the preliminary objections have been reiterated. The cause of action set up by the complainants is denied. The consumer complaint is sought to be contested.”
“………..41. Any person aggrieved by an order made by the District Commission may prefer an appeal against such order to the State Commission on the grounds of facts or law within a period of forty-five days from the date of the order, in such form and manner, as may be prescribed:
Provided that the State Commission may entertain an appeal after the expiry of the said period of forty-five days, if it is satisfied that there was sufficient cause for not filing it within that period:
“…… a. That the order in the Consumer Complaint bearing no; 233 of 2021 was passed on 03.11.2023 and a copy of the order was dispatched to the Applicants/Appellants on 17.11.2023
b. That the present matter pertains to multi acre project and involved voluminous documents and the same had to be given by the Appellants/Applicants to his counsel. The Applicants hasn't received the brief from the earlier counsel as there was a process of shifting of offices wherein the files pertaining to the said matter were lost. As a result, it took considerable time in the procurement of the contents of the said file. An affidavit to that effect is attached herewith as Annexure A-1. Apart from documents requisite permissions were also to be obtained from the Appellants/Applicants which took a considerable time. It is submitted that a lot of time was spent in procuring and assessing the voluminous documents and hence has resulted into delay for filing the present appeal.
c. That after a considerable lapse of time, finally the counsel for the Appellants/Applicants received the documents and permissions from the Appellants/applicants, delay caused was because of the busy schedule of the parties involved along with the bulkiness of the said documents.….…”
“9. Sufficient cause is the cause for which Defendant could not be blamed for his absence. The meaning of the word “Sufficient” is “adequate” or “enough”, inasmuch as may be necessary to answer the purpose intended. Therefore, the word “sufficient” embraces no more than that which provides a platitude, which when the act done suffices to accomplish the purpose intended in the facts and circumstances existing in a case, duly examined from the view point of a reasonable standard of a cautious man. In this context, “sufficient cause” means that the party should not have acted in a negligent manner or there was a want of bona fide on its part in view of the facts and circumstances of a case or it cannot be alleged that the party has “not acted diligently” or “remained inactive”. However, the facts and circumstances of each case must afford sufficient ground to enable the Court concerned to exercise discretion for the reason that whenever the Court exercises discretion, it has to be exercised judiciously. The applicant must satisfy the Court that he was prevented by any “sufficient cause” from prosecuting his case, and unless a satisfactory explanation is furnished, the Court should not allow the application for condonation of delay. The court has to examine whether the mistake is bonafide or was merely a device to cover an ulterior purpose.”
“12……… . we are not satisfied with the cause shown to justify the delay of 590/601 days. Day to day delay has not been explained. Hon’ble Supreme Court in a recent judgment of “Anshul Aggarwal Vs. New Okhla Industrial Development Authority, IV (2011) CPJ 63 (SC)” has held that – “while deciding the application filed for condonation of delay, the Court has to keep in mind that special period of limitation has been prescribed under the Consumer Protection Act, 1986, for filing appeals and revisions in consumer matters and the object of expeditious adjudication of the consumer disputes, will get defeated if the appeals and revisions, which are highly belated are entertained.”
“5. We are in complete agreement with the view taken by the High Court. Once it was found even by the learned trial Court that delay has not been properly explained and even there are no merits in the application for condonation of delay, thereafter, the matter should rest there and the condonation of delay application was required to be dismissed. The approach adopted by the learned trial Court that, even after finding that, in absence of any material evidence it cannot be said that the delay has been explained and that there are no merits in the application, still to condone the delay would be giving a premium to a person who fails to explain the delay and who is guilty of delay and laches. At this stage, the decision of this Court in the case of Popat Bahiru Goverdhane V. Land Acquisition Officer, reported in (2013) 10 SCC 765 is required to be referred to. In the said decision, it is observed and held that the law of limitation may harshly affect a particular party but it has to be applied with all its rigour when the statute so prescribes. The Court has no power to extend the period of limitation on equitable grounds. The statutory provision may cause hardship or inconvenience to a particular party but the Court has no choice but to enforce it giving full effect to the same.”
Pronounced
13.11.2024
(RAJESH K. ARYA)
PRESIDING MEMBER
Ad
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.