BEFORE THE A.P. STATE CONSUMER DISPUTES REDRESSAL COMMISSIONAT HYDERABAD.
CC 12 of 2011
Between:
Smt. P. V. Nagaratnam
W/o. P. Srinivas Rao
Age: 37 years, House Wife
R/o. Flat No. 506
Shanthi Apartments,
Bhagyanagar Colony
Opp. KPHB, Kukatpally
Ranga Reddy Dist. *** Complainant.
And
M/s. Constructions
Rep. by V. Venkateshwarlu
S/o. V. Polaiah, Age: 44 years
Plot No. 195/C, Western Hills
Opp. JNTUC, Kukatpally
Hyderabad-500 072. *** Opposite Party
Counsel for M/s. K. Ram Murthy
Counsel for the Resp: M/s. T. Aruna Chalam
CORAM:
HON’BLE SRI JUSTICE D. APPA RAO, PRESIDENT
SMT. M. SHREESHA, MEMBER
&
SRI S. BHUJANGA RAO, MEMBER
TUESDAY, THE TWENTIETH DAY OF MARCH TWO THOUSAND TWELVE
Oral Order: (Per Hon’ble Justice D. Appa Rao, President)
***
1) This is a complaint under Consumer Protection Act u/s 17(a)(i) of the Consumer Protection Act seeking the following prayers:
i. To pay the loss of Rs. 24,30,000/- on account of non-construction of 2,700 sft and 45% share of the complainant i.e., 1215 sft @ Rs. 2,000/- per sft.
ii. To pay the outstanding construction work in five of complainants share @ Rs. 3 lakhs per flat and total of Rs. 15 lakhs.
iii. To pay the rental value of Rs. 7 @ Rs. 30,000/- per month from 1.1.2009 till the date of payment.
iv. To pay the erection of transformer and providing of individual meters and internal electrical wiring with switches etc. at Rs. 2 v. To pay for providing of municipal water supply at Rs. lakhs.
vi. To pay for parking area flooring Rs. 3 lakhs.
vii. To pay for lift Rs. 3 lakhs.
viii. To pay for building common area Rs. 4 lakhs.
ix. To pay the penal as deemed fit from 1.1.2009 till the date of completion.
x. To pay of present complaint.
2) The case of the complainant in brief is that she hired the services of the opposite party construction company for construction of apartments under development agreement-cum-GPA It had developed 15,300 sft as against 18,000 sft as agreed. Even after three years of the agreement it did not finish the construction and development work for which she gave a notice. It gave reply stating that two flat Nos. 203 and have been handed over by completing 80% of the work after obtaining loan on said flats. The complainant had to pay Rs. There less extent than mentioned in the agreement besides objections from neighbours for which the complainant gave a detailed reply. In fact it has started selling the flats fell to its share leaving the complainant’s share of 45%. Non-completion of even a single flat huge financial loss as well as rentals. She estimated the left out works and un-constructed built up area by computing at Rs. 55 lakhs. Therefore she prayed that the above amount be paid besides erection of transformer, internal electrical wiring, providing municipal water, parking area and other works mentioned in the reliefs.
3) The opposite party did not choose to file written version despite granting several adjournments.
4) The complainant in proof of her case filed affidavit evidence and got Exs. A1 to marked.
5) The opposite party did not avail the opportunity of filing affidavit controverting the evidence of the complainant.
6) The points that arise for consideration
I. Whether the complainant is entitled to flooring and of five flats a sum of Rs. 15 lakhs @ Rs. 3 lakhs?
II. Whether she is entitled to a sum of Rs. 24 2700 sft.?
III. Whether the complainant is entitled to Rs. 2,25,000/- towards erection of transformer?
IV. Whether the complainant is entitled Rs. 4 lakhs towards municipal water?
V. Whether the complainant is entitled an amount of Rs. 3 lakhs towards parking area?
VI. Whether the complainant is entitled to Rs. 3 lakhs towards lift facility and Rs. 4 lakhs towards common area colouring?
VII. Whether the complainant is entitled to Rs. 7
7) It is an undisputed fact that the complainant is an owner the property consisting of 770.77 sq.yds in S.No. 133 and 134 situated at Madinaguda of Serilingampally mandal in Ranga Reddy district evidenced under Encumbrance Certificate Ex. A6. The opposite party entered into a development agreement-cum-GPA Ex. A1 & A2 dt. It was agreed that the complainant was entitled to 45 while the opposite party was entitled to 55% of share in the proposed construction. Ex. A8 supplementary deed dt. there is a categorical mention as to the shares fell to each of the parties viz. 102, 103, 203, 302 and fell to the share of the complainant while the remaining flat Nos. 101, 201, 202, 301, 303, 402 and 403 fell to the share of the builder vide Ex. A8. It seems that the opposite party had sold some of the flats fell to his share vide Ex. A6 Encumbrance Certificate.
8) When the opposite party did not complete the construction as per the nor handed over the flats, she got issued Ex. A3 registered lawyer notice on 4.9.2010 for which the opposite party gave reply under Ex. A4. While the execution of the agreement, however it alleged that it was facing problems from north side boundary as the government was claiming that it was its land. Anjaneyulu filed a case against the original pattadar by name Purnachander and was creating problems. It has already handed two flats to the complainant wherein 80% of work was completed. had agreed to pay Rs. 30 lakhs but failed to pay the same. Though the agreement provides actual extent of 770 on calculation it came to a lesser extent. However, he stated that he ready to develop the above property as per the norms if the complainant fulfilled the above said lacunas He would hand over the share of the complainant, as per ratio, agreed.
9) For the reasons not known the opposite party did not substantiate any of the objections raised by it in its notice. The complainant by filing her affidavit evidence supporting documents proved that flooring and finishing of five flats were not completed. Built up area of 1215 sft was not handed over besides erection of transformer, municipal water supply, parking area, lift facility, common area colouring etc. To substantiate the same she the valuation report of Hari Krishna Architects & Constructions marked as Ex. A9. He inspected and found that the work was still going though it was commenced in 2008. He the total value of the balance work at Rs. 27,86,000/-. He had given details of each work running into 20 pages. Since the opposite party did not controvert any of the facts, and in the light of technical valuation made by an architect, we are of the opinion that the complainant is entitled to the following amounts.
i. Flooring and finishing of five flats Rs. 15,00,000/-
(Rs. 3 lakhs x 5 flats)
ii. To be built up area of 1215 @ Rs. 24,30,000/-
2,000/- per sft.
iii. Erection of transformer etc. Rs. 2,25,000/-
iv. Municipal water Rs. 4,00,000/-
v. Parking area flooring Rs. 3,00,000/-
vi. Lift facility Rs. 3,00,000/-
vii. Building common area colouring Rs. 4,00,000/-
----------------------
Total Rs. 55 ----------------------
The complainant also Rs. 7,20,000/- towards rentals. There is no in the agreement for payment of rentals in case of delay. The complainant could not establish the rents prevailing in the locality. She could not establish as to the time stipulated for completion of the in order to award some rents to her. In the circumstances, we are unable to any amount towards rents. In view of delay and non-completion, we are of the opinion a sum of Rs. 5 could be awarded towards compensation for mental agony and harassment.
10) In the result the complaint is allowed in part directing the opposite party to pay in all Rs. 55,55,000/- together with compensation of Rs. 5 lakhs and costs of Rs. 20,000/-. Rest of complaint is dismissed.
1) _______________________________
PRESIDENT
2) ________________________________
MEMBER
3) ________________________________
MEMBER
APPENDIX OF EVIDENCE
WITNESSES EXAMINED
COMPLAINANT OPPOSITE PARTY
None None
Documents marked for complainant:
Ex A-1 Certified copy of Document No. 12086/2007 of Irrevocable Development Agreement Cum GPA
Ex A-2 Copy of Document No. 12140 /2007 of Irrevocable Development Agreement cum GPA
Ex A-3 Copy of Legal notice to the Respondent 4..09..2010
Ex A-4 Original Copy of Reply to Legal notice 29.9.2010
Ex A-5 Certified copy of Reply to Reply notice 7.12..2010
Ex A-6 & 7 original copy of Encumbrance certificates 20.11.2010
Ex A-8 Supplementary Deed dated 24.12.2008
Ex A-9 Original copy of balance work valuation by an Architect 13.6.2011
1) _______________________________
PRESIDENT
2) ________________________________
MEMBER
3) ________________________________
MEMBER
20/03/2012
*pnr