BEFORE THE A.P STATE CONSUMER DISPUTES REDRESSAL COMMISSION AT HYDERABAD.
C.C. 17 of 2011
Between:
1) N. V. G. Krishna Kumar
S/o. N. L. Narsimha Rao
2) Smt. N. Sandhya Kumari
W/o. NVG Krishna Kumar
Both R/o. Pruthvi Apartments
Block No. 2, Flat No. C1
12-5-49/1, Vijayapuri
Tarnaka, Secunderabad. *** Complainants
And
M/s. Ascent Infratech Properties India (P) Ltd.,
Rep. by its Managing Director
SNV Siva Kumar Raju,
S/o. Late Rama Krishnam Raju
O/o. # 207, Rama Krishna Nivas,
Plot Nos. 23, 24, 27 & 28
Sai Kunj Layout, Bachupally,
Ranga Reddy Dist. *** Opposite Parties
Counsel for the Complainant: M/s. B.N. Swamiji
Counsel for the Respondents: Ex-parte.
CORAM:
HON’BLE SRI JUSTICE D.APPA RAO, PRESIDENT.
SRI R. L. NARASIMHA RAO, MEMBER
&
SRI T. ASHOK KUMAR, MEMBER
THURSDAY, THE SECOND DAY OF SEPTEMBER TWO THOUSAND ELVEN
ORAL ORDER: (Per Hon’ble Sri Justice D. Appa Rao, President)
***
1) This is a complaint filed u/s 17(a)(1) of the Consumer Protection Act for the following reliefs:
I. To direct the opposite party to complete the pending works in all aspects and hand over the flat No. 204, admeasuring 1630 sft in Viswanadha Residency, Bachupalli, Ranga Reddy Dist.
II. To pay interest @ 36% p.a., on an amount of Rs. 34.50 lakhs from 10.62008 till date.
III. To pay Rs. 5 lakhs towards mental agony and trauma suffered by the complainants.
IV. To pay Rs. 5,000/- towards costs.
2) The case of the complainants in brief is that he purchased a flat No. 204 admeasuring 1630 sft from the opposite builder/developer for a consideration of Rs. 35 lakhs though the actual cost was Rs. 38,50,000/- including registration charges. He had paid an amount of Rs. 34,50,000/- on various dates in all 90% of the cost. However, the opposite party had agreed to complete the construction within 10 months from the date of agreement viz., by 15.9.2008. Despite the above payment the opposite party did not complete the structures viz., staircase, railing inside and outside, electrical fittings, plumbing fittings, wall paintings, floor polishing nor provided car parking area, water and sewerage arrangements etc. It had agreed to pay Rs. 8,000/- per month from 15.9.2008 to 14.6.2010 which comes to Rs. 1,68,000/- towards rent and future rent till handing over of possession. The banker forced him to pay the loan amount and closed the account on 12.1.2009. He had to pay Rs. 4 lakhs towards balance. Though it executed registered sale deed it did not hand over possession. While so on 24.5.2010 the opposite party issued legal notice for which he gave reply demanding interest @ 36% p.a., on Rs. 34,50,000/- from 10.6.2008 which would come to Rs. 24.84 lakhs. The opposite party had to pay Rs. 1.68 lakhs rent + interest Rs. 24.84 lakhs in all Rs. 26.52 lakhs. After deducting a sum of Rs. 4 lakhs payable by him the opposite party has to pay Rs. 22.52 lakhs. Therefore while directing the opposite party to complete the pending works sought for recovery of Rs. 34.50 lakhs with interest @ 36% p.a., besides Rs. 5 lakhs towards compensation for mental agony and Rs. 5,000/- towards costs.
3) Despite several notices and even to the last known address notices were returned with endorsement ‘left’. Since it is the last known address the notice deemed to be sufficiently served as provided u/s 28A (4) of he Consumer Protection Act. It reads as follows:
28A. Service of notice, etc. - (1) All notices required by this Act to be served shall be served in the manner hereinafter mentioned in sub-section (2).
(2) The service of notices may be made by delivering or transmitting a copy thereof by registered post acknowledgment due addressed to opposite party against whom complaint is made or to the complainant by speed post or by such courier service as are approved by the District Forum, the State Commission or the National Commission, as the case may be, or by any other means of transmission of documents (including FAX message).
(3) When an acknowledgment or any other receipt purporting to be signed
by the opposite party or his agent or by the complainant is received by the District Forum, the State Commission or the National Commission, as the case may be, or postal article containing the notice is received back by such District Forum, State Commission or the National Commission, with an endorsement purporting to have been made by a postal employee or by any person authorized by the courier service to the effect that the opposite party or his agent or complainant had refused to take delivery of the postal article containing the notice or had refused to accept the notice by any other means specified in sub- section (2) when tendered or transmitted to him, the District Forum or the State Commission or the National Commission, as the case may be, shall declare that the notice had been duly served on the opposite party or to the complainant :
Provided that where the notice was properly addressed, pre-paid and duly sent by registered post acknowledgment due, a declaration referred to in this sub-section shall be made notwithstanding the fact that the acknowledgment has been lost or mislaid, or for any other reason, has not been received by the District Forum, the State Commission or the National Commission, as the case may be, within thirty days from the date of issue of notice.
(4) All notices required to be served on an opposite party or to complainant shall be deemed to be sufficiently served, if addressed in the case of the opposite party to the place where business or profession is carried and in case of complainant, the place where such person actually and voluntarily resides.
4) The complainants in proof of their case filed their affidavit evidence and got Exs. A1 to A19 marked.
5) The points that arise for consideration are :
i) Whether the complainants are entitled to any amount?
ii) Whether the opposite party is liable to finish the pending works?
iii) If so to what relief?
6) It is an undisputed fact that the complainant has purchased flat No. 204 admeasuring 1630 sft in Viswanadha Residency, Bachupalli in Ranga Reddy for a sum of Rs. 35 lakhs vide agreement of sale Ex. A7 however an amount of Rs. 9,11,500/- was mentioned in the registered sale deed dt. 15.11.2007 Ex. A10. It is also not in dispute that at the earliest the opposite party issued legal notice on 24.5.2010 vide Ex. A14 demanding balance of Rs. 4 lakhs.
7) From the pleadings as well as affidavit evidence it is beyond doubt that the opposite party executed registered sale deed for the flat as long back as on 15.11.2007. It is also not in dispute that the possession was also delivered. Now the complainant alleges that some of the constructions were not completed. To prove the said fact he filed some photographs. It is not known why the complainant all through not demanded for completion of those structures while the possession was delivered to him way back on 15.11.2007. Evidently, the sale deed for a lesser amount was taken, obviously to evade lawful stamp duty and registration charges to the Government. The complainant equally for the reasons not known did not take out either a Commissioner or an Engineer to certify that structures were not completed. In fact pending works were valued in the agreement of construction dt. 15.11.2007 at Rs. 1,89,500/-. What all it was mentioned was “ the developer agreed to complete the following works as mutually agreed over the said property as follows :
Structure: RCC framed structure
Walls mortar Table moulded red bricks in cement
Super Structure: Plastering on both inside and outside
Main doors & Windows: Frames with MS safety grills
The above work has been estimated to a tune of Rs. 1,89,500/- and the pending work will be completed within a period of 10 months from this date of agreement. The amount of Rs. 1,89,500/- will be paid by the purchaser to the developer.”
8) The complainant was unable to show the stipulation where the opposite party has agreed to pay the rent. There is no stipulation if the works are not completed within a period of 10 months the opposite party would pay rent or any amount as contended by the complainant. If really that were to be so, he could have filed the affidavit evidence of remaining flat owners. Except his self-serving testimony it is neither evidenced by the documents nor from construction agreement. Obviously as the opposite party demanded balance sale consideration the complainant has come up with this complaint to complete some of the structures, however, claimed the amount towards rent and interest @ 36% p.a., computing more than what he had to pay towards balance of sale consideration. He himself admits that he lost his job, and therefore was unable to pay. It is clear that the opposite party in order to claim remaining balance threatened it would take action for recovery of amount. The disbursement letter issued by the complainant addressed to the bank to release an amount of Rs. 4 lakhs was not honoured. Therefore the opposite party cautioned the complainant that it would take action u/s 420 of IPC. On that the complainant claimed these amounts. It is not known how he could get interest @ 36% p.a., that too on the amount, which the opposite party had agreed to pay towards rents, the stipulation of which does not find in the agreement. What all the complainant is entitled to is for a direction to complete the unfinished works provided pays Rs. 4 lakhs towards balance of sale consideration. In regard to other claims the complainant could not substantiate, therefore, we are unable to grant the same.
9) In the result the complaint is allowed in part with costs computed at Rs. 5,000/- directing the opposite party developer to complete the unfinished works within two months on receipt of Rs. 4 lakhs payable by the complainant.
1) _______________________________
PRESIDENT
2) ________________________________
MEMBER
3) ________________________________
MEMBER
APPENDIX OF EVIDENCE
Witnesses examined for Complainants: None
Witness examined for opposite party: None
Documents marked for complainants:
Ex A-1 Receipt for an amount of Rs.2,00,000/- issued by opposite party dt : 24.10.2007
Ex A-2 Receipt for an amount of Rs.2,00,000/- issued by opposite party dt : 24.10.2007
Ex A-3 Receipt for an amount of Rs.2,00,000/- issued by opposite party dt : 24.10.2007
Ex A-4 Receipt for an amount of Rs.2,30,000/- issued by opposite party dt : 24.10.2007
Ex A-5 Receipt for an amount of Rs.2,70,000/- issued by opposite party dt : 24.10.2007
ExA-6 Receipt for an amount of Rs.1,50,000/- issued by opposite party dt : 24.10.2007
Ex A-7 Copy of Agreement of Sale dt : 25.8.2007
Ex A-8 Part Disbursement Letter issued Axis Bank dt : 1.11.2007
Ex A-9 Statement of Account dt : 10.6.2008
Ex A-10 Copy of Registered Sale Deed bearing Document No. 1554 /2007
dt :15.11.2007
Ex A-11 Copy of Registered Agreement of Construction for Semi Finished Flat bearing Document No. 1554/2007 dt : 15.11.2007
Ex A-12 Letter for Closure of Loan account issued by Axis Bank dt : 12.1.2009
Ex A-13 Certificate of Closure of Loan of complainant No.1 dt : 12.1.2009
Ex A-14 Legal notice issued by counsel for opposite party dt : 24.5.2010
Ex A-15 o/c of Reply notice dt : 2.6.2010
Ex A-16 Returned postal acknowledgement duly signed by counsel for opposite party dt : 8.6.2010.
Ex A-17 Returned postal Cover from opposite party dt : 8.6.2010
Ex A-18 Photographs (13 nos) and CD dt : 31.5.2010.
1) _______________________________
PRESIDENT
2) ________________________________
MEMBER
3) ________________________________
MEMBER
02/09/2011
*pnr
UP LOAD – O.K.