West Bengal

Kolkata-II(Central)

CC/98/2019

Subhasish Pahari - Complainant(s)

Versus

M/S. Unnayan Developers Pvt. Ltd. - Opp.Party(s)

Madanmohan Das

22 Nov 2021

ORDER

DISTRICT CONSUMER DISPUTES REDRESSAL COMMISSION
KOLKATA UNIT - II (CENTRAL)
8-B, NELLIE SENGUPTA SARANI, 7TH FLOOR,
KOLKATA-700087.
 
Complaint Case No. CC/98/2019
( Date of Filing : 20 Mar 2019 )
 
1. Subhasish Pahari
Vill-Deulbarh, P.O.Deulbarh, P.S. Marishda, Dist-Purba Medinipur, Pin-721427.
2. Sucharita Kar Pahari
Vill-Deulbarh, P.O.Deulbarh, P.S. Marishda, Dist-Purba Medinipur, Pin-721427.
...........Complainant(s)
Versus
1. M/S. Unnayan Developers Pvt. Ltd.
47/1K, Hazra Road, P.S. Ballygunge, Kolkata-700019.
............Opp.Party(s)
 
BEFORE: 
 HON'BLE MR. Swapan Kumar Mahanty PRESIDENT
 HON'BLE MRS. Sahana Ahmed Basu MEMBER
 HON'BLE MR. Ashoke Kumar Ganguly MEMBER
 
PRESENT:Madanmohan Das, Advocate for the Complainant 1
 
Dated : 22 Nov 2021
Final Order / Judgement

FINAL ORDER/JUDGEMENT

 

SHRI SWAPAN KUMAR MAHANTY, PRESIDENT

 

  

           Briefly stated, the facts of the case are that the complainants had entered into an Allotment Agreement  dated 17.04.2010 with the OP M/s. Unnayan Developers (P) Ltd. for purchase of  a land measuring about 4 Cottahs 0 Chittak 0 Sq. ft. comprised in  Dag No. 370, under Khatian  No.770, Mouza- Balakhali, being Plot No. A-26 at a total consideration of Rs. 4,20,000/- to be paid by 48 equal monthly installments.  Complainants further pleaded that in terms of  the Allotment Agreement , they  had already paid Rs. 4,20,000/- to the OP by cash and cheque.   The OP should have developed the said Project Site with construction of metal road along with side drain and other necessary work pertaining to the basic infrastructures within a period of  48 months for which the complainant shall  have to pay Rs. 20,000/- per cottah towards  costs of the water connection and electricity. The OP has failed and neglected to fulfill the terms of the Allotment Agreement.  As a result, complainants lost their hope. No positive assurance was offered on the part of the OP when the project would be completed in habitable condition. Having no other alternative, the complainants claim refund of money paid to the OP. OP is deficient in rendering service and attitude of the OP is tantamount to unfair trade practice. Hence, the complainants have  filed the instant Consumer Complaint seeking direction upon the OP to refund Rs.4,20,000/- along with interest   at the rate of 18  percent P.A., Rs. 2,00,000/- for mental agony and harassment including Rs. 15,000/- as litigation cost.

          The complaint is resisted by the OP by filing a written version in which they have stated that the complainants are not “consumers” as define under the Consumer Protection Act. It is specifically mentioned in clause 12 of the Allotment Agreement  that Rs.  20,000/- per cottahs will have to be paid in addition to the price mentioned in the clause of the allotment agreement. Thus, total price of the land is Rs.  5,00,000/- including water connection and electricity. Total consideration amount was to be paid in 48 equal monthly installments. Timely payment of monthly installments was condition precedent for availing the said benefits. It was provided in clause 4 of the said agreement if the complainant failed to pay monthly installment on due time they would pay interest  at the rate of 10  percent P.A.  Equally in clause 22 of the said agreement it was provided that if the company failed to complete the project within time, the complainants may take refund of the money paid by the interest  at the rate of 10  percent subject to the condition that if the allotee avail the benefit of weaver of interest as provided in clause 4 of the agreement, they will not get any interest while getting back the money in terms of clause 22 of the agreement. On execution of the agreement the complainants did not pay EMIs on due time for which they are not liable to get interest.  Complainants  did not pay interest and, therefore, they cannot claim interest over the refund amount.  There is no negligence on the part of the OP and / or any attitude of the OP which tantamount to unfair trade practice. Accordingly, the OP has prayed for dismissal of the complaint.

            To prove their case both parties have adduced evidence on affidavit. They have also filed questionnaires and replies vis-à-vis relevant documents in support of their respective cases. We have also examined the entire material on record and given a thoughtful consideration to the arguments advance before us.

            Fact remains that there was an Allotment Agreement dated 17.04.2010 between the parties to the complaint petition in respect of the subject plot of land and the OP is liable to develop with infrastructure of the plot. The Ld. Advocate for the OP has contended that the complainants are not consumers and there is no negligence on the part of the OP which tantamount to unfair trade practice.  In a decision reported in 04 SCC 407 (U.T. Chandigarh Administration and Anr. Vs. Amarjeet Singh and Anr.)  the Hon’ble Apex Court duly discussed the vide connotation of the terms “consumer ” and “service ” under the Consumer Protection Laws and reiterated the observations of the Hon’ble Supreme Court in Lucknow Development Authority   vs. M K Gupta. In such scenario the OP as service provider is obligated to fascilate the utilization and enjoyment of plot as intended by allottees and set out in the Allotment Agreement  .

            We have considered the contentions and perused the record. In order to properly appreciate the contentions of the parties, it is necessary to have look clause – 11 of the Allotment Agreement dated 17.04.2010 which reads thus :

            “ The Company shall develop the said land on behalf of the Allottee with construction of metal road to reach the plots of land along with side drains and other necessary works pertaining  to the basic infrastructure such as water supply, electricity connection and telephone connection, which shall be completed within the period of payment of 48 installments.’’

            On reading of the aforesaid clause, the OP is required to provide the requisite basic infrastructure and therefore has to render services within the meaning of Consumer Protection Act. We agree with the law laid down by the Hon’ble NCDRC in the case of ‘ Unnayan Builders Pvt. Ltd.- VS- Sona Bera decided on 16.03.2018 in Revision Petition No. 715 of 2018 that the complainants are  consumers within the meaning of Consumer Protection Act. As such, we devoid the submission of the learned Advocate for the OP that complainants are not Consumers within the meaning of C.P. Act. The decision relied by the Learned Advocate for the complainants clearly indicate that complainants are “Consumers” within the meaning of C.P. Act. Thus,   we are of the opinion that complainants are the “consumers” according to the Consumer Protection Act.

          In course of hearing, the Learned Advocate for the OP has submitted that the case  of the complainants is based on a document which is unstamped and the allotment letter  dated 17.04.2010 was typed on  non-judicial stamp paper of Rs.10/- though the value of the land in question is Rs.4,20,000/-. He has further contended that U/section 2 (14) of the Indian Stamp Act, “ Instrument “ includes every document including the Agreement of Allotment of a immovable property and due to explanation added to Item No. 5 of schedule “1A” even in case of more agreement to transfer or delivery of possession of a immovable property with an intention to transfer  right, title and interest of such property at any future date by executing  separate conveyance, such agreement is to be stamped as if it is  a conveyance as mentioned in Item No. 23 of the said schedule. Therefore, the Allotment Agreement dated 17.04.2010 should be stamped according to item No. 23 of the schedule “1A” of Section 35 of the Indian Stamp Act. According to him, the unstamped agreement dated 17.04.2010 cannot be taken into evidence. He has further urged that vide Indian Stamp (West Bengal Amendment) Act, 1990 (W/V, Act XVII) Section 6 (a) (w.e.f. 31.01.1994) authorize the collector to impugned any instrument which has not been executed but is brought to him under section 31 for determination the duty with which the instrument is chargeable or any instrument which he is authorized to endorse U/s 32. In support of such contention, the Ld. Advocate for the OP has cited four decisions reported in 2009 (1) Supreme 58 (Avinash Kumar Chauhan -Vs- Vijay Krishna Mishra),  2001 (2) Supreme 365 (Chilakuri Gangulappa -Vs- Revenue Disposal Officer, Madanpalle & Another), 1999 (2) CHN 369 (Dr. Swapnadin Lahiri vs. Tridib Das Rai with Chittarnjan Jaan Vs. Arun Kumar Jana and  M/s Magma Fincorp Ltd. Vs Rajesh Kumar Tiwari  (Civil Appeal No. 5622/2019).

         The Ld. Advocate for the OP has further submitted that there is disruption of development work as many customers who booked the plots did not pay the balance consideration price in terms of Clause-12 of the Allotment Agreement and the OP is ready and willing to refund the advance amount after deducting interest  at the rate of 10  percent P.A. from the date of installments became due.  He further submitted that the complainants did not pay EMIs in due time including development charges.

           Per-contra, the Learned Advocate for the complainants has submitted that the OP prepared the Allotment Agreement on a non-judicial stamp paper of Rs.10/- and the instant complaint has been filed for deficiency in service for non-delivery of possession of the plot in question in the project  “Madhuban” by the OP after developing the basic infrastructure. According to him, the complainants have entered into an agreement with the OP for possession of the plot after completion of infrastructure against consideration of Rs.4,20,000/-. Complainants have already paid the entire consideration amount  but the OP has not yet completed the infrastructure  within the stipulated period on receiving full  payment. In support of his contention, the Ld. Advocate for the complainants referred two Judgments of Hon’ble NCDRC passed in First Appeal No.670 of 2018 dated 27.04.2018 and Hon’ble SCDRC West Bengal passed on 08.08.2018 in connection with C. Case No.402/2014 (Pijush Chakraborty  - Vs - Unnayan Builders Pvt. Ltd.).

           We have perused the above cited decisions of the Ld. Advocates of the parties and also considered the evidence as well as documents on record.

           It is true that the complainants had entered in to an Allotment Agreement with the OP on a non-judicial stamp paper of Rs.10/- for purchasing a plot of land measuring about 4 Cottahs 0 Chitak 0 sq. ft. situated at Dag No.370, under Khatian  No.777, Mouza- Balakhali, being Plot No. A-26 at a total consideration of Rs. 4,20,000/- excluding development charges. Complainants have paid entire amount to the OP on different dates.

          On reading of the clause-11 of the Allotment Agreement, it is clear that the OP shall develop the said plot of land on behalf of the Allottee with construction of metal road to reach the plot of land along with side drains and other necessary works pertaining to the basic infrastructure which shall completed within the period of payment of 48 installments. The plea of the OP is that the complainants did not pay the EMIs regularly, as such, they are liable to pay interest.  OP in its written version has admitted that they could not completed the development work within the specified time as many customers did not pay their EMIs in time though the complainants have not paid development charges.

           In the first cited decision it was held that if a document is not properly stamped the same cannot be admitted into evidence even for collateral purpose because the bar provided in Section 35 of the Indian Stamp Act. In the second cited decision it was held that the party produces a document which is not properly stamped and if the Court chooses to admit the document, the Court will ask the party to pay the stamp duty together with penalty amount to ten times the deficiency of stamp duty. If party concerned refused to pay the said amount, the Court has no option except to impound the document and forward the same to the Collector. After receipt of the opinion of the collector, the court will collect the amount from the party who produced the said document. All the three decisions cited by the Learned Advocate for the OP are in respect of matters related to non-payment of stamp duty in a matter arising out of Civil Suits. The judgment passed in Civil Appeal  5622/2019  (M/s Magma FinCorp Ltd. Vs. Rajesh Kumar Tiwari) as has been relied upon by the Ld. Advocate for the OP is distinguishable on facts, in as much as such judgment is related to Hire  Purchase  Agreement. Thus, the above cited decision is not help to the OP.

          We have gone through the decisions cited by the Ld. Advocate for the complainants. The Hon’ble NCDRC in First Appeal No. 617 of 2018 (Unnayan Builders Pvt. Ltd. –Vs- Nabhanil Mondal) has been pleased to observe that in the pleadings of the parties that the Developer had entered into a transaction with the complainant for developing plot and making the development plot available to him for a consideration within a period of four years from the date of agreement on which the agreement was executed between the parties. The onus, therefore, is upon the OP to prove either that it had developed the plot and offered its possession to the complainant within the stipulated period or that the development could not completed on account of reasons beyond its control.

          On perusal of the written version we find that the OP has taken a plea that several plot buyers have failed to make payment to them in time. In our opinion, if other plot buyers failed to honour their commitment, in that event, the OP, could not have a ground for not completing the development of the plot, which is the subject matter of the Agreement. The OP ought to have arrange financers from the alternative sources and complete the development work. As such, the complainants cannot be made any suffer without there being any default on their part. Therefore, the submission made by the Ld. Advocate for the OP that the allotment agreement between the parties about sale of plot of land was not come under the purview of the Act has no force at all.

            The intent and object behind the legislation of the Act to adopt a constructive approach and not to bagged down by hyper technicalities of procedure. A Consumer commission is primarily meant to protect to the consumers and their claims cannot be defeated on technical grounds. In fact, the alleged non-payment of stamp duty and non payment of installment is not at all material for the purpose of determining the question whether  there is any deficiency in service U/s 2 (11)  of the Act. Since the agreement has been signed by the parties with their open eyes, it indicates that they have accepted the terms and conditions of the said agreement. Therefore, after accepting full consideration amount, the OP has no locus-standi to raise any objection that the agreement is not properly valued or stamped as per provision of Section 35 of the Indian Stamp Act.

            Clause-22 of the Agreement between the parties provides –

“22. In the event of the Company failing to complete the project within the stipulated time, the allottee may take refund of the full money paid him / her towards price of the land with interest   at the rate of 10 percent P.A.”

             Needless to say, the parties are bound by the Agreement. Both the parties have signed the Agreement of Allotment with full knowledge and understanding about its contents.   Therefore, the OP is liable to pay interest  at the rate of 10  percent P.A. to the complainants.  

                Based on foregoing  discussion, in the given facts and relying upon the cited decisions of the Hon’ble Supreme Court and the entire evidence adduced before us,  we  are of the considered opinion that the complainants are consumers under section 2 (7 ) CP Act.  There is deficient in rendering service and indulged in unfair trade practice by the OP. As such, the complainants are entitled to refund an amount of Rs. 4,20,000/- along with compensation in the form of interest thereon  at the rate of 10  percent P.A. from the date of payment till its recovery.

          In view of the discussion above, the complaint is allowed with following directions:-

            1. OP is directed to refund Rs. 4,20,000/- only together with interest  at the rate of 10  percent P.A. from  the date of payment till its realization to the complainants within 60 days from the date of order.

             2. OP is also directed to pay litigation cost of Rs. 5,000/- to the complainants within the stipulated period as mentioned. 

          A copy of judgment be provided to the parties as mandated by the Consumer Protection Act. The judgment be uploaded forthwith on the website of this commission for perusal of the parties.

Dictated & Corrected by

 

 

 

 

President      

     

                                Member (L)                   Member (M)               President

 

 

 

 
 
[HON'BLE MR. Swapan Kumar Mahanty]
PRESIDENT
 
 
[HON'BLE MRS. Sahana Ahmed Basu]
MEMBER
 
 
[HON'BLE MR. Ashoke Kumar Ganguly]
MEMBER
 

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.