NCDRC

NCDRC

CC/2737/2017

ATIN GOEL - Complainant(s)

Versus

M/S. UNITECH LTD. - Opp.Party(s)

MR. AMIT SAXENA

21 Dec 2018

ORDER

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION
NEW DELHI
 
CONSUMER CASE NO. 2737 OF 2017
 
1. ATIN GOEL
...........Complainant(s)
Versus 
1. M/S. UNITECH LTD.
(THROUGH ITS MD) REGD. OFFICE AT : 6, COMMUNITY CENTRE, SAKET,
NEW DELHI-110017.
...........Opp.Party(s)

BEFORE: 
 HON'BLE MR. JUSTICE V.K. JAIN,PRESIDING MEMBER

For the Complainant :
Mr. Amit Saxena, Advocate
For the Opp.Party :NEMO

Dated : 21 Dec 2018
ORDER

JUSTICE V.K.JAIN, PRESIDING MEMBER (ORAL)

          The complainant Atin Goel booked a residential flat with the OP in a project namely ‘Exquisite’ in Nirvana Country-2 which the OP was to develop in Gurgaon.  Flat No.0501 in Block J-1 of the above referred project was allotted to him for a consideration of Rs.1,49,35,000/-, he executed an Apartment Buyers Agreement with the OP on 05.02.2011.  As per clause 4(a)(i) of the said agreement, the possession of the apartment ought to have been delivered within 36 months of its execution, meaning thereby that the possession ought to have been delivered by 05.02.2014.  The grievance of the complainant is that the possession has not even been offered to him despite he having already paying Rs.1,41,12,224/- to the OP.  The complainant is therefore, before this Commission seeking refund of the amount paid by him to the OP alongwith compensation etc.  The OP did not file its written version within the prescribed period but filed the same with a delay of 28 days alongwith an application seeking extension of time for the said purpose.  Vide order dated 09.02.2018, the delay in filing the written version was condoned subject to payment of Rs.25,000/- as cost to the complainant.  The said cost however, was not paid and the learned counsel for the OP, when he appeared on 22.05.2018, expressed inability to pay the said cost.  The written version therefore, was rejected. 

2.      I have heard the learned counsel for the complainant who states on instructions that the complainant is restricting his claim to the refund of the principal amount paid by him to the OP alongwith compensation in the form of simple interest @ 10% per annum in terms of clause 4.e of the agreement which reads as under:

 “4.(e) Default

          If for any reason the developer is not in a position to offer the apartment, as agreed herein, the developer may offer the apartment allottee(s) alternative property or refund the amount paid by the apartment Allotttee (s) in full with interest @ 10% per annum from the date of payment(s) by the Apartment Allottee(s) without any further liability to pay any damages, charges or compensation.”

 

3.      The documents and the affidavits filed by the complainant prove the allotment made to him as well as the payment received from him by the OP.  Since the possession of the allotted apartment has not been offered to him, he is entitled to refund of the amount paid by him to the OP alongwith appropriate compensation.

4.          The learned counsel for the complainants places reliance upon the decision of this Commission in CC No. 1100 of 2015 Vibha Gupta Vs. M/s Unitech Ltd. & other connected matters decided on 28.11.2016 and the decision of this Commission dated 30.09.2016 in CC No. 472 of 2015 Anil Kumar Gupta Vs. Unitech Ltd.

5.      The decision of this Commission in Vibha Gupta (supra) which pertains to this very project, to the extent it is relevant, reads as under:

5.    As regards the alleged non-availability of ground water on account of the use of ground water in building activities, having been stayed by the Punjab and Haryana High Court, the following view taken by this Commission in Cap. Gurtaj Singh Sahni Vs. Unitech Limited, Consumer Complaint No.603 of 2014 and connected matters, decided on 2.5.2016 is pertinent:-

 “6. The next question which arises for consideration is the quantum of compensation which should be paid to the complainants for the delay in completion of the villas. As far as the prohibition on use of underground water in construction is concerned, the learned counsel for the complainant has drawn my attention to the order dated 21.08.2012 passed by a Divisional Bench of Punjab & Haryana High Court in Civil Writ Petition No. 20032 of 2008 wherein the High Court noted that the public notice issued under Section-5(3) of the Environment Protection Act, 1986 was published in the newspaper on 26.12.2000. It further shows that the said notice had imposed a complete ban upon the use of underground water in the construction without prior approval of the competent authority. It was noted by the High Court that despite publication of the aforesaid notice, the builders continued to use underground water for construction purposes. If there was a complete ban on use of underground water for construction and the said prohibition was notified on 26.12.2000, the opposite party must have taken into account, the impact of the said prohibition while entering into Buyers Agreements with the complainants. Therefore, it is not open to the opposite party to rely upon the said prohibition in order to justify the delay in construction of the villas sold to the complainants. The opposite party knew at the time of entering into agreements with the complainants that it will not be able to use underground water for construction of the villas and therefore, will have to make alternative arrangements from authorized sources for making the water available for the said construction. Therefore, the aforesaid prohibition on use of the underground water for construction purpose does not justify the delay in completion of the construction. In any case, no material has been placed by the opposite party on record to show that efforts were made by it during the relevant period to procure water from alternative sources but it was unable to obtain the water from the said sources. More importantly, in the Buyers Agreement executed between the parties, it was not disclosed to the buyers that since no underground water can be used for construction purpose, the developer will have to arrange water from alternative sources and in case it is not able to arrange water, the construction would be delayed and in that case, it will not be held responsible for the delay in completion of the construction.”

6.    For the reasons stated hereinabove, the complaint is disposed of with the following directions:

(i)   The OP shall refund the entire principal amount of Rs.1,41,12,224/- to the complainant alongwith compensation in the form of simple interest @ 10% per annum from the date of each payment till the date on which the aforesaid amount is refunded along with compensation in terms of this order.

(ii)        The OP shall also pay a sum of Rs.25,000/- as the cost of litigation to the complainant.

(iii)     The payment in terms of this order shall be made within three months from today.

 
......................J
V.K. JAIN
PRESIDING MEMBER

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.