NCDRC

NCDRC

CC/472/2015

ANIL KUMAR GUPTA - Complainant(s)

Versus

M/S. UNITECH LTD. - Opp.Party(s)

M/S. DIWAN & COMPANY

30 Sep 2016

ORDER

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSION
NEW DELHI
 
CONSUMER CASE NO. 472 OF 2015
 
1. ANIL KUMAR GUPTA
EC-369,DDA SFS FLATS, MAYA ENCLAVE, NERA HARI NAGAR
NEW DELHI-110064.
...........Complainant(s)
Versus 
1. M/S. UNITECH LTD.
Registered Office: 6, Community Centre, Saket,
New Delhi-110017
...........Opp.Party(s)

BEFORE: 
 HON'BLE MR. JUSTICE V.K. JAIN,PRESIDING MEMBER

For the Complainant :
Mr. Vishal Diwan, Advocate &
Mr. Vikram Diwan, Advocate
Ms. Anamika Aggarwal, Advocate
For the Opp.Party :
Mr. Sahil Sachdeva, Advocate

Dated : 30 Sep 2016
ORDER

HON’BLE MR. JUSTICE V.K.JAIN, PRESIDING MEMBER (ORAL)

1.      The complainant booked a residential flat with the OP in a project namely “Exquisite”, Nirvana Country – 2, Gurgaon.  An allotment letter dated 27.10.2010 was issued to him, allotting flat no. 0801 having super area of about 218.32 sq. meters to him for a total consideration of Rs.1,46,57,700/-.  The parties then entered into a Buyers Agreement dated 11.11.2010.  As per clause 4.a of the said agreement, the possession was to be delivered to the complainant within a period of 36 months from the date of the said agreement.  Thus, possession was to be delivered on or before 11.11.2013.  As per clause 4.e of the said agreement, if for any reason, the developer was not in a position to offer the apartment, he could offer an alternative property or refund the amount paid by the apartment allottee, in full, with interest @ 10% per annum from the date of payment by the apartment allottee, without any further liability to pay any damages, charges or compensation. 

2.      The grievance of the complainant is that despite he having already paid Rs.1,44,29,715/- to the OP, the possession has not been offered to him and the construction is not even near completion.  The complainant is therefore, before this Commission seeking refund of the amount paid to the OP alongwith interest @ 18% per annum. 

3.      The complaint has been resisted by the OP on several grounds though it has admitted allotment of the flat to the complainant as well as receipt of the consideration from him.   It has been alleged in the written version filed by the OP that the possession of the flat could not be handed over to the complainant on account of reasons beyond its control.  The following according to the OP, were the reasons on account of which the possession could not be offered to the complainant:

  1. There was slump in the real estate market, because of overall economic conditions, as a result of which the supply of labour and raw-material became scarce.

  2. There was shortage of labour and the building material due to Common Wealth Games held in October 2010.

  3. There was shortage of labour due to implementation of social schemes such as National Rural Employment Guarantee Scheme (NREGS) and Jawahar Lal Nehru National Urban Renewal Mission (JNNURM)

  4. The use of ground water for building purposes was stayed by Punjab & Haryana High Court vide its order dated 16.7.2012.

  5. Restrictions were placed by Ministry of Environment and Forests vide Notification dated 14.9.1999 which resulted in the reduction in availability of bricks in the market since manufacture of clay bricks was stopped within a radius of 50 km from Coal and Ignite based Thermal Power Plants without mixing at least 25% of ash with soil.

  6. The Ministry of Environment & Forest had issued a notification in terms of the National Environment Policy approved by the Government on 18.05.2006 requiring environment clearance.The said notification was published on 14.09.2006.

4.      All the above referred grounds have repeatedly been rejected by this Commission in a number of cases including CC No. 182 of 2015 and connected matters decided on 29.09.2016.  The following view taken in the aforesaid matters is relevant for the purpose of deciding this complaint:  

6.     As regards the delay in obtaining the environmental clearance, the opposite party knew before accepting booking from the complainants and allotting a flat to them that since the size of the project was more than 20,000 sq.ft. of built up area, environmental clearance in terms of the Notification dated 14.9.2006 would be necessary and the said clearance would be given only after the project was approved by State Environment Impact Assessment Committee and then by State Level Environment Impact Assessment Authority.  It was, therefore, necessary for the opposite party to either obtain the requisite environmental clearance before accepting the booking or at least inform the buyers that the construction would commence only after obtaining the requisite environmental clearance which they were yet to receive. This is particularly necessary in a case where the builder is promising delivery of the apartment in a time-bound manner linked with the date of the Buyer’s Agreement and not with the date on which the construction actually commences after obtaining all the requisite clearances. If such a disclosure is made to the buyer and still he chooses to make a booking knowing fully well that the builder may not  be held responsible for the delay to this extent it is attributable solely to the concerned environmental  authority, it will not be possible to hold the builder responsible for the delay in the aforesaid extent.”

5.      As regards the alleged non-availability of ground water on account of the  use of ground water in building activities, having  been stayed by the Punjab and Haryana High Court, the following view taken by this Commission in Cap. Gurtaj Singh Sahni Vs. Unitech Limited, Consumer Complaint No.603 of 2014 and connected matters, decided on 2.5.2016 is pertinent:-

“6. The next question which arises for consideration is the quantum of compensation which should be paid to the complainants for the delay in completion of the villas. As far as the prohibition on use of underground water in construction is concerned, the learned counsel for the complainant has drawn my attention to the order dated 21.08.2012 passed by a Divisional Bench of Punjab & Haryana High Court in Civil Writ Petition No. 20032 of 2008 wherein the High Court noted that the public notice issued under Section-5(3) of the Environment Protection Act, 1986 was published in the newspaper on 26.12.2000. It further shows that the said notice had imposed a complete ban upon the use of underground water in the construction without prior approval of the competent authority. It was noted by the High Court that despite publication of the aforesaid notice, the builders continued to use underground water for construction purposes. If there was a complete ban on use of underground water for construction and the said prohibition was notified on 26.12.2000, the opposite party must have taken into account, the impact of the said prohibition while entering into Buyers Agreements with the complainants. Therefore, it is not open to the opposite party to rely upon the said prohibition in order to justify the delay in construction of the villas sold to the complainants. The opposite party knew at the time of entering into agreements with the complainants that it will not be able to use underground water for construction of the villas and therefore, will have to make alternative arrangements from authorized sources for making the water available for the said construction. Therefore, the aforesaid prohibition on use of the underground water for construction purpose does not justify the delay in completion of the construction. In any case, no material has been placed by the opposite party on record to show that efforts were made by it during the relevant period to procure water from alternative sources but it was unable to obtain the water from the said sources. More importantly, in the Buyers Agreement executed between the parties, it was not disclosed to the buyers that since no underground water can be used for construction purpose, the developer will have to arrange water from alternative sources and in case it is not able to arrange water, the construction would be delayed and in that case, it will not be held responsible for the delay in completion of the construction.”

6.      As regards the alleged shortage of labour and building material on account of Commonwealth Games, the plea taken by the opposite party is wholly misplaced since the said games were over in October 2010 much before the allotment in this project was made to the complainant.

7.      As regards the alleged economic slowdown and consequent recession in the real estate market, the same cannot be a valid ground for delaying the possession of the flats to the  complainant since some of the buyers made advance payment of almost 95% of the sale consideration whereas the other buyers were to make payment linked with the progress of construction and this is not the case of the opposite party that they had defaulted in performing their contractual obligations as regards the payment of the sale consideration. Therefore, it cannot be said, as far as this project is concerned, that the construction was delayed on account of funds not being available with the opposite party.

8.      As regards the alleged shortage of labour due to NREGS and Jawahar Lal Nehru National Urban Renewal Mission, there is no evidence of the opposite party having attempted to recruit labour and having not found the requisite labour available in the market. Ordinarily such big builders operate by giving contracts/sub-contracts to third parties. There is no evidence of the opposite party having not been able to get any contractor/sub-contractor on account of non-availability of labour and/or building material in the market. Moreover, this is not the case of the opposite party that no construction activity took place in Gurgaon in the last 5 years or so. Had the labour and/or building material not been available in the market, the problem would have been faced not only by the opposite party but by all other builders as well as the individuals who were seeking to construct houses in this area. Therefore, I find no merit in the aforesaid plea taken by the opposite party. 

9.      As regards the alleged shortage of bricks and sand, there is no evidence of the opposite party having invited tenders for supply of bricks and sand and the said material having not been available in the market. Moreover, there is no evidence of any sub-contractor/contractor of the opposite party having stopped the work awarded to him on account of non-availability of labour and/or building material in the market. It is possible that the wages of the laour and the cost of the building material may have gone up with the passage of time but it would be difficult to accept that neither the required labor nor the building material in sufficient quantity was available in the open market.

5.      For the reasons stated hereinabove, I am satisfied that the delay in offering possession of the flat allotted to the complainant did not take place on account of the reasons beyond the control of the OP and therefore, the said OP was deficient in rendering services to him. 

6.      It is also an admitted position that no alternative allotment was offered to the complainant at any point of time. Even during the pendency of this complaint, the opposite party has not come out with any offer to provide an alternative flat to the complainant. Therefore, in view of clause 4.e of the Buyer’s Agreement, the opposite party is under a contractual obligation to refund the entire amount received from the complainant along with interest on that amount @ 10% per annum from the date the said amount was deposited with it.

7.      The learned counsel for the complainant states on instructions that in order to avoid any further litigation and bring the matter to a closure, the complainant is ready and willing to accept the principal amount paid by him along with compensation in the form of simple interest @ 10% per annum in terms of clause 4.e of the Buyer’s Agreement.

8.      For the reasons stated hereinabove, the complaint is disposed of with the following directions:-

(i)     The OP shall refund the entire principal amount received from the complainant in respect of the flat allotted to him along with compensation in the form of simple interest @ 10% per annum from the date of receipt of each payment till the date on which the entire amount payable to the complainant along with compensation in the form of interest in terms of this order is refunded.

(ii)      The OP shall also pay Rs.10,000/- as the cost of litigation in each complaint.

(iii)     The payment in terms of this order shall be made within three months from today.

 
......................J
V.K. JAIN
PRESIDING MEMBER

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.