Dt. of filing – 22/02/2018
Dt. of Judgement – 31/01/2019
Mrs. Sashi Kala Basu, Hon’ble President
This consumer complaint is filed by the complainants namely Zakaria Ahmed and Rehana Khatun under Section 12 of the Consumer Protection Act against the opposite parties namely: - (1) M/s. UMA Associates, (2) Subrata Gupta , (3) Manju Naskar and (4) Somnath Naskar alleging deficiency in service on the part of the OP.
Case of the complainants in short is that by an agreement for sale dated 03.03.2010 complainants agreed to purchase a flat being No. A2, Block-A measuring 740 sq.ft. to be constructed on the land measuring about 16 cottah 4 chittaks 7 sq.ft. at Mouja – Tegori comprising Khatian No. 147 pertaining to Dag No. 495 within Police Station - Sonarpur at a total consideration price of Rs. 7,40,000/-. OP Nos. 3 and 4 ( Proforma OPs ) are the owner of the land. Complainants paid an amount of Rs. 2,75,000/- out of the total consideration price to the OP No.2 the sole proprietor of the OP Firm. Inspite of making of the payment, the construction was not completed by the OP No.2. Several request was made by the complainant but OP Nos. 1 and 2 failed to complete the construction work and thus complainant lodged a complaint at Survey Park Police Station. Ultimately present complaint has been filed by the complainants for directing the OPs to complete the schedule flat and deliver the peaceful possession of the same to the complainant after registering the sale deed or in alternatively for directing the OPs to refund Rs. 2,75,000/- paid to the OP No.2 with interest @ 12% p.a., to pay compensation of Rs. 6,00,000/- for harassment and mental agony and to pay the litigation cost.
Complainant has annexed with the complaint petition, agreement entered into between the parties dated 03.03.2010. Money receipts showing payment and copy of the FIR lodged at Survey Park Police Station, Santoshpur.
OP Nos.3 and 4 have contested the case by filing W.V. stating inter alia that the developer/OP No.1 failed and neglected to construct the building on the schedule property in terms of the development agreement entered into between OP Nos. 3 to 4 with OP Nos. 1 and 2 within the stipulated period as per the building sanctioned plan. He only constructed one building namely Block – B comprising 12 nos. Self-contained residential flats and failed to deliver the possession of the owner’s allocation even in the said building in terms of the development agreement dated 05.05.2009. Consequent to the same, OP Nos. 3 to 4 have cancelled the development agreement and revoked the General Power of Attorney in favour of OP No.2. So, OP No.1 had no authority to enter into agreement for sale with the complainant. OP Nos. 3 and 4 have also filed a Civil Suit
being T. S. 21 of 2016 before the Ld. Court of 2nd Civil Judge ( Junior Division ) at Baruipur against the OP No.1. So, the OP nos. 3 and 4 have prayed for dismissal of the case.
Inspite of service of notice, OP Nos. 1 and 2 did not take any step and thus vide order dated 23.05.2018, case proceeded exparte against them.
Following points require determination:
- Whether there has been any deficiency in service or unfair trade practice on the part of the OPs ?
- Whether the complainants are entitled to relief as prayed for?
Decision with reasons
Point nos. 1 and 2 :
Both these points are taken up for a comprehensive discussion. Complainant has filed the agreement entered into between the complainants and the OPs on 03.03.2010. The agreement was executed by OP No.2 sole proprietor of OP No.1 as developer and constituted attorney of OP Nos. 3 and 4, at a total consideration price of Rs. 7,40,000/-. As per the schedule of payment in the agreement, construction was to be completed before 18 months of the agreement indicating the flat was to be handed over within the said period of 18 months. Admittedly, the flat has not been handed over to the complainant. Complainant has filed the receipts showing payment of total amount of Rs. 2,75,000/- out of the total consideration amount of Rs. 7,50,000/-. It is stated by the complainant that the OP has failed and neglected to complete the construction of the building. It appears from the W.V. filed by the OP nos. 3 and 4 that as per development agreement the said OP /developer was to raise the construction of two buildings in two Blocks but he only constructed one building namely Block-B comprising of 12 nos. Self-contained residential flats indicating that Block –A has not been constructed by the said developer. The schedule –B in the agreement reveals that the complainants agreed to purchase the flat in block-A. So, claim of the complainant that the OPs have failed and neglected to complete the construction of the flat as agreed is substantiated by OP Nos. 3 and 4. If that be so than there has been deficiency in service on the part of the OPs, cannot be denied and disputed. However, it may be pointed out that OP Nos. 3 and 4 have stated that they cancelled the development agreement and so OP No.2 could not enter into the agreement for sale with the complainant, cannot be accepted as it appears that the General Power of Attorney was revoked on 24.11.2014 whereas the agreement for sale in favour of the complainant was executed by the OP Nos. 1 and 2 with the complainant on 03.03.2010. In such a situation complainants are entitled to the relief as prayed for. It is settled law that the ‘Consumer’ cannot be made to suffer due to dispute between the builder and the owner of the property and pendency of the civil suit does not bar a consumer claiming the relief under the Consumer Protection Act. However, as it is apparent that the building namely Block ‘A’ in which the complainant had booked the flat, has not been raised, it would be appropriate to allow the alternative relief of refund of amount as prayed by the complainant together with interest therein. Thus these points are accordingly answered.
Hence,
Ordered
CC/83/2018 is allowed on contest against the OP Nos. 3 and 4 and exparte against OP nos. 1 and 2. OP nos. 1 and 2 are directed to refund Rs. 2,75,000/- paid by the complainant with interest on the said amount @12% p.a. from the date of last payment i.e. 09.12.2015 within two months from the date of passing this order. OPs are further directed to pay litigation cost of Rs.12,000/- to the complainants within the aforesaid period of two months failing which the entire sum shall carry interest @ 10% p.a. till realisation.