Dt. of filing- 10/04/2018
Dt. of Judgement- 01/11/2019
Mrs. Sashi Kala Basu, Hon’ble President.
This consumer complaint is filed by Shri Ramendra Nath Saha under Section 12 of the Consumer Protection Act against the Opposite Party namely M/s. Modern Construction alleging deficiency in service on its part.
Case of the complainant in short is that complainant was the owner in respect of the property described as homestead land measuring an area of 4 cottha 5 chitaks and 37 sq.ft. comprised in J.L. N. 45, Dag No. 140, being Municipal Premises No. 116, Arabindra Park locally known as C/2, Arabind Park. With an intention to develop the said property, complainant entered into a development agreement with the OP on 11.03.2011 to construct a building upon the roof of the ground floor on his said plot of land. He also executed a registered General Power of Attorney in favour of OP on 09.09.2016 to construct the said new building. OP undertook to construct the building within 18 months from the date of the sanction of the building plan. OP started the construction work initially but for the reason best known to OP, work was suddenly stopped. However, on much persuasion, OP resumed the construction work but did some brick works only. It was agreed that the building was a G + 3 storied and in terms of the agreement complainant was entitled to entire ground floor, one flat of the 1st floor front side and 1 flat on the 3rd floor front side and also 1 flat on the 2nd floor back side. But the same has not been handed over to the complainant. OP is trying to transfer the entire project to some other builder for gains without the consent and knowledge of the complainant. Inspite of the repeated requests of the complainant to complete the building and to hand over owner’s allocation, OPs have been avoiding to comply the same. So, ultimately notice was sent by the complainant through his Ld. Advocate requesting to complete and hand over owner’s allocated portion but all in vain. So, present complaint has been filed directing the OP to complete the construction work, to handover the owner’s allocation, to pay compensation of Rs. 18,50,000/- and to pay litigation cost of Rs. 50,000/- and further to give the possession letter along with Completion Certificate.
Complainant has annexed with complaint, copy of the Sale Deed showing the ownership of the complainant over the land, K.M.C. tax receipt, copy of agreement dated 11.03.2011 , copy of the General Power of Attorney dated 09.09.2016 and copy of the notice sent by the complainant through his Ld. Advocate.
OP has contested the case by filing the Written Version denying and disputing the allegation made in the complaint contending inter alia that the possession of the owner’s allocation has already been handed over and a declaration dated 21.12.2015 has been made by the complainant to that effect. Complainant after getting the owner’s allocation put a door in the car parking space lying in his allocation and tried forcibly to occupy the unsold portion of the developer’s allocation. Complainant restructured his allocation violating the building rules of the K.M.C. for which K.M.C refused to issue Completion Certificate. Complainant has also taken Rs. 2,50,000/- from the OP but has not refunded the same. So, OP has prayed for dismissal of the complaint with heavy cost.
During the course of the trial, both parties have filed their respective affidavit in chief followed by filing questionnaire and reply thereto and ultimately both parties have filed written notes of argument. So, the following points require determination :
- Whether there has been any deficiency in service on the part of the OP ?
- Whether the complainant is entitled to the relief as prayed for ?
Decision with reason
Point Nos. 1 & 2: Both the points are taken up together for a comprehensive discussions. It is claimed by the complainant that the development agreement dated 11.03.2011 was executed between him and the OP to raise construction of G + 3 storied building upon the roof of the ground floor. But the OP has not completed the said building and has not handed over the owner’s allocated portion.
So far as execution of the development agreement has not been denied and disputed by the OP. But it is the specific claim of the OP that the owner’s allocation has already been handed over to the complainant in terms of the agreement and to this effect a declaration has already been made by the complainant acknowledging such handing over of the owner’s allocation. OP has filed the said declaration and confirmation dated 21.12.2015. It appears from the said declaration that the same has been executed by the complainant on 21.12.2015. It has been specifically stated in the said declaration that “as per development agreement dated 11.03.2011, the developer completed the construction and after completion of the said building on the said plot, developer handed over to me as owner my allocation flats/units”. So, the specific recital in the declaration dated 21.12.2015 suggests complainant has already been handed over the owner’s allocation which indicates completion of the building as per the development agreement entered into between the parties.
It appears from the questionnaire filed by OP that a specific question was put by the OP being question no. 27 that “ Did you make any declaration and confirmation dated 21.12.2015 that the OP completed the construction in compliance to the agreement dated 11.03.2011 and after completion of the said building on the said plot, OP handed over to you the owner’s allocation ?” Complainant has replied to the said question being reply no. 12 that it was a matter of records. So, the execution of the said declaration and confirmation dated 21.12.2015 has not been disputed and denied by the complainant. Complainant has also admitted that the electric meters in three separate floors have also taken in the said building in the names of his two sons and in his name. Two separate deed of conveyance dated 28th June, 2017 and 23rd April, 2014 in the name of purchasers namely Rash Mohan Saha and Suman Patra have been filed bearing specific recital that as per development agreement, developer duly constructed G + 3 storied building and the possession of the flat as per the agreement for sale entered into between those parties with the developer and owner, has been handed over and accordingly deed of conveyance has been executed in their favour. So, on consideration of the declaration as referred to above made by the complainant himself and the two deeds as well as the possession letter issued in their favour, negates the claim of the complainant that the building has not been completed or that the possession of owner’s allocation has not been handed over. So in such a situation, complainant is not entitled to the reliefs as prayed and thus the complaint is liable to be dismissed.
Hence,
Ordered
CC/186/2018 is dismissed on contest.