ORDER

Date of Filing: 18 Nov 2009

NATIONAL CONSUMER DISPUTES REDRESSAL COMMISSIONNEW DELHIREVISION PETITION NO. No. RP/4263/2009
(Against the Order dated 02/03/2009 in Appeal No. 1329 & 1336/03 of the State Commission Haryana)
1. KULBIR SINGHS/o. Sh. Mam Chand R/o. Village. Rampur Jattan Post Chouli Yamuna Nagar Haryana ...........Appellant(s)

Vs.
1. M/S. KINETIC ENGINEERS LTD. & ANR.Tl Shriru Pune Maharashtra -412207 Though its MD. Sales 2. NEEL AUTHOMOBILES KANHIYA SAHIB CHOWK Gondpuri Bye Pass Road. Yamuna Nagar 3. NEEL AUTHOMOBILES KANHIYA SAHIB CHOWK Gondpuri Bye Pass Road. Yamuna Nagar ...........Respondent(s)

BEFORE:
HON'BLE MR. JUSTICE ASHOK BHAN ,PRESIDENTHON'BLE MR. B.K. TAIMNI ,MEMBER
For the Appellant :MR. GYANENDRA SINGH
For the Respondent :NEMO

Dated : 04 Dec 2009
ORDER

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.

 

          This Revision Petition has been filed with a delay of 140 days in filing the Revision Petition, which is over and above the period of 90 days statutorily given to file the Revision Petition. Under the Consumer Protection Act, the consumer fora are required to decide the case within a period of 90 days from the date of filing, in case, no evidence is required to be taken and within 150 days, wherever evidence is required to be taken. Delay of 140 days cannot be condoned without sufficient cause being shown. The only reason given by the petitioner is that he could not collect the material from his counsel who had conducted the case at Yamunanagar. We are not satisfied with the cause shown. 

            Application for condonation of delay is dismissed.   Consequently, the Revision Petition is dismissed as barred by limitation.



......................JASHOK BHANPRESIDENT
......................B.K. TAIMNIMEMBER