Suman Ray filed a consumer case on 26 Jul 2022 against M/s. India Green Realty Pvt. Ltd. & another in the Kolkata Unit-IV Consumer Court. The case no is CC/85/2021 and the judgment uploaded on 30 Jul 2022.
| |||||||||||||
| |||||||||||||
| |||||||||||||
| |||||||||||||
| |||||||||||||
| |||||||||||||
Dated : 26 July, 2022
Judgement
HON’BLE MR. SUDIP NIYOGI, PRESIDENT | |||||||||||||
The instant complaint in short is that in the project, Greenland Eco Village Project at Makrampur Gram Panchayat P.S. Sonarpur, District South 24 Parganas, Kolkata 700150 launched by the OPs, the complainants had booked one bungalow area of which was 1442 sqr.ft., namely, Sandhyarag Unit No. B-135 on a plot measuring 2 cottahs and one agreement for sale was executed between the parties. Complainants paid Rs.7,00,000/- as advance till 17.06.2014 towards consideration. Subsequently, complainants could realize that the OPs having no valid sanctioned plan from the appropriate authority would not be able to complete the project within stipulated time of December, 2015, and decided to cancel the booking and demanded for refund of the said advance amount paid by him, through email dated 28.12.2016. The complainants were handed over seven number of post-dated cheques by OP No. 2 vide their letter dated 15.05.2017 totalling a sum of R.6,78,370/-, but the said chques could not be honoured for want of sufficient funds. There were several correspondences between the parties on this matter but the refund of the advance by the OPs still remaining unpaid. On being aggrieved, the complainants filed the instant case by filing a petition of complaint U.S. 35 read with Section 38 of the C.P. Act, 2019, with this commission praying for refund of Rs.7,00,000/- which was paid as advance, Rs.1,00,000/- for compensation and Rs.20,000/- towards cost of litigation. Despite receipt of notice, OPs did not enter appearance in this case and contest. As a result, the case was heard ex parte. The petition of complaint has been treated as evidence on the part of the complainants, on their prayer. Complainants produced allotment letter (Annexure P-1) agreement for sale, payment receipt B-3. Several correspondences between the parties including issuance of cheque for refund by the OPs. Annexure P-4, P-5, P-6, and P-7. Now the point for consideration is whether the complainants are entitled to the relief(s) as prayed for? FINDINGS We have gone through the materials on record including documents filed. The complainants had booked their bungalow in the project launched by the OPs for which they advanced Rs.7,00,000/- in total to the OPs by making payment of different dates. It is also revealed that the complainants subsequently, cancelled the booking on realizing that the OPs would not be able to complete the project and handover their bungalow to them. That is why, they cancelled the booking on 28.12.2016 and sought for refund of the advance. It is said that the OPs issued seven number of cheques for payment of refund but owing to want of funds the cheques were dishonoured. The refund of money is still due. So, it is clear that due to delay in completion of the project, the complainants were compelled to cancel the booking and prayed for refund of the advance. In such a situation, complainants cannot be blamed for cancellation of their booking. The contentions of the complainants remained unchallenged as the OPs did not contest the case. Thus, on consideration of the instant case, we find that the complainants have been able to prove their case for which they are entitled to get relief(s). Complainants are entitled to refund of advance of Rs.7,00,000/- with interest at the rate of 9% per annum. Complainants are also entitled to Rs.3,000/- for cost of litigation. No amount on compensation separately is considered taking into account the rate of interest awarded.
Hence, it is
ORDERED
That the instant case be and the same is allowed ex parte against the OPs. Complainants are entitled to refund of Rs.7,00,000/- (seven lakh only) with interest @ of 9% p.a. from until realization from the OPs. They are also entitled to Rs.3,000/- (three thousand only) for cost of litigation from the OPs. OPs are directed to make the aforesaid payments within 60 days from the date of this order, failing which the complainants shall be entitled to proceed in accordance with law.
Dictated and corrected by me.
| |||||||||||||
| |||||||||||||
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.