PER: HON’BLE MR. SAMARESH PRESAD CHOWDHURY, PRESIDING MEMBER
The instant complaint under Section 17 of the Consumer Protection Act, 1986 (for brevity, ‘the Act’) is at the instance of a couple/intending purchasers against the Developer/Builder Company on the allegation of deficiency in services on the part of developer/builder in respect of a flat and car parking space in a dispute of housing construction.
Succinctly put, the complainants’ case is that on 05.01.2008 they had entered into an Agreement for Sale with the Opposite Party/Builder to purchase of a flat measuring about 1893 sq. ft. being apartment No.1403 on 13th floor, Tower -02 and a car parking space in the basement of the said tower in the complex ‘Harmony’ in Uniworld City, Kolkata at a total consideration of Rs.64,29,205/- under payment plan. In pursuance of the said Sale Agreement, the complainants have paid a total sum of Rs.41,90,161/- on diverse dates through A/C payee cheques and also avail a cash discount of Rs.1,18,542/- for early lump sum single payment of 2nd instalment to 10th instalment and thus total payment of Rs.43,08,733/- has been completed out of the total consideration amount of Rs.64,29,205/-. As per terms of the Agreement, the OP was under obligation to handover the subject flat within 31st March, 2011 subject to Force Majeure circumstances. The complainants have alleged that all their attempts and persuasions to get the flat in favour of them on payment of balance consideration amount went in vain. Hence, the complainants approached this Commission with prayer for several reliefs, viz. – to direct the OP to deliver possession of the residential flat forthwith upon payment of Rs.21,20,472/- alternatively to refund Rs.73,08,733/- along with interest @ 18% p.a., to pay cost etc.
The Opposite Party/development company by filing a written version has stated that as per terms and conditions the company was under obligation to give possession of the apartment to the complainants within 31.03.2011. However, the delay in construction is attributed to delays in obtaining statutory infrastructural provisions pertaining to road, electricity, water, sewerage, sanctions etc. beyond control of them but the construction of Uniworld City is steadily progressing. The OP has stated that as per terms of the agreement, they are ready to pay compensation to the purchaser @ 5% per sq. ft. per month for the period of delay in offering the delivery of the flat and the same will be adjusted at the time of issuance of final notice of possession to the complainants.
During hearing of the case, both the parties have tendered evidence through affidavit. The complainants have filed reply against the questionnaire set forth by OP. However, no questionnaire has been filed by the complainants and as such question of filing reply by OP Company does not arise. Both the parties have also relied upon some documents including the Agreement for Sale dated 05.01.2008. Both the parties have also filed brief notes of arguments in respect of their respective cases.
On perusal of pleadings and the evidence on record it transpires that the complainants had entered into an agreement with the OP Company to purchase of an apartment measuring about 1893 sq. ft. being apartment No.1403 on 13th floor, Tower -02 and a car parking space in the basement of the said tower in the complex ‘Harmony’ in Uniworld City, Kolkata at a total consideration of Rs.64,29,205/-. It is not in dispute that the complainants had paid a total sum of Rs.41,90,191/- in account payee cheques on diverse dates in favour of OP Company and availed a cash discount of Rs.1,18,542/- for early lump sum single payment of 2nd instalment to 10th instalment and thus total payment of Rs.43,08,733/- has been paid by the complainants towards the total consideration of Rs.64,29,205/-. It also remains undisputed that the OP Company was under obligation to handover the apartment to the complainants within 31.03.2011 subject to Force Majeure circumstances and payment of dues in respect of the apartment.
In the written version, the opposite party took the plea of Force Majeure circumstances by stating that the construction of ‘Harmony’ in Uniworld City has been delayed for obtaining statutory infrastructural provisions pertaining to road, electricity, water, sewerage, sanction etc. beyond the control of them.
It is trite law that the parties are bound by the terms of agreement. When either of the parties did not pick up any quarrel with the terms and conditions of the agreement, they are certainly bound to follow the terms and conditions contained in the agreement. In a case reported in AIR 1996 SC 2508 (Bharti Knitting Co. – vs. – DHL World Wide Express Courier Division of Airfreight Ltd.) the Hon’ble Supreme Court has observed thus:-
“It is seen that when a person signs a document which contains certain contractual terms, as rightly pointed out by Mr. R.F.Nariman, Ld. Senior Counsel, that normally parties are bound by such contract; it is for the party to establish exception in a suit. When a party to the contract disputes the binding nature of the signed document, it is for him to prove the terms in the contract or circumstances in which he came to sign the documents need to be established. The question we need to consider is whether the District Forum or the State Commission or the National Commission could go behind the terms of the contract? It is true, as contended by Mr. M.N.Krishanmani, that in an appropriate case, the Tribunal without trenching upon acute disputed question of facts may decide the validity of the terms of the contract based upon the fact situation and may grant remedy. But each case depends upon it own facts. In an appropriate case where there is an acute dispute of facts necessarily the Tribunal has to refer the parties to original Civil Court established under the CPC or appropriate State law to have the claims decided between the parties. But when there is a specific term in the contract, the parties are bound by the terms in the contract”
For appreciation of the present dispute, let us see the relevant terms and conditions of the agreement. Clause 5.a of the agreement pertains to possession which rewrites below-
“(i). That the developer shall make its best endeavours to deliver the possession of the apartment to the purchaser by 31st march, 2011, subject, however, to ‘Force Majeure circumstances and after all dues in respect of the apartment including stamp duty and registration charges as applicable have been paid. It is, however, understood between the parties that various blocks/towers comprised in the complex shall be ready and completed in phases and after completion, the apartments shall be handed over to the purchaser in the respective block/Tower”.
The Force Majeure circumstances has been mentioned in Clause 9.a of the Agreement which provides that if the completion of apartment is delayed for reasons of Force Majeure which inter alia include delay on account of non-availability of steel, cement or any other building materials or water supply or electricity power back-up or slow down, strike or due to dispute with the construction agency employed by the developer, civil commotion or war or criminal action or earth quake or any act of God, delay in certain decisions/clearance from the statutory bodies or any notice, order, rule or notification of the Government or any public or any competent authority or any change in the policy of government/statutory bodies or for any other reason which are beyond the control of the developer. But it reveals that no such occurrence has happened. The delay in handing over the possession of the apartment could have been justified if there was to be a new legislation, regulation or order suspending, stopping or delaying the construction of the complex and the apartments.
The fact remains that the O.P./Developer has failed to advance any evidence as to reasons on delay in handing over the apartment to the complainant as per clause 5.a of the terms of agreement. The O.P Company has raised some Force Majeure circumstances but none of them appeared to be acceptable. The delay in handing over the possession of the apartment could be justified if there was to be new legislation, regulation or order suspending, stopping of delaying the construction of the complex and the apartments. Therefore, the Force Majeure circumstances are totally inapplicable in the facts and circumstances of the present case.
Evidently, in their evidence on affidavit, the OP Company has stated that the 4th floor slab casting of Tower -02 is under progress. The OP Company was under obligation to handover the apartment within 31.03.2011. The delay has already been committed for long eight years from committed date of delivery of possession. The complainants’ apartment to be constructed on the 13th floor and the dilly-delaying process of the OP Company clearly indicates that there is hardly any chance for the complainants to get the apartment in near future.
In that perspective, Mr. Sugata Shankar Roy, Ld. Advocate for the complainants drawing my attention to Clause 5.e of the Agreement prays for refund of the amount with compensation @ 10% p.a. Clause 5.e of the Agreement is dealt with alternative property/compensation which is set out below –
“That if for any reason the developer is not in a position to offer the apartment herein applied for apartment, the Developer shall offer the Purchaser an alternative property or refund the amount in full with simple interest @ 10% per annum without any further liability to pay any damages or compensation”.
Mr. P.R. Bakshi, Ld. Advocate for the OP, on the other hand has contended that the complainants have failed to pay the amount as per schedule of payment and stopped payment after paying 10th instalment and as such being defaulter in payment as per agreement, they cannot claim compensation. To fortify his submission, Ld. Advocate for the OP has placed reliance to three decisions of the Hon’ble National Commission reported in – (1) III (2012) CPJ 149 [Gulab – Vs. – Force Motors Ltd. & Anr.]; (2) III (2015) CPJ 121 [Agra Development Authority – Vs. – Sardar Bhagat Singh] and (3) III (2015) CPJ 192 [Manas Developers – Vs. – Madhur Arjun Bhabal & Anr.].
We have considered the rival contention of the parties. The evidence on record suggests that the complainants were very much regular in payment for having shelter and as such they had paid a total sum of Rs.41,90,191/- and availed a cash discount of Rs.1,18,542/- for early lump sum single payment of 2nd instalment to 10th instalment. Therefore, it cannot be said that the complainants were defaulter. The referred decisions, therefore, have no similarity with the facts and circumstances of the present case. The evidence on record speaks that on 08.12.2012 in Tower-02 slab casting of 2nd floor was in progress and at the time of giving evidence by OP in October, 2018 it has come to surface that only 4th floor slab casting is in progress. Therefore, within long span of six years, only progress has been made for slab casting of only two floors and as such it could be ascertained that there is hardly any chance on the part of complainants to get their flat on the 13th floor during their life time.
On evaluation of materials on record, it transpires that the complainants being ‘consumer’ as defined in Section 2(1)(d) of the Act hired the services of OP on consideration and OP has failed to fulfil their part of obligations as per agreement for Sale dated 05.01.2008 and thereby deficient in rendering services towards the complainants within the meaning of Section 2(1)(g) read with Section 2(1)(o) of the Act. Therefore, the complainants are entitled to some reliefs. In our view, any direction to deliver possession would be a meaningless one and therefore alternative relief to refund the amount of Rs.41,90,191/- along with compensation in the form of simple interest @ 10% p.a. from the date of each payments till its realisation will meet the ends of justice. Under compelling circumstances, the complainants have to knock the door of this Commission and therefore, complainants are entitled to litigation cost which we quantify at Rs.20,000/-.
With the above discussion, we dispose of the complaint with the following directions –
- The Opposite Party is directed to refund Rs.41,90,191/- along with compensation thereon in the form of simple interest @ 10% p.a. from the date of each payments till its realisation’
- The Opposite Party is directed to pay Rs.20,000/- to the complainants as costs of litigation.;
- The above payments must be paid within 60 days from date positively.