West Bengal

Kolkata-III(South)

CC/27/2022

SRI ABHIJIT NATH. - Complainant(s)

Versus

M/S USASHI REALESTATES PVT.LTD. a company incorporated under the Companies Act, 1956 - Opp.Party(s)

28 Jun 2023

ORDER

DISTRICT CONSUMER DISPUTE REDRESSAL COMMISSION
KOLKATA UNIT-III(South),West Bengal
18, Judges Court Road, Kolkata 700027
 
Complaint Case No. CC/27/2022
( Date of Filing : 14 Jan 2022 )
 
1. SRI ABHIJIT NATH.
S/O Prabir Kumar Nath residing at Tower-33, Flat 7-C, Genexx Valley, P.S. Previously Thakurpukur now Haridevpur, Kol-104.
...........Complainant(s)
Versus
1. M/S USASHI REALESTATES PVT.LTD. a company incorporated under the Companies Act, 1956
having its office at 594/1, Dakshindari Road, Bima Abasan, Flat No. E2/1, First Floor, P.S. Lake Town, Kol-48 and also having office at 81, Golaghat V.I.P. Road, Flat-1B, Radhakunja Apartment near Bika Banquet Hal, P.S. Lake Town, Kol-48 represented by
2. Mr. Supriya Patra
S/O Sri Asis Kumar Patra residing at Radhapur, P.O. Madhapur, P.S. Bhupati Nagar, Dist-Purba Medinipur, Pin-721 626.
3. EVANIE INFRASTRUCTURE PVT. LTD.
represented by Mr. Supriya Patra having office at 86, Golaghat V.I.P. Road, Jamuna Apartment First Floor, behind Shree Venkatesh Banquet Hal, P.S. Lake Town, Kol-48.
............Opp.Party(s)
 
BEFORE: 
 HON'BLE MRS. Sashi Kala Basu PRESIDENT
 HON'BLE MRS. Ashoka Guha Roy (Bera) MEMBER
 HON'BLE MR. Dhiraj Kumar Dey MEMBER
 
PRESENT:
 
Dated : 28 Jun 2023
Final Order / Judgement

Date of filing: 14/01/2022                                                    

Date of Judgment: 28/06/2023

Mrs. Sashi Kala Basu, Hon’ble President.

This complaint is filed by Sri Abhijit Nath under section 35 of the Consumer Protection Act, 2019, against opposite parties (referred as OPs hereinafter) namely (1) USASHI REALESTATES PVT. LTD. (2) Mr. Supriya Patra and (3) Evanie Infrastructure Pvt. Ltd. alleging deficiency in service on the part of OPs.

Case of the complainant in short is that by an agreement for sale dated 24/06/2017 entered into between the complainant and OP 1, OP 1 the developer being represented by OP 2 agreed to sell a flat along with one covered car parking space described in the 2nd schedule Part – 1 of the said agreement at a total consideration price of Rs. 20,80,407/-. Complainant has paid total sum of Rs. 4,03,456/- out of the said total consideration price. But no construction work has been started by the opposite parties. As per the terms and conditions of the agreement for sale the project was to be completed within 30th September, 2020 and the possession of the flat and car parking space was to be handed over within 40 months from the date of execution of the agreement for sale. Since no construction was carried out and possession of flat and car parking space not delivered, present complaint has been filed praying for directing the opposite parties to return the sum of Rs. 4,03,456/- along with interest @ 18% p.a., to pay Rs. 5,00,000/- towards harassment and litigation cost of Rs. 20,000/-.

On perusal of the record it appears that OPs did not turn up on service of notice and thus the case has been heard exparte.

So the only point requires determination is whether the complainant is entitled to the relief as prayed for?

DECISION WITH REASON

In order to substantiate his claim, complainant has filed the agreement for sale, bank statement and the money receipts. On perusal of the agreement for sale, it appears that the complainant had agreed to purchase the flat and car parking space described in Part – 1 of 2nd schedule and as per the terms and conditions in the said agreement the construction was to be completed within 30/09/2020 and the possession of the flat and car parking space was to be handed over within 40 months from the date of execution of the said agreement for sale dated 24/06/2017. It is evident from the memo of consideration therein that a sum of Rs. 4,03,456/- has been paid by the complainant and the same has been acknowledged to have received by the OP 2 as authorised signatory of OP 1. The payment of the said sum of Rs. 4,03,456/- is further established from the bank statement filed by the complainant. Since it is the specific claim of the complainant that no construction work has been started by the OP and neither the possession has been delivered nor the money has been refunded, complainant is entitled to the refund of the sum paid by him as there is absolutely no contrary material before this commission to counter the claim of the complainant. Complainant is also entitled for compensation in the form of interest.

Hence,

             ORDERED

CC/27/2022 is allowed exparte against OPs. OPs are directed to refund Rs. 4,03,456/- to the complainant along with interest on the said sum @ 8% p.a. from the date of agreement for sale i.e. 24/06/2017, within two months from the date of communication of this order. OPs are further directed to pay litigation cost of Rs. 10,000/- to the complainant within the aforesaid period of two months. In default of payment the entire sum shall carry interest @ 8% p.a. till realisation. 

 
 
[HON'BLE MRS. Sashi Kala Basu]
PRESIDENT
 
 
[HON'BLE MRS. Ashoka Guha Roy (Bera)]
MEMBER
 
 
[HON'BLE MR. Dhiraj Kumar Dey]
MEMBER
 

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.