Andhra Pradesh

StateCommission

FA/413/08

Mr. K. Gangaram - Complainant(s)

Versus

Ms United India Insurance Com.Ltd. - Opp.Party(s)

Ms V.Gouri Sankara Rao

29 Dec 2010

ORDER

 
First Appeal No. FA/413/08
(Arisen out of Order Dated null in Case No. of District ADILABAD)
 
1. Mr. K. Gangaram
Nirmal, dist.Adilabad.
Adilabad
Andhra Pradesh
...........Appellant(s)
Versus
1. Ms United India Insurance Com.Ltd.
Podduturi complex, N.H.No.7, Opp.R.T.C. Bus Depot, Nirmal-504 106.
Adilabad
Andhra Pradesh
...........Respondent(s)
 
BEFORE: 
 HONABLE MR. JUSTICE HON'BLE SRI JUSTICE D. APPA RAO PRESIDENT
 HON'ABLE MS. M.SHREESHA Member
 
PRESENT:
 
ORDER

A.P. STATE CONSUMER DISPUTES REDRESSAL COMMISSION

 AT HYDERABAD.

 

F.A. 413/2008 against C.D. 41/2007, Dist. Forum, Adilabad.  

 

Between:

K. Gangaram, S/o. Gangaram

Age: 68 years, Contractor

R/o. Nirmal, Adilabad Dist.                        ***                         Appellant/

                                                                                                Complainant

                                                                   And

United India Insurance Company Ltd.

Podduturi Complex, N.H. No. 7,

Opp. RTC Bus Depot, Nirmal-504 106

Adilabad, Rep. by its Branch Manager.       ***                         Respondent/                                                                                                        Opposite Party. 

 

Counsel for the Appellant:                          M/s.  V.G.S. Rao

Counsel for the Respondent:                      M/s.  E. Venugopal Reddy

 

CORAM:

HON’BLE SRI JUSTICE D. APPA RAO, PRESIDENT  

                                                          &

                                    SMT. M. SHREESHA, MEMBER

 

WEDNESDAY, THE  TWENTY NINETH DAY OF DECEMBER  TWO THOUSAND TEN

 

 

Oral Order: (Per Hon’ble Justice D. Appa Rao, President)

 

                                                          *****

 

1)                This is an appeal preferred by the complainant against inadequacy of  the amount  granted by the Dist. Forum   by its order dt. 30.1.2008.

 

2)                The case of the complainant in brief is that  he is a contractor obtained ‘Contractors all risk policy  from the respondent insurance company for  Rs. 60,59,088/- covering the period from  28.7.2006 to 30.10.2006 for the proposed works  in  Dehegaon village  of Bhainsa Mandal  in Adilabad District.    He completed his work.  However, in view of rains between  2.8.2006 and  8.8.2006  the work done by him was damaged.    When he made claim the insurance company  deputed a surveyor who inspected the work,  and assessed the loss at Rs. 2,04,941/-  The insurance company has purposefully  reduced  the amount,  and in fact he was entitled to  Rs. 15 lakhs with interest @ 24% p.a., besides compensation of Rs. 2 lakhs towards mental agony and costs.

3)                The insurance company resisted the case.   While admitting the issuance of policy it alleged that as against estimated work  of Rs. 60,59,088/-  the complainant offered to take up  at Rs. 46,84,280.93 by quoting  22.69% less, and the same was executed.    Since the complainant could not complete the work within the  stipulated period second policy was issued covering the period from 28.7.2006 to 30.10.2006. He had to take all reasonable precautions to prevent loss, damage or liability.    He was not entitled to the  amount of  loss shown  as excess in the schedule viz., Rs.  6 lakhs.    He had to bear the excess which is not related to the policy.    He did not complete the work in accordance with specifications  and it was sub-standard.    It also denied that there was heavy rain fall during the period from 2.8.2006 to 8.8.2006.    As the work was not completed, new formation silt arresting tank across  local stream  has over flooded  due to which North  East corner of embankment bund was breached.    On intimation a surveyor was  appointed who inspected the site.    On the basis of measurements, he found that the damage or loss of breach of bund was Rs. 8,04,941/- less policy excess  of Rs. 6 lakhs  and arrived at  Rs. 2,04,941/-.    The allegation that  he had sustained loss of  Rs. 15 lakhs is false  and the same is excessive, exorbitant and baseless.    He was not entitled to any interest.   Therefore it prayed for dismissal of the complaint with costs.

 

4)                 The complainant in proof of his case filed his affidavit evidence and got Exs. A1 to A3 marked, while the  insurance company filed the affidavit evidence of  its   Divisional Manager  and filed Exs. B1 to B4. 

 

5)                The Dist. Forum after considering the  evidence placed on record accepted the report of the surveyor,  and accordingly directed the insurance company to pay Rs. 2,84,941.84 ps  with interest @ 9% p.a.,  from the date of complaint till the date of realization but without costs.

 

6)                 Aggrieved by the said decision, the complainant preferred the appeal contending that the Dist. Forum did not appreciate the facts in correct perspective.   It did not consider the  report of  Sri S. Mohan, Surveyor who assessed the loss at Rs. 8,04,941/- vide Ex. B2.    It ought not to have deducted the policy excess of Rs. 6 lakhs.    The complainant did not opt for higher amount  on deductible excess.    Therefore he prayed that the complaint be allowed as claimed.

 

7)                 The point that arises for consideration is whether the order of the Dist. Forum is vitiated by mis-appreciation of fact or law?

 

8)                It is an undisputed fact that the  opposite party insurance company has issued ‘Contractors all risk policy  for  Rs. 60,59,088/- covering the period from  23.7.2004 to 23.7.2008 and later extended from 28.7.2006 to 30.10.2006 vide policy Ex. A1 pertaining to the works  in  Dehegaon village  of Bhainsa Mandal  in Adilabad District.    The complainant alleges that there were heavy rains between  2.8.2006 and  8.8.2006 due to which  new formation silt arresting tank across  local stream  has over flooded  due to which North  East corner of embankment bund was breached.   The complainant  had estimated the damage  at Rs. 15 lakhs under Ex. A2.    In fact the   Executive Engineer, Construction Sub-Division, Bhainsa  also estimated the loss at Rs. 15 lakhs vide his letter  Ex. A3 enclosing the details of estimate.     Admittedly  for the original estimated contract  of Rs. 60,59,088/-  he offered 22.69% less viz.,  at   Rs. 46,84,280.93  vide Ex. B1.    On receipt of claim the insurance company appointed  Sri S. Mohan, Surveyor & Loss Assessor  who after inspecting the site  on  9.8.2006  and subsequent dates  found the damage portion of the embankment bund was in post damaged condition as visible in photographs.  He found the measurements taken by  the insured’s representative  were on very high side,  and therefore  he had taken actual measurement,   and also made local enquiries  with regard to the work done by the complainant and cause and nature of loss.    In fact he himself states that  during his first and second visit to the site, the water level was not receded  and the stream was in flow.  Hence it was  not possible for him to take the measurements  of the damaged portion.    In the meantime  the insured’s representative  Sri Parmjit  Singh has submitted an estimate  of loss for Rs. 39,41,359/-  which  according to her was on very high side.   Hence, he has taken the measurements of the damaged portion  physically and assessed the loss.   The enquiries made with nearby villagers have confirmed  that there was rain fall and the local stream  silt arresting  the tank was submerged, flooded, inundated and the North Eastern side of embankment bund was breached and damaged.

 

9)                 The schedule of work given to the complainant was originally estimated at  Rs. 60,59,088/-  wherein the complainant offered to take up  at Rs. 46,84,280.93 by quoting  22.69% less.   He found that the insured had estimated the loss at Rs. 39,41,359/- towards rectification of damage/loss  under various heads.    He differed from the said estimate and assessed  the net amount at Rs. 8,04,941/- and deducted policy excess at Rs. 6 lakhs and arrived  at Rs. 2,04,941/-.    The insurance company did not file the affidavit of the surveyor  in order to state that the estimate made by  the Executive Engineer  under Ex. A3 was in a  way incorrect.    The complainant got the estimate  prepared through  Mr. Mirza Nazeer Ali Baig, Consulting Engineer & Valuor under Ex. A2.  He noted each  item of the work in detail, assessed the amounts and arrived at Rs. 15 lakhs confirmed by the Executive Engineer  under Ex. A3.   It is not as though the said report was not furnished to the surveyor  appointed by the insurance company.    Except stating that it was on high side he could not point out  where  exactly  he estimated on high side.    If that were to be so, equally it could be said that the surveyor appointed by the insurance company has estimated  the loss at a very lower side.    He could not give any basis for his estimation. 

 

 

10)               The learned counsel for the  insurance company contended that by virtue of terms of the exclusion clause, the insurance company was  not liable  for the first amount of loss on each and every occurrence shown as excess. 

 

 

11)              At the outset, we may state that  Ex. B4 in the proposal form  dt.  28.7.2006  the complainant had estimated the contract work at Rs. 60,59,088/- and without any demur  the insurance company  has accepted  and agreed to cover the risk for the said amount.   In fact  there was also escalation of amount and therefore the period of insurance policy was also extended.    The total escalation was Rs. 15,14,772/- and the total work was   for Rs. 75,73,860/-.  vide report of  the very surveyor appointed by the insurance company at para-2.    Therefore it cannot be said that  there was  policy excess of Rs. 6 lakhs.    Assuming without admitting that there was policy excess of Rs. 6 lakhs  there is no reason why  the estimate prepared by the consultant under Ex. A2 confirmed by the  Executive  Engineer  under Ex. A3  could not be accepted.    The surveyor had the advantage of  perusing Ex. A2 report.  He could not point out where the surveyor appointed by the complainant  went wrong.    It is not as though  he could assess  on his own method and drastically  reduce the claim from Rs. 15 lakhs  to Rs. 2 lakhs.    He should have given work memo detailing each of the work mentioning the estimate made by him.    Had the same been made,  this Commission  would have been in a position to verify with the estimate  prepared under Ex. A2.    The Executive Engineer who is a public servant  would not have certified that the loss was at Rs. 15 lakhs.    It is not as though it was issued without any  basis.     It  was  conformed  by  estimate  prepared  under  Ex.  A2.   

 

 

 

 

 

 

 

The insurance surveyor himself admits  in his report that the embankment bund was damaged.  Except stating that the estimate  made by the complainant was  on higher side, he could not point out  where he went wrong.      In the light of the fact that the complainant has claimed  Rs. 15 lakhs  and in view of policy excess an amount of Rs. 6 lakhs could be deducted.    Therefore, we are of the opinion that an amount of Rs. 9 lakhs could be awarded towards the claim. 

 

12)               In the result the appeal is allowed  in part and the order of the Dist. Forum is modified  directing the insurance company to pay Rs. 9 lakhs  together with interest @ 9% p.a., from the date of complaint  till the date of realization together with costs of Rs. 5,000/-.  Time for compliance four weeks.

 

 

1)      _______________________________

PRESIDENT                 

 

 

2)      ________________________________

 MEMBER           

   Dt.   29.  12.  2010.

 

*pnr

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

“UP LOAD – O.K.”

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 
 
[HONABLE MR. JUSTICE HON'BLE SRI JUSTICE D. APPA RAO]
PRESIDENT
 
[HON'ABLE MS. M.SHREESHA]
Member

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.