BEFORE THE A.P.STATE CONSUMER DISPUTES REDRESSAL COMMISSION :HYDERABAD
F.A.No.36/2008 against C.D.No.1462/2000, Dist. Forum-II,Hyderabad .
Between:
M/s. Rindavani Flat Owners Association,
Rep. by its Secretary A.Srinivas,
R/o.Flat No.303, Rindavani Apartments,
Malkpet, Hyderabad. …Appellant/
Complainant
And
M/s.Siva Sai Builders & Developers Pvt. Ltd.,
Rep. by its M.D.Smt.B.H.Lakshmi ,
R/o.1-9-318/5, Vidyanagar,
Hyderabad-44. … Respondent/
Opp.party
Counsel for the Appellant : M/s. V.Gowrisankar Rao
Counsel for the Respondent : M/s. S.Agastya Sharma
CORAM:HON’BLE JUSTICE SRI D.APPA RAO, PRESIDENT,
AND
SMT. M.SHREESHA, HON’BLE MEMBER,
FRIDAY, THE TWENTIETH DAY OF AUGUST,
TWO THOUSAND TEN.
Oral Order :(Per Smt. M.Shreesha, Hon’ble Member)
****
Aggrieved by the order in C.D.No.1462/2000 on the file of District Forum-II, Hyderabad, the complainant preferred this appeal. The said C.D. was originally disposed of by the District Forum on 26.8.2004 directing the complainant association to deposit an amount of Rs.2 lakhs with the opp.party and also directed opposite party to complete the electricity connection and water connection and other minor pending works within one month of the deposit amount and against the said order , the complainant preferred appeal before this Commission stating that the members who signed the order dated 26.8.2004 never heard the case and hence they do not form part of the quorum in the said order and the said order is not sustainable. This Commission vide its order in F.A.No.997/04 set aside the order of Dist. Forum dt.26.8.2004 and the matter was remanded to the Dist Forum with a direction to conduct denovo enquiry and dispose of the complaint expeditiously. Before the Dist Forum the matter underwent several adjournments but the opposite party did not advance arguments. The District Forum after hearing the arguments of the complainant stated that the earlier judgement dt.26.8.2004 holds good and there is no need to interfere with the earlier judgement and confirmed the same order.
The brief facts as set out in the complaint are that the opposite party is a builder and developer engaged in construction activity and offered to sell residential units on various rates and terms and conditions and the members of the complainant association being induced by the representations of the opp.party entered into separate construction agreements to purchase their respective residential units. As per the terms and conditions of the construction agreements the opp.party has to complete the construction of the residential portion within 12 months from the date of agreement and as per Clause no.15 ‘C’ of the said construction agreements, the purchasers have to bear the cost of the external electrification such as meter boxes , fixing of meter, electricity transformer, laying of cables, security deposit etc. by paying the approximate cost of Rs.15,000/- to the opp.party and the purchasers have to pay to the developer an approximate amount of Rs.10,000/- towards meeting the demands raised by Hyderabad Metropolitan Water Works and Sewerage Board. The flat owners of the complainant association who are 12 in number paid their respective total considerations towards purchase of their respective residential units, including additional amounts towards electricity, drinking water deposits and other items as stipulated under the constructions agreements and they have taken possession of flats during December,1999 to February,2000 whereas the final payments were made on 11.9.1999 itself and the hading over letters were given on 16.2.2000 after repeated persuasion. The opp.party collected all the due amounts, but it did not complete the common works such as Southern side compound wall of the residential complex, the commissioning of the lift and also exteriors of the building on the backside have not been completed. The opposite party has also kept pending some of the works in the individual flats. The complainant issued legal notice to the opp.party to complete the pending works and after receipt of the legal notice, the opp.party completed plumbing and electrical works and painting of exteriors of the back side of the building. They sent a reply notice stating that the members of the complainant association are due a sum of Rs.2 lakhs towards extra works. The opposite party has collected more than Rs.31,500/- towards electricity and water supply and is bound to provide lift and get it commissioned in proper way. Alleging deficiency in service on behalf of the opposite party, the complainant approached District Forum seeking direction to the opposite party as prayed for in the complaint.
The opposite party filed counter stating that the flat owners have paid only the sale consideration and approximate amounts towards electricity and water connection and the opp.party addressed letter dt.20.12.1999 to the flat owners stating that they have to pay approximately Rs.2 lakhs towards electricity and water charges apart from the amounts they have already paid, but the flat owners failed to make any payment. The opp.party submits that they have incurred expenditure of Rs.40,000/- towards electricity consumption charges consumed by the flat owners on temporary electricity connection from January, 2000 till the regular supply was given. The opp.party submits that there is fault on behalf of the flat owners of complainant association as they did not pay the amounts towards electricity, water connection and sewerage charges because of which the opp.party could not erect the lift in the year 1998 itself. The opp.party further submits that they have commissioned the lift in October,2002 as per the directions of the Forum dt.1.4.2002. and there is no deficiency in service on their behalf and seeks dismissal of the complaint with costs.
The District Forum based on the evidence adduced and pleadings put forward stated that there is no need to interfere with the earlier judgement dt.26.8.2004 which reads as follows:
“In the result, the complainant association is directed to deposit an amount of Rs.2,00,000/- with the opp.party and thereafter within a month after the deposit of the said amount, the opposite party is directed to complete the electricity connection and water connection and other minor pending works.”
The brief point that falls for consideration is whether the complainant is liable to pay Rs.2 lakhs for the water connection?
Aggrieved by this order the complainant preferred this appeal.
It is a case of the complainant that the members of the complainant association entered into separate construction agreements with the opp.party to purchase their respective residential units. As per the terms of the said construction agreement (Ex.A29) the opp.party has to complete the construction within 12 months from the date of the agreement and as per clause 15’C’ the purchasers have to bear the cost of the external electrification such as meter boxes, fixing of the meter, electricity transformer, laying of cables, security deposit etc. by paying the said approximate cost of Rs.15,000/- to the developer. Clause 15‘d’ of construction agreement (Ex.A29) specifies that an approximate amount of Rs.10,000/- should be paid by the purchaser towards the demands raised by HMWSB. These two amounts have to be borne over and above the agreed sale consideration. The members of the complainant association took possession of their flats between December, 1999 and February, 2000 on various dates. It is a complainant’s case that the opposite party did not complete several pending works as follows:
1. Commissioning of the lift.
2. Provision of starter to municipal water motor.
3. Provision of windows and electric wiring to office room and watchman room
4. Provision of door to the lift room on the terrace
5. Allotment of car parking area.
6. Provision of H.P.motor for pumping drinking water
7. Provision of grill and internal pending works like electrical, carpentory and masonry.
8. Handover all original documents like sanctioned plan, BRS sanctioned plan, development agreement, GPA, original link documents , documents pertaining to erection of transformer and water and sewerage to the complainant’s association.
9. To complete all civil pending works vide their representation dt. 24.4.2000.
The complainant submits that inspite of reminders and also meeting on 30.4.2000 the opp.party did not complete these works and so they got issued legal notice on 3.7.2000 (Ex.A33) for which the opp.party issued reply dt.24.7.2000 (Ex.A34) in which the opp.party contended that it has completed almost all the works such as construction of compound wall and starter for municipal water and when the balance amounts are received commissioning of lift will be started.
The complainant filed Exs.A1 to A50 in support of its case .
It is a case of the opp.party that they have commissioned the lift in October,2002 as per directions of the Forum on 1.4.2002 and contended that as per Ex.B33 dt.2.2.2000 issued by A.P.Transco an amount of Rs.2,80,000/- is to be paid towards electricity connection charges and also an amount of 2,05,570/- (Ex.B34) is to be paid towards water and sewerage charges. The learned counsel for the opposite party contended that all these amounts were paid towards electricity connection and water and sewerage under Ex.B1, B19, B24, B48 and B49. He contends that apart from these amounts he also paid an amount of Rs.38,195/- towards electricity consumption charges evidenced under Exs.B23, B25 and B55.
The learned counsel for the appellant/complainant contended that they have never asked for water connection and hence the question of payment of Rs.2 lakhs for the water connection does not arise .
A brief perusal of the record and main complaint copy shows that the complainant’s prayer does not include water connection. We also perused Ex.A30 dt.24.4.2000 wherein the complainant pointed out various defects and Ex.A31 which are the minutes of the meeting held on 30/4/2000 in which the opp.party has signed these minutes and had promised to complete the pending works with respect to plumbing, masonry, commissioning of lift, construction of compound wall, handing over of original documents and allotment of car parking. It is apparent on the face of record vide Ex.A30 and A31 that there has never been any demand for water connection on behalf of the complainant association or any counter demand on respondent/opp.party for payment of Rs.2 lakhs from the complainant association towards water connection. The Dist Forum relied on Ex.A21 which is the letter dt.20.12.99 in which an amount of Rs.2 lakhs was demanded towards water/electricity and sewerage connection charges. Firstly the minutes of the meeting Ex.A31 is dt.30.4.2000 which is subsequent to Ex.A21 and secondly we also observe from Ex.A21 that this demand has not been addressed to the flat owners association but an individual flat owner of flat no. 203 and also it has not been specifically made towards water connection alone. Taking into consideration that there was never any prayer from the complainant towards water connection and keeping in view the afore mentioned facts and circumstances of the case we are of the considered view that the order of the District Forum with respect to payment of Rs.2 lakhs by the complainant is to be set aside. The learned counsel for the complainant submitted that all the reliefs prayed for have been complied with except for submission of documents for which the opposite party agreed vide Ex.A31 dt.30.4.2000. Keeping in view that the respondent/opp.party has agreed to handover the original documents as per Ex.A31 we direct the opp.party to handover these documents under acknowledgment to the complainant association within four weeks from the date of receipt of this order. The member should not raise any contention with regard to the custody of the documents and equally the association should keep the documents without parting it to any of the parties and should keep the documents in safe custody
In the result this appeal is allowed in part by setting aside the order of the District Forum with respect to payment of Rs.2 lakhs to be made by the complainant and we direct the respondent/opp.party to handover the documents as per Ex.A31 along with the afore mentioned directions within four weeks from the date of receipt of this order together with costs of Rs.5000/-. Time for compliance four weeks.
PRESIDENT
MEMBER
20.8.2010
PM*