Prem Kumar Gupta filed a consumer case on 20 May 2015 against M/s Parsvnath Developers Ltd. in the StateCommission Consumer Court. The case no is CC/66/2015 and the judgment uploaded on 04 Jun 2015.
Prem Kumar Gupta son of Tara Chand Gupta, resident of B-XXX-891, Sherpur Road, Chandigarh, through Power of Attorney Ravi Kant Sahni @ Ravi Kant Sawhney son of Sh. Jagdish Kumar, resident of House No.298, Sector 8, Panchkula.
……Complainant
V e r s u s
M/s Parsvnath Developers Limited, a Company incorporated under the provisions of the Companies Act 1956, having its Registered Office at 6th Floor, Arunanchal Building 19, Barakhamba Road, New Delhi-141001 and Local Office at SCO No.1, 1st Floor, Sector 26, Madhya Marg, Chandigarh, through its Chairman/Managing Director/Authorized Person.
Second Address:- Parsvnath Project Pride Asia, RGCTP, Opposite Mahindra, I.T. Park, Chandigarh.
Chandigarh Housing Board, established and constituted under Section 3 of the Haryana Housing Board Act 1971, as extended to UT Chandigarh, having its Office at 8, Janmarg, Sector-9, Chandigarh, through its Chairman.
.... Opposite Parties
Complaint under Section 17 of the Consumer Protection Act, 1986.
BEFORE: JUSTICE SHAM SUNDER (RETD.), PRESIDENT.
MR. DEV RAJ, MEMBER.
MRS. PADMA PANDEY, MEMBER
Argued by: Sh. B.B.S. Sobti, Advocate for the complainant.
Sh.Aftab Singh, Advocate for Opposite Party No.1
Sh.Vishal Sodhi, Advocate for Opposite Party No.2.
JUSTICE SHAM SUNDER (RETD.), PRESIDENT
The facts, in brief, are that, vide application dated 24.12.2007, at page 40 of the file, the complainant applied for the allotment of a residential flat, in the project of Opposite Party No.1, known as “Parsvnath Prideasia”, Rajiv Gandhi Chandigarh Technology Park, Chandigarh, to be developed, and constructed by it, on the land of Opposite Party No.2. Alongwith the application form, an amount of Rs.6,07,750/-, as earnest money, vide cheque No.134586 dated 16.12.2008, in respect of the said unit, was also paid by the complainant. The total sale consideration of the said unit was to the tune of Rs.1,21,55,000/-.
It was stated that the complainant was allotted flat No.4, in the said project. The complainant paid the total amount of Rs.34,38,750/-, towards part price of the said unit, to the Opposite Parties.
It was further stated that the Flat Buyer Agreement dated 26.03.2008 Annexure-1, was executed amongst the parties, at Chandigarh. As per Clause 9 (a) of the said Agreement (at page 27 of the file), construction of the residential units and other related infrastructure, was likely to be completed, within a period of 36 months, from 06.10.2006, the date of signing the Development Agreement.
It was further stated that after the stipulated date of handing over possession of the said unit, the complainant visited the site, where the flats were to be constructed, and came to know that the Opposite Parties failed to construct the same (flats). It was further stated that it also came to the knowledge of the complainant that the project of the Opposite Parties had been cancelled, on account of their interse dispute.
It was further stated that it was found that the entire project of the Opposite Parties was nothing but a farce. It was further stated that, as such, the amount of Rs.34,38,750/-, deposited by the complainant, towards part price of the said unit, was refunded by the Opposite Parties, in the ratio of 70:30 i.e. Rs.24,07,125/- by Opposite Party No.1, vide cheque No.34080 dated 10.02.2015 and Rs.10,31,625/- by Opposite Party No.2, vide DD No.886329 dated 06.02.2015. Opposite Party No.2 also paid interest @9% P.A., to the tune of Rs.5,80,977/- vide DD No.886889 dated 03.03.2015. It was further stated that, however, interest on the amount of Rs.24,07,125/-, as per Clause 9 (c) of the Flat Buyer Agreement dated 26.03.2008 Annexure-1, was not paid by Opposite Party No.1. It was further stated that even the interest which was paid by Opposite Party No.2, was wrongly calculated by it. It was further stated that even compensation, as per the Flat Buyer Agreement dated 26.03.2008 Annexure-1, was not paid by the Opposite Parties.
It was further stated that the aforesaid acts of the Opposite Parties, amounted to deficiency, in rendering service, as also indulgence into unfair trade practice. When the grievance of the complainant, was not redressed, left with no alternative, a complaint under Section 17 of the Consumer Protection Act, 1986 (hereinafter to be called as the Act only), was filed, claiming various reliefs.
The Opposite Parties were served and put in appearance on 21.04.2015.
In its short written statement, filed on 19.05.2015, Opposite Party No.1 pleaded that the complaint was barred by time. It was further pleaded that the consumer complaint was not maintainable, and only a suit for specific performance, in the Civil Court, for enforcement of the Agreement, could be instituted. It was further pleaded that even the instant complaint under the Act, was barred, on account of the reason that remedy for the settlement of dispute, by way of arbitration, had already been availed of, by the Opposite Parties. It was stated that the award dated 09.01.2015 had already been made by the Arbitrator. It was admitted that the Flat Buyer Agreement dated 26.03.2008 Annexure-1, was executed amongst the complainant, and the Opposite Parties. Allotment of flat No.4, in favour of the complainant, in the said project was also admitted. The price of the flat, as stated by the complainant, in the complaint, was also admitted. It was also admitted that the complainant deposited a sum of Rs.34,38,750/-, towards part price of the unit, in question. It was further stated that, as per award dated 09.01.2015, made by the Arbitrator, Opposite Party No.1, had already refunded the amount of Rs.24,07,125/- being 70% of its share of the principal amount, vide cheque No.34080 dated 10.02.2015. It was further stated that since the complainant had encashed the said cheque, as such, neither Opposite Party No.1, was liable to pay any interest thereon, nor compensation, for mental agony and physical harassment.
It was further stated that the Hon’ble Supreme Court, vide its order dated 10.05.2013, passed in Special Leave Petition No.17133-134 of 2013, in the case titled as Parsvnath Developers Ltd. & another Vs. Harsohin Kaur & another stayed the operation of the judgment, in so far as the payment of compensation under Clause 9(c) of the Flat Buyers' Agreement, was concerned. It was denied that Opposite Party No.1, was deficient, in rendering service, and indulged into unfair trade practice. The remaining averments, were denied, being wrong.
In its written statement filed on 29.04.2015, Opposite Party No.2 pleaded that the complaint was barred by time. It was admitted that the complainant was allotted the unit, in question, in Parsvnath Prideasia, in the manner, referred to above. It was also admitted that the Flat Buyer Agreement dated 26.03.2008 Annexure-1, was executed, amongst the complainant and the Opposite Parties. It was also admitted that the complainant deposited Rs.34,38,750/- towards part price of the unit, as per the payment plan. It was stated that, as per Clause 9(e) of the Flat Buyer Agreement dated 26.03.2008 Annexure-1, Opposite Party No.2, Chandigarh Housing Board, was to only provide the land for the project and the Developer (Opposite Party No.1) was to undertake development of the said project, and, as such, it (Developer), was solely responsible for all quality parameters, timely delivery of residential units, all claims/liabilities and compensation, towards defects/ delay etc. It was further stated that since Opposite Party No.2, had already refunded the amount of Rs.10,31,625/- being 30% of its share of the principal amount, vide DD No.886329 dated 06.02.2015, as also interest @9% P.A., to the tune of Rs.5,80,977/- vide DD No.886889 dated 03.03.2015, from the respective date(s) of deposits till the date of refund, neither it was liable to pay any further interest thereon, nor compensation, for mental agony and physical harassment. It was further stated that neither there was any deficiency, in rendering service, nor indulgence into unfair trade practice, on the part of Opposite Party No.2.
The complainant, in support of his case, led evidence, by way of filing the affidavit of Sh. Ravi Kant, his power of attorney holder, alongwith which, a number of documents were attached.
Opposite Party No.1, filed the short affidavit of Mr.Yudhvir Arora, its Senior Manager (Commercial), by way of evidence, alongwith which, a number of documents were attached.
Opposite Party No.2, in support of its case, filed the affidavit of Mr. M.L. Chauhan, Chief Accounts Officer, Chandigarh Housing Board, Chandigarh, alongwith which, a number of documents were attached.
We have heard the Counsel for the parties, and have gone through the evidence and record of the case, carefully.
The Counsel for the complainant, submitted that the complainant, applied for the allotment of a flat, and he was, ultimately, allotted flat No.4, in the project of Parsvnath Prideasia, Rajiv Gandhi Chandigarh Technology Park, Chandigarh. He further submitted that the complainant deposited the total amount of Rs.34,38,750/-, with the Opposite Parties. He further submitted that, as per the Flat Buyer Agreement dated 26.03.2008 Annexure-1, the construction of residential units, was likely to be completed within 36 months of signing the Development Agreement dated 06.10.2006, between the Developers and the Chandigarh Housing Board. He further submitted that though a sum of Rs.34,38,750/-, was deposited by the complainant, towards part price of the flat, in question, yet not even a brick was laid, at the spot, what to speak of construction of flats. He further submitted that though there was no breach of the Agreement, on the part of the complainant, yet, neither the project was developed nor the question of delivery of possession of the flat arose. He further submitted that the complainant, therefore, could not wait for an indefinite period, and was entitled to the refund of entire amount, deposited by him, with interest, as also compensation for mental agony and physical harassment. He further submitted that, no doubt, Opposite Party No.2, refunded 30% principal amount of its share to the complainant, alongwith interest, referred to above, yet, on the other hand, Opposite Party No.1 was certainly deficient, in rendering service, to him (complainant), by neither paying interest on the amount of Rs.24,07,125/- refunded by it, towards 70% of its share of the principal amount, nor paying him the compensation, as per Clause 9 (c) of the Flat Buyer Agreement dated 26.03.2008 Annexure-1, and it also indulged into unfair trade practice.
On the other hand, the Counsel for Opposite Party No.1, submitted that since the Flat Buyer Agreement Annexure-1, was executed amongst the parties, on 26.03.2008, and possession of the said unit, was to be handed over to the complainant by 05.10.2009, as per the Development Agreement dated 06.10.2006, executed between the Opposite Parties, the complaint having been filed by him (complainant), on 07.04.2015, was barred by limitation. He further submitted that the instant complaint under the Act, was also barred, on account of the reason that remedy for the settlement of disputes, by way of arbitration was availed of by the Opposite Parties, and award dated 09.01.2015, had already been made by the Arbitrator. He further submitted that, as per award dated 09.01.2015, made by the Arbitrator, Opposite Party No.1, had already refunded the amount of Rs.24,07,125/- being 70% of its share of the principal amount, vide cheque No.34080 dated 10.02.2015. He further submitted that only a suit for specific performance was maintainable. He further submitted that since the complainant had admittedly received the said amount, as such, neither Opposite Party No.1, was liable to pay any interest thereon, nor compensation/penalty for the period of delay, nor compensation, for mental agony and physical harassment. He further submitted that the Hon’ble Supreme Court, vide its order dated 10.05.2013, passed in Special Leave Petition No.17133-134 of 2013, in the case titled as Parsvnath Developers Ltd. & another Vs. Harsohin Kaur & another stayed the operation of judgment, in so far as the payment of compensation under Clause 9(c) of the Flat Buyers Agreement was concerned. He further submitted that, under these circumstances, Opposite Party No.1, was neither deficient, in rendering service, nor it indulged into unfair trade practice nor it was liable to pay compensation.
The Counsel for Opposite Party No.2, submitted that since as per the Escrow Agreement, Opposite Party No.2, had already refunded the amount of Rs.10,31,625/- being 30% of its share of the principal amount, vide DD No.886329 dated 06.02.2015, as also interest @9% P.A., to the tune of Rs.5,80,977/- vide DD No.886889 dated 03.03.2015, from the respective date(s) of deposits till the date of refund, and the remaining amount, alongwith interest, was to be paid by Opposite Party No.1, neither it was liable to pay any further interest thereon, nor compensation, for mental agony and physical harassment to the complainant.
The first question, that falls for consideration, is, as to whether, the complaint filed by the complainant, is within limitation or not. It may be stated here, that, no doubt, the Flat Buyer Agreement Annexure-1, in respect of the said unit, was executed amongst the parties, on 26.03.2008, yet, neither physical possession of the flat, by the promised date i.e. 05.10.2009, was delivered to the complainant, as per the terms and conditions of the same (Agreement), nor interest on the amount of Rs.24,07,125/- being 70% of its share of the principal amount refunded, vide cheque No.34080 dated 10.02.2015, was paid by Opposite Party No.1. At the most, cause of action arose to the complainant on 10.02.2015, when payment of the principal amount without interest and compensation was made by Opposite Party No.1, in his favour. The complaint having been filed on 06.04.2015, thus, was well within limitation. The submission of the Counsel for Opposite Parties, in this regard, being devoid of merit, must fail, and the same stands rejected
s rejected.stated here, that teh The next question, that falls for consideration, is, as to whether, the instant complaint, under the Act, was barred, on account of the reason that remedy for the settlement of dispute, by way of arbitration, had already been availed of, by the Opposite Parties, and award dated 09.01.2015, was given by the Arbitrator. It may be stated here, that the same does not merit acceptance. With a view to appreciate the controversy, in its proper perspective, reference to Section 3 of the Consumer Protection Act, 1986, is required to be made, which reads as under;
“3. Act not in derogation of any other law.—
The provisions of this Act shall be in addition to and not in derogation of the provisions of any other law for the time being in force.”
Section 3 of the Act, is worded in widest terms, and leaves no manner of doubt, that the provisions of the Act, shall be, in addition to, and not in derogation of any other law, for the time being, in force. The mere fact that the remedy of arbitration, which was provided in Clause 18 of the Escrow Agreement, had already been availed of by the Opposite Parties and the award was given on 09.01.2015, would not oust the Jurisdiction of this Commission, in view of the provisions of Section 3 of the Act. Similar principle of law, was laid down, in Fair Engg. Pvt. Ltd. & another Vs N.K.Modi III (1996) CPJ 1 (SC) and C.C.I Chambers Coop. Housing Society Ltd. Vs Development Credit Bank Ltd. III (2003) CPJ 9 (SC). Not only this, the Arbitrator in his decision under Claim No.(11) of the Award dated 09.01.2015, wherein Opposite Party No.1 was the claimant and Opposite Party No.2 was the respondent held as under:-
“The claimant and respondent are liable to bear and pay the amounts payable to the residential unit buyers/customers, towards refund of the advance payments, interest and compensation, as directed by the consumer fora/Courts, their interse liability being in the ratio 70:30 respectively”.
In this view of the matter, the submission of the Counsel for the Opposite Parties, being devoid of merit, must fail, and the same stands rejected.
The next question, that falls for consideration, is, as to whether, since the complainant sought enforcement of the Flat Buyer Agreement dated 26.03.2008 Annexure-1, in respect of the immoveable property, only a suit for specific performance, in the Civil Court was maintainable. It may be stated here, that the complainant hired the services of the Opposite Parties, for purchasing the flat, in question, and he was allotted the same for consideration. According to Clause 9 (a) of the said Agreement (at page 27 of the file), the construction of the residential units and other related infrastructure, was likely to be completed, within a period of 36 months, from 06.10.2006, the date of signing the Development Agreement. According to this Clause, the Opposite Parties were committed to deliver possession of the unit, in question, to the complainant. It was not that the complainant purchased the unit, in an open auction, on “as is where is basis”. Section 2 (1) (o) of the Act, defines service as under:-
“service” means service of any description which is made available to potential users and includes, but not limited to, the provision of facilities in connection with banking, financing insurance, transport, processing, supply of electrical or other energy, board or lodging or both, housing construction, entertainment, amusement or the purveying of news or other information, but does not include the rendering of any service free of charge or under a contract of personal service”
From the afore-extracted Section 2 (1) (o) of the Act, it is evident that housing construction, also comes within the definition of a service. In Narne Construction P. Ltd., etc. etc. Vs. Union Of India andOrs. Etc., II (2012) CPJ 4 (SC), it was held that when a person applies for the allotment of a building or site or for a flat constructed by the Development Authority and enters into an Agreement with the Developer, or the Contractor, the nature of transaction is covered by the expression ‘service’ of any description. Housing construction or building activity carried on by a private or statutory body constitutes ‘service’ within the ambit of Section 2(1)(o) of the Act. Similar principle of law, was laid down, in Haryana Agricultural Marketing Board Vs. Bishambar Dayal Goyal & Ors. (AIR 2014 S.C. 1766). Under these circumstances, the complaint involves the consumer dispute, and the same is maintainable. Not only this, Section 3 of the Act, provides an alternative remedy. Even if, it is assumed that the complainant had a remedy to file a suit, for specific performance, in the Civil Court, the alternative remedy provided under Section 3 of the Act, could be availed of by him, as he falls within the definition of a consumer. In this view of the matter, the submission of the Counsel for the Opposite Parties, being devoid of merit, must fail, and the same stands rejected.
The next question, that arises for consideration, is, as to within which period, the construction of the residential units, was likely to be completed. There is, no dispute, about the factum that the complainant applied for the allotment of a flat, and he was finally allotted flat No.4, in the manner, explained above. He deposited the amount of Rs.34,38,750/-, towards part price of the flat, according to the payment plan, as admitted by the Opposite Parties. Clause 9 (a) of the Flat Buyer Agreement dated 26.03.2008 Annexure-1, referred to above, which is relevant, for answering the question, posed, at the outset of this paragraph, reads as under ;
“Construction of the residential units is likely to be completed within a period of thirty six (36) months of the signing of the Development Agreement i.e. 06.10.2006 between the Developer and CHB and/or as may be extended in terms of the Development Agreement shall be subject to force majeure and circumstances beyond the control of the Developer, and any restrains, restrictions from any Courts/ authorities. The delay in grant of environmental clearances beyond 12 months of the signing of the Development Agreement shall not be counted towards the said period of 36 months.”
The plain reading of Clause 9(a) of the Flat Buyer Agreement, extracted above, clearly goes to reveal that construction of the residential units, was to be completed, within a period of thirty six months of signing the Development Agreement dated 06.10.2006. The time could be extended, in terms of the Development Agreement, dated 06.10.2006, subject to force majeure, and the circumstances, beyond the control of the Developer. No document was produced by Opposite Party No.1, that any restriction was imposed by any Court or Authority, upon it, or the project, in question, as a result whereof, it could not raise construction of the residential units, in time. Opposite Party No.1, fleeced the complainant of his huge amount, by making misleading statement that the construction of residential units, will be completed within 36 months from 06.10.2006. Even, long after the expiry of the stipulated period, not even a brick was laid, at the site, what to speak of raising construction. Opposite Party No.1, thus, indulged into unfair trade practice. It is, therefore, held that construction of the residential units was to be completed within 36 months from 06.10.2006 i.e. by 06.10.2009.
The next question, that arises for consideration, is, as to whether, the complainant is entitled to the refund of amount, deposited by him, with interest or not? Clause 9 (d) of the Flat Buyer Agreement dated 26.03.2008 Annexure-1, which is relevant, to answer this question, reads as under;
“9(d) If as a result of any rules or directions of the Government or if any competent authority delays, withholds, denies the grant of necessary approvals for the Project, or if due to any force majeure conditions, the Developer is unable to deliver the unit to the Buyer, the Developer and CHB shall be liable to refund to the Buyer the amounts received from the Buyer with interest at the SBI Term Deposit Rate as applicable on the date of refund.”
The complainant deposited the amount towards part payment of the price of flat, in the hope of getting its possession, within a period of 36 months from 06.10.2006, but he found that there was no development, and even a single brick, had not been laid, at the spot, what to speak of construction of flats, and delivery of possession thereof, to the buyers. In these circumstances, the complainant could not wait for an indefinite period. The only option left with the complainant, in such circumstances, was to ask for the refund of amount. The plain reading of Clause 9(d) extracted above, reveals that if the Developer for, whatever the reasons may be, fail to deliver possession of the residential unit to the buyers, it (Developer) and the Chandigarh Housing Board, shall be liable to refund the amounts, received from the buyers, with interest, at the SBI Term Deposit Rate, as applicable, on the date of refund. The Opposite Parties were, thus, deficient, in rendering service, by neither delivering possession of the flat, within the stipulated time, nor refunding the amount immediately, with interest, as provided under Clause 9(d) of the Agreement, referred to above.
It may be stated here that 'Interest' in general terms is the return or compensation for the use or retention by one person of a sum of money belonging to or owed to another. In its narrow sense, 'interest' is understood to mean the amount, which one has contracted to pay for use of borrowed money. In whatever category 'interest' in a particular case may be put, it is a consideration paid either for the use of money or for forbearance in demanding it, after it has fallen due, and thus, it is a charge for the use or forbearance of money. In the instant case, as per Clause 9(d) extracted above, as stated above, in case, the project is abandoned or the construction could not be carried out, on account of certain reasons, then in that event, refund of the amount was to be made at the SBI Term rate deposit of interest. Since, the project had not taken off at all, the question of offering the possession by 05.10.2009, did not at all arise. It was, thus, the duty of the Opposite Parties, to offer the refund of amount to the complainant, the moment the stipulated date, for the delivery of possession expired. The Opposite Parties, however, did not make any offer, immediately, despite the fact that the project had not taken off, and no construction of the flats, had taken place, but, on the other hand, refunded the same, in the year 2015, in the manner, referred to above. The Opposite Parties, thus, had utilized the money, deposited by the complainant, for a long time. The Opposite Parties had been earning handsome returns, on the amount, deposited by the complainant, either by depositing the same, in the Bank, or by investing the same, in some other projects. Had the amount been returned to the complainant immediately after the stipulated date, when the Opposite Parties were unable to deliver possession of the flats, he (complainant) would have either deposited the same, in some Bank and earned handsome returns or invested the same, in some business, resulting into handsome income, to him. The complainant was, thus, deprived of his money, illegally and arbitrarily retained by the Opposite Parties, and, as such, he (complainant) was entitled to interest, on the amount deposited, from the respective dates of deposits, till the refund was made, in the manner, referred to above, as per Clause 9(d) of the Flat Buyer Agreement dated 26.03.2008 Annexure-1.
Now the next question, that arises for consideration, is, as to what amount, the complainant is entitled to. It is evident from the record that vide cheque No.34080 dated 10.02.2015, Opposite Party No.1, had refunded the amount of Rs.24,07,125/- being 70% of its share of the principal amount, to the complainant. Thus, in our considered opinion, since Opposite Party No.1, has already refunded Rs.24,07,125/- being 70% of its share of the principal amount, on 10.02.2015, to the complainant, it is only liable to pay interest, on the said amount, from the respective dates of deposits till that date (10.02.2015) at the SBI Term deposit rate of interest, according to Clause 9(d) of the Flat Buyer Agreement dated 26.03.2008 Annexure-1. By not paying the interest on the amount of Rs.24,07,125/-, at the SBI Term deposit rate of interest, according to Clause 9(d) of the Flat Buyer Agreement dated 26.03.2008 Annexure-1, Opposite Party No.1 was deficient, in rendering service and also adopted unfair trade practice.
As far as the liability of Opposite Party No.2, is concerned, it may be stated here, that it is evident from the record that it has already refunded Rs.10,31,625/-, being 30% of the principal amount, vide DD No.886329 dated 06.02.2015, as also interest @9% P.A., to the tune of Rs.5,80,977/- vide DD No.886889 dated 03.03.2015, from the respective date(s) of deposits till the date of refund. Thus, in our considered opinion, since Opposite Party No.2, has already refunded Rs.10,31,625/-, being 30% of its share of the principal amount, alongwith interest at the rate aforesaid, according to Clause 9(d) of the Flat Buyer Agreement dated 26.03.2008 Annexure-1, no relief survives against it, and the complaint qua Opposite Party No.2, deserves to be dismissed.
The next question, that arises for consideration, is, as to whether, the complainant is entitled to compensation, for not handing over possession to him, as per the terms and conditions of the Flat Buyer Agreement dated 26.03.2008 Annexure-1, referred to above, and for deficiency in service and indulgence into unfair trade practice, by Opposite Party No.1. Clause 9 (c) of the Agreement, which is relevant for answering the question, reads as under :
“9(c) In case of possession of the built up area is not offered to the Buyer within a period of 36 months or extended period as stipulated in sub-clause (a) above the Buyer shall be entitled to receive from Developer compensation @ Rs.107.60 per sq.mtr (Rs.10/- per sq.ft) of the super area of the unit per month and to no other compensation of any kind. In case the Buyer fails to clear his account and take possession of the unit within 30 days of offer, the Buyer shall be liable to pay to the Developer holding charges @ 107.60 per sq.mtr. (Rs.10/- per sq.ft) of the super area of the unit per month in addition to the liability to pay interest to the sellers and other consequences of default in payment. ”
The possession of the flat was not offered, to the buyers, within a period of 36 months from 06.10.2006. As stated above, even till date, not even a single brick, has been laid, at the spot. In these circumstances, as per Clause 9 (c) of the aforesaid Agreement, the complainant became entitled to compensation @107.60 per sq.mtr (Rs.10/- per sq.ft.) of the super area of the unit, per month from 06.10.2009 onwards, which was to be paid by Opposite Party No.1. By not paying the compensation aforesaid, Opposite Party No.1 was deficient, in rendering service.
The next question, that arises for consideration, is, as to whether, the complainant is entitled to compensation for mental agony and physical harassment, as claimed by him, when he had already been granted compensation, as per Clause 9 (c) of the aforesaid Agreement. In our considered opinion, the complainant is not entitled to additional compensation for mental agony and physical harassment. Once, it has already been held by this Commission above, that as per Clause 9 (c) of the aforesaid Agreement, the complainant became entitled to compensation @107.60 per sq.mtr (Rs.10/- per sq.ft.) of the super area of the unit, per month from 06.10.2009 onwards, he could not be granted any further compensation for mental agony and physical harassment. It is settled principle of law, that the parties are bound by the terms and conditions of the contract, entered into between them. In Bharathi Knitting Company vs. DHL Worldwide Express Courier Division of Airfreight Ltd.1996 (IV) 4 SCC 704, a case decided by a three Judge Bench of the Hon'ble Supreme Court, a question arose, that when the parties had contracted and limited their liabilities, whether the State/National Commission could go beyond the terms of the contract, and give relief for damages, in excess of the limit, prescribed under the same (contract) or not. It was held that when there is a specific term, in the contract, signed by the parties, they are bound by the same, and relief for damages, in excess of the limit, prescribed under the same (contract), cannot be given. The principle of law, laid down, in the aforesaid case, is fully applicable to the facts of the instant case. Under these circumstances, as stated above, the complainant is only entitled to compensation/penalty as per Clause 9 (c) of the aforesaid Agreement, i.e. @107.60 per sq.mtr (Rs.10/- per sq.ft.) of the super area of the unit, per month from 06.10.2009 onwards. The complainant is, thus, not entitled to any additional compensation for mental agony and physical harassment, claimed by him. The submission of the Counsel for the complainant, in this regard, being devoid of merit, must fail, and the same stands rejected.
No other point, was urged, by the Counsel for the parties.
For the reasons, recorded above, the complaint is partly accepted with costs of Rs.10,000/-, and Opposite Party No.1, is directed as under:-
To pay interest on the amount of Rs.24,07,125/- at the SBI Term Deposit rate, (as applicable on 10.02.2015) as per Clause 9(d) of the Flat Buyer Agreement dated 26.03.2008 Annexure-1, from the respective dates of deposits, till 10.02.2015, the date when the same (Rs.24,07,125/-) was refunded to the complainant, vide cheque/ demand draft dated 10.02.2015.
To pay compensation @ Rs.107.60 per sq. mtr (Rs.10/- per sq.ft) of the super area of the unit, per month, from 06.10.2009, the last date of completion of the project, till actual payment of interest as indicated above, to the complainant is made, as provided by Clause 9 (c) of the Flat Buyer Agreement dated 26.03.2008 Annexure-1.
To pay cost of litigation, to the tune of Rs.10,000/-, to the complainant.
To comply with the aforesaid directions, within a period of 30 days, from the date of receipt of a certified copy of this order, failing which it (Opposite Party No.1) shall be liable to pay penal interest @ 12% p.a., instead of SBI Term Deposit rate of interest, on the amount of Rs.24,07,125/- from the date of default till realization, besides payment of costs of Rs.10,000/-.
The complaint qua Opposite Party No.2 is dismissed with no order as to costs.
Certified Copies of this order be sent to the parties, free of charge.
The file be consigned to Record Room, after completion.
Pronounced.
May 20, 2015
Sd/-
[JUSTICE SHAM SUNDER (RETD.)]
PRESIDENT
Sd/-
[DEV RAJ]
MEMBER
Sd/-
(PADMA PANDEY)
MEMBER
Rg.
Consumer Court Lawyer
Best Law Firm for all your Consumer Court related cases.