Pushpa Devi filed a consumer case on 16 Nov 2018 against M/s Omaxe Chandigarh Extension Developers Pvt. Ltd. in the StateCommission Consumer Court. The case no is CC/275/2017 and the judgment uploaded on 29 Nov 2018.
STATE CONSUMER DISPUTES REDRESSAL COMMISSION,
U.T., CHANDIGARH
Complaint case No. | : | 275 of 2017 |
Date of Institution | : | 31.03.2017 |
Date of Decision | : | 16.11.2018 |
Pushpa Devi W/o Sh.Vijay Kumar, resident of House No.306, Sector 13, Hisar.
……Complainant
M/s Omaxe Chandigarh Extension Developers (P) Limited, SCO No.139-140, First Floor, Sector 8-C, Madhya Marg, Chandigarh-160008, through its Managing Director/Principal Officer/ Authorized Officer.
2nd Address:- 10 L.S.C., Kalkaji, New Delhi-110019.
.... Opposite Party
Complaint under Section 17 of the Consumer Protection Act, 1986.
BEFORE: JUSTICE JASBIR SINGH (RETD.), PRESIDENT
MRS.PADMA PANDEY, MEMBER
SH.RAJESH K. ARYA, MEMBER
Argued by: Sh.Saroj Malakar, Advocate for the complainant.
Sh.Munish Gupta, Advocate for the opposite party.
PER PADMA PANDEY, MEMBER
The complainant has filed this complaint seeking possession of plot bearing no.1054, measuring 301 square yards, purchased in the project of the opposite party, named ‘Omaxe New Chandigarh’, Mullanpur, Punjab, total cost whereof was fixed at Rs.33,62,351.79ps. inclusive of all charges. It is definite case of the complainant that despite the fact that as per demands raised by the opposite party from time to time, she has paid substantial amount of Rs.28,98,235/- towards price of the said plot, yet, it failed to deliver possession thereof, within a period of 18 months plus 6 months totaling 24 months from 06.06.2012, as envisaged under Clause 24 (a) of the Allotment Letter of even date i.e. on or before 05.06.2014. It was stated that since the complainant is not in the custody of payment receipts and allotment letter, pertaining to the plot, in question, as such, the opposite party be directed to produce the same on record. It was prayed that let directions be issued to the opposite party to hand over possession of the plot, in question, to the complainant; get registered sale deed; to make payment of interest on the deposited amount @18% p.a., from the due date till delivery of possession of the plot; pay compensation for mental agony, physical harassment and also litigation expenses.
As such, under above circumstances, the only question that needs consideration, is, as what relief can be granted to a consumer, in case of delay in offering possession of a residential unit/plot purchased, in the absence of any force majeure circumstances having been faced by the builder. The said question, came up for consideration before this Commission in Ankur Gupta Vs. Omaxe Chandigarh Extension Developers Pvt. Ltd. and another, Consumer Case No.309 of 2016 decided on 22.11.2016, wherein, it was observed as under:-
“What relief can be granted to a consumer, in case of delay, in offering possession, came up for consideration before the Hon’ble National Commission, in a case titled as Parsvnath Exotica Ghaziabad Resident's Association Vs. Parsvnath Buildwell Pvt. Ltd. & Anr., consumer complaint no.45/2015, decided by the Hon’ble National Commission, on 06.05.2016, wherein, it was argued by the project proponent that at the maximum, as provided in the Agreement, the consumer will be entitled to claim penalty for delayed compensation @Rs.5/- per square feet, per month. Noting that in case of delay in making payment, the project proponent was charging heavy penal interest, instead of penal amount, the interest on the deposited amount, for the period of delay was granted, by holding as under:-
“Though, the Agreement between the developer and the flat buyers provides for payment of compensation in case of delay @ Rs.5/- per square feet of the super area per month, such clauses have been found to be unfair trade practice and have been consistently rejected by this Commission in several decision, including Consumer Complaint No. 427 of 2014 Satish Kumar Pandey & Ors. Vs. Unitech Ltd. and connected matters decided on 08.6.2015. Therefore, the aforesaid clauses cannot be taken into consideration, while determining the compensation payable to the members of the complainant association for the aforesaid delay in completion of construction.”
Not only this, in another case, titled as Capt. Gurtaj Singh Sahni & anr. Vs Manager, Unitech Limited & anr., consumer complaint bearing no.603/2014, decided on 02.05.2016, the Hon'ble National Commission, directed the opposite party/builder to pay interest on the deposited amount, for the period of delay, till delivery of possession of the unit. Relevant contents of the said order reads thus:-
“8. If the compensation for the delay in construction is restricted to what is stipulated in the Buyers Agreement, there will be no pressure upon the builder to complete the construction since he will be more than happy to keep on paying paltry compensation of about 3% per annum of the capital investment, instead of arranging funds at much higher cost, to complete the construction.
9. xxxxxxxxxxxxx
10. For the reasons stated hereinabove, the complaints are disposed of with the following directions:
(1) xxxxxxxxxxxxxx
(2) The opposite party shall pay compensation in the form of simple interest @ 12% per annum from the expected date of possession till the date on which the possession is actually offered to the complainants after completing the construction in all respects and obtaining the requisite completion certificate.”
Thus, keeping in view the principle of law laid down by the Hon'ble National Commission, in the cases, referred to above, if interest @12% on the deposited amount for the period of delay, till delivery of possession of the unit, is awarded, that would meet the ends of justice.”
Not only as above, in H.P. Housing Board Vs. Janak Gupta [2009] INSC 627 (26 March 2009) (Civil Appeal No. 6346 of 2002), it was clearly held by the Hon’ble Supreme Court of India that in the cases of delay, in delivery of possession, award of interest @ 12% per annum, on the deposited amount, for the period of delay, would meet the ends of justice.
In the present case, it is not disputed that Allotment Letter/Agreement was signed between the parties on 06.06.2012. Total price of the unit was fixed at Rs.33,62,351.79ps. It is also not in dispute that by the time this complaint was filed, the complainant had already paid an amount of Rs.28,98,235/-, to the opposite party, which fact is evident from the contents of affidavit submitted by the complainant during pendency of this complaint, which is not seriously disputed by the opposite party. As per Clause 24 (a) of the said Allotment Letter/Agreement, it was clearly stated by the opposite party that the Company shall put its best efforts to complete the development of the plot within 24 months (18 months (+) 06 months extended period) from the date of signing thereof i.e. latest by 05.06.2014. Possession of the unit was delivered only on 02.12.2017, during pendency of this complaint. Admittedly, there is a delay in handing over possession of the plot, in question, to the complainant. Taking note of above said proposition of law, in the present case also, ends of justice would meet, if interest is granted for delayed period, to the complainant whereof 05.06.2014 till 02.12.2017, when possession was delivered to the complainant.
Besides as above, the opposite party is also liable to pay compensation to the complainant, for providing her deficient service and guilty of adoption of unfair trade practice.
Pronounced.
16.11.2018
Sd/-
(JUSTICE JASBIR SINGH (RETD.) PRESIDENT.
Sd/-
(PADMA PANDEY)
MEMBER
Sd/-
(RAJESH K. ARYA)
MEMBER
Rg.
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.