Gorav Gupta filed a consumer case on 10 Aug 2017 against M/s Omaxe Chandigarh Extension Developers Pvt. Ltd. in the StateCommission Consumer Court. The case no is CC/318/2017 and the judgment uploaded on 11 Aug 2017.
STATE CONSUMER DISPUTES REDRESSAL COMMISSION,
U.T., CHANDIGARH
Complaint case No. | : | 331 of 2017 |
Date of Institution | : | 18.04.2017 |
Date of Decision | : | 10-Aug-17 |
Tejpal Kaur wife of R.S. Dhindsa, R/o H.No.99, Sector 9, Ambala (Haryana).
……Complainant
Omaxe Chandigarh Extension Developers Private Limited, SCO No.143-144, Sector 8-C, Chandigarh, through its Managing Director.
.... Opposite Party
Argued by: Sh.G.S. Virk, Brother of the complainant.
Sh.Munish Gupta, Advocate for the opposite party.
======================================================
Complaint case No. | : | 318 of 2017 |
Date of Institution | : | 12.04.2017 |
Date of Decision | : | 10-Aug-17 |
Both R/o House No.2474, Sector 37-C, Chandigarh.
……Complainant
M/s Omaxe Chandigarh Extension Developers Private Limited, Regional Office SCO No.139-140, Sector 8-C, Madhya Marg, Chandigarh.
2nd Address:- Omaxe City, 111th Mile Stone Near Bad Ke Balaji Bus Stand, Jaipur-Ajmer Express Way Jaipur, 302026, through its Managing Director.
3rd Address:- M/s Omaxe Chandigarh 10th LSC, Kalkaji, New Delhi 110019, through its Managing Director.
.... Opposite Party
Argued by: Sh.Raj Kumar Sahota, Advocate for the complainants.
Sh.Munish Gupta, Advocate for the opposite party.
Complaints under Section 17 of the Consumer Protection Act, 1986.
BEFORE: JUSTICE JASBIR SINGH (RETD.), PRESIDENT.
MR. DEV RAJ, MEMBER.
MRS. PADMA PANDEY, MEMBER
PER JUSTICE JASBIR SINGH (RETD.), PRESIDENT
By this order, we propose to dispose of aforesaid two consumer complaints. Arguments were heard in common, in the above cases, as the issues involved therein, except minor variations, here and there, of law and facts are the same. At the time of arguments, on 04.08.2017, it was agreed by the contesting parties, that facts involved in the above complaints, by and large, are the same, and therefore, both the complaints can be disposed of, by passing a consolidated order.
To dictate order, facts are being taken from consumer complaint bearing no.331 of 2017, titled as Tejpal Kaur Vs. Omaxe Chandigarh Extension Developers (P) Ltd. The complainant is a resident of Ambala. To settle near to Chandigarh, she purchased a built-up flat, from the opposite party, in a project, launched by it, namely “Omaxe Cassia” New Mullanpur, Punjab. It was represented to her that the project is fully approved by the Competent Authorities. Further, the unit was booked in the office of the opposite party, situated in SCO No.139-140, Sector 8, Manimajra, Chandigarh. The unit was an independent floor, constructed on the area measuring 300 square yards, having built-up area of 1725 square feet. Total sale price of the unit was fixed at Rs.46.25 lacs. First payment, in the sum of Rs.8 lacs was paid by her on 11.03.2011. Thereafter, from time to time, an amount of Rs.44,75,066/- was paid by her, in the following manner:-
Sr.No. | Receipt No. | Date | Amount |
484119 | 11.03.2011 | 800000.00 | |
530961 | 24.08.2011 | 617381.00 | |
687600 | 22.02.2012 | 330000.00 | |
687605 | 22.02.2012 | 519185.00 | |
687607 | 22.02.2012 | 2208500.00 |
As per Clause 23 (b) of the said Allotment Letter/Agreement, the opposite party undertook to complete the construction work within 30 months (24 months (+) 06 months grace period) from the date of signing of allotment letter dated 09.02.2012 i.e. upto 08.08.2014, subject to force majeure conditions. The said period was to be computed, after excluding Saturdays, Sundays etc. Relevant Clause 23 (b) reads thus:-
“The Company shall put its best efforts to complete the development/construction of the Unit within 24 (Twenty Four) months from the date of signing of this Allotment Letter by the Allottee(s) or within an extended period of 6 (six) months, however construction within aforesaid 30 months is subject to force majeure conditions (as mentioned in Clause (c) & (d) hereunder) and subject to all Unit Allottee(s) making timely payment or subject to any other reasons beyond the control of the Company. No claim by way of damages/compensation shall lie against the Company in case of delay in handing over the possession on account of any of the aforesaid reasons and the Company shall be entitled to a reasonable extension of time for the delivery of possession of the said Unit to the Allottee(s). The aforesaid period of development shall be computed by excluding Sundays, Bank Holidays, enforced Govt. holidays and the days of cessation of work at site in compliance of order of any Judicial/concerned State Legislative Body.”
“As per averments made, it is stated that the basic facilities are missing at the spot. Let the complainant sent a detailed notice to the Opposite Party indicating deficiencies in construction of the unit. If any, such notice is sent by the complainant, the Opposite Party is directed to give specific reply to each query raised by the complainant, within 15 days from receipt of the said letter.
Accordingly, this complaint stands disposed of with liberty to the complainant to file it again, if need be in future.
Certified copies of this order be sent to the parties, free of charge”
We are not going to agree with the objection raised. This Commission, in a case titled as ‘Sarbjit Singh Vs. Puma Realtors Private Limited’, IV (2016) CPJ 126 has already elaborately dealt with this question, while relying upon ratio of judgments of the Hon’ble Supreme Court, titled as Fair Air Engg. Pvt. Ltd. & another Vs. N. K. Modi (1996) 6 SCC 385, C.C.I Chambers Coop. Housing Society Ltd. Vs Development Credit Bank Ltd. (2003) 7 SCC 233, Rosedale Developers Private Limited Vs. Aghore Bhattacharya and others, (Civil Appeal No.20923 of 2013), Secretary, Thirumurugan Cooperative Agricultural Credit Society v. M. Lalitha (2004) 1 SCC 305 and United India Insurance Co. Ltd. Vs. M/s Pushpalaya Printers, I (2004) CPJ 22 (SC), and LIC of India and another Vs. Hira Lal, IV (2011) CPJ 4 (SC), and held that even in the face of existence of arbitration clause in an Agreement, to settle disputes between the parties through Arbitration, in terms of provisions of Section 8 (amended) of 1996 Act, this Commission has jurisdiction to entertain the consumer complaint. Furthermore, under similar circumstances, the National Commission, in a case titled as Lt. Col. Anil Raj & anr. Vs. M/s. Unitech Limited, and another, Consumer Case No.346 of 2013, decided on 02.05.2016, held as under:-
“In so far as the question of a remedy under the Act being barred because of the existence of Arbitration Agreement between the parties, the issue is no longer res-integra. In a catena of decisions of the Hon’ble Supreme Court, it has been held that even if there exists an arbitration clause in the agreement and a Complaint is filed by the consumer, in relation to certain deficiency of service, then the existence of an arbitration clause will not be a bar for the entertainment of the Complaint by a Consumer Fora, constituted under the Act, since the remedy provided under the Act is in addition to the provisions of any other law for the time being in force. The reasoning and ratio of these decisions, particularly in Secretary, Thirumurugan Cooperative Agricultural Credit Society Vs. M. Lalitha (Dead) Through LRs. & Others - (2004) 1 SCC 305; still holds the field, notwithstanding the recent amendments in the Arbitration and Conciliation Act, 1986. [Also see: Skypak Couriers Ltd. Vs. Tata Chemicals Ltd. - (2000) 5 SCC 294 and National Seeds Corporation Limited Vs. M. Madhusudhan Reddy & Anr. - (2012) 2 SCC 506.] It has thus, been authoritatively held that the protection provided to the Consumers under the Act is in addition to the remedies available under any other Statute, including the consentient arbitration under the Arbitration and Conciliation Act, 1986.”
Furthermore, the National Commission in a case titled Omaxe Limited Vs. Dinesh Lal Tarachandani, First Appeal No.1433 of 2016, decided on 24.11.2016, while dismissing the appeal filed by the builder (Omaxe), held as under:-
“We are unable to persuade ourselves to agree with the Learned Counsel. In our opinion, the decision of the State Commission being based on the authoritative pronouncements by the Hon’ble Supreme Court and also on the decision dated 02.05.2016, rendered by this Bench in the case of Lt. Col. Anil Raj & Ors. Vs. M/s Unitech Limited & Ors. in CC No. 346/2013, in which we have held that notwithstanding the amendments in the Arbitration Act, the reasoning and ratio of the decision of the Hon’ble Supreme Court, in the case of Secretary, Thirumurugan Cooperative Agricultural Credit Society Vs. M. Lalitha (Dead) Through LRs. & Ors. (Supra) still holds good, no fault can be found with the view taken by the State Commission.
Consequently, the Appeal fails and is dismissed accordingly.”
Recently, the larger Bench of the National Commission in a case titled as Aftab Singh Vs. Emaar MGF Land Limited & Anr., Consumer Case No. 701 of 2015, vide order dated 13.07.2017, has held that an Arbitration Clause in the Agreements between the complainants and the Builder cannot circumscribe the jurisdiction of a Consumer Fora, notwithstanding the amendments made to Section 8 of the Arbitration Act.
In view of the above, the objection raised in this regard, being devoid of merit is rejected.
“In the case of the purchase of the houses which a builder undertakes to construct for the buyer, the purchase can be said to be for a commercial purpose where it is shown, by producing evidence, that the buyer is engaged in the business of a buying and selling of houses and or plots as a trading activity, with a view to make profits by sale of such houses or plots. A person cannot be said to have purchased a house for a commercial purpose only by proving that he owns or had purchased more than one houses or plots. In a given case, separate houses may be purchased by a person for the individual use of his family members. A person owning a house in a city A may also purchase a house in city B for the purpose of staying in that house during short visits to that city. A person may buy two or three houses if the requirement of his family cannot be met in one house.
The principle of law, laid down, in the aforesaid cases, is fully applicable to the present case. The complainant, thus, falls within the definition of a ‘consumer’, as defined under Section 2(1)(d) of the Act. Such an objection, taken by the opposite party, in its written reply, therefore, being devoid of merit, is rejected.
It may be stated here, that the complainant has sought possession of the unit, in question, price whereof is Rs.46.25 lacs; interest @18% p.a. on the deposited amount; and @Rs.10/- per square feet of the super area, for the period of delay in delivery of possession; compensation to the tune of Rs.5 lacs, for mental agony, physical harassment, financial loss, deficiency in providing service and unfair trade practice; cost of litigation to the tune of Rs.50,000/- etc., aggregate value whereof fell above Rs.20 lacs but below Rs.1 crore. In no way, the aggregate value of the relief claimed, exceeds Rs.1 crore. Thus, this Commission has got pecuniary Jurisdiction, to entertain and decide the complaint. The objection taken by the opposite party, that this Commission lacks pecuniary Jurisdiction, being devoid of merit, must fail and the same stands rejected.
According to Section 17 of the Act, a consumer complaint can be filed by the complainant, before the State Consumer Disputes Redressal Commission, within the territorial Jurisdiction whereof, a part of cause of action arose to her. In the instant case, perusal of almost all the payment receipts reveals that the same have been issued by Regional Office of the opposite party at Chandigarh, as the same bore the first address as “SCO 143-144, Sector 8-C, Madhya Marg, Chandigarh”. Furthermore, offer of possession letter dated 19.01.2017 Annexure C-7, Statement of account dated 19.01.2017 (at page 54 of the file), second offer of possession letter dated 31.03.2017 Annexure C-13 alongwith statement of account attached therewith, also revealed that the same were issued by Chandigarh Office of the opposite party. Since, as per the documents, referred to above, a part of cause of action arose to the complainant, at Chandigarh, this Commission has got territorial Jurisdiction to entertain and decide the complaint. The objection taken by the opposite party, in its written version, in this regard, therefore, being devoid of merit, must fail, and the same stands rejected.
In view of above, it is held that the offer of possession, made by the opposite party letter dated 19.01.2017, followed by reminder dated 31.03.2017, is nothing, but mere a paper possession, which is not sustainable in the eyes of law. By making a misleading statement that possession of the constructed unit, with all basic amenities required, will be delivered within the maximum period of 30 months from the date of Allotment Letter/Agreement i.e. latest by 08.08.2014, and not abiding by the commitment made and at the same time issuing paper possession, the opposite party was not only deficient, in rendering service, but also indulged into unfair trade practice.
However, in connected consumer complaint bearing no. 318 of 2017, titled as Gorav Gupta and another Vs. M/s Omaxe Chandigarh Extension Developers Private Limited, the position is worst, as possession of the unit therein, has not even been offered to the complainants, till the date of arguments, in this complaint.
Under above circumstances, the complainants, in both the complaints, referred to above, are certainly entitled to delivery of physical possession of the unit, in question. At the same time, it is also held that the opposite party is also liable to pay compensation to the complainant(s), for causing mental agony, physical harassment, deficiency in providing service and adoption of unfair trade practice.
“We feel that the contention raised is liable to be rejected. In Clause 23(b) of the Agreement, it is stated that possession will be delivered within 24 months, from the date of allotment letter, with six months extension. It is further stated that when computing the said period all Saturdays, Sundays and Bank Holidays will be excluded. A similar issue came up for consideration before this Commission qua another project of the opposite parties, in the case of Dr.Divya Dahiya Vs. M/s Omaxe Chandigarh Extension Developers Private Limited and another, Consumer Complaint No.57 of 2016, decided on 15.07.2016, wherein, it was observed as under:-
“The first question, which falls for consideration, is, as to whether there was delay in offering possession of the plot, in question, and if so, to what extent. The allotment letter for independent floor in Row-Housing Project “Silver Birch” in the project of the Opposite Parties (Annexure C-4) was issued to the complainant on 30.08.2011. As per Clause 31(a) of the allotment letter, the Opposite Parties were to complete the development of the unit within 24 months or within an extended period of six months from the date of start of construction, subject to force majeure conditions. Since allotment letter is dated 30.08.2011, by computing 24 months plus 6 months period, the Opposite Parties were bound to deliver possession of the plot, in question, by 01.03.2014. The Opposite Parties have stated that period was to be computed by excluding Sundays, Bank Holidays, enforced Govt. holidays and the days of cessation of work at site in compliance of order of any Judicial/concerned State Legislative Body. Apparently, for seeking six months extension beyond 24 months or beyond six months extended period, the Opposite Parties owe an explanation, if the delay was on account of force majure conditions but nothing by way of cogent evidence to this effect has been placed on record. Thus, when no explanation for extension of six months period has been furnished, the Opposite Parties at the most could be allowed one out of the two benefits i.e. either six months extension beyond 24 months or period on account of Sundays/Holidays etc. This Commission in Consumer Complaint No.153 of 2015 titled ‘Mr. Madan Lal Taneja and another Vs. M/s Omaxe Chandigarh Extension Developers P. Ltd.’ decided on 03.11.2015, facts of which were almost identical, held that Opposite Parties were to hand over possession within 30 months from the date of start of construction. Thus, the possession of the unit, in question, was to be delivered by 01.03.2014.”
Similar view has also been reiterated by this Commission, in number of cases, thereafter, in respect of the same project. It was specifically held that when there is no explanation of getting extension of 6 months’ period to deliver possession beyond the stipulated date, the benefit of exclusion of Saturdays, Sundays, Bank Holidays etc. cannot be given. Out of the two benefits, only one can be made available to the opposite party. In this view of the matter, the contention raised by Counsel for the opposite party, being devoid of merit, must fail and the same stands rejected.
“What relief can be granted to a consumer, in case of delay, in offering possession, came up for consideration before the Hon’ble National Commission, in a case titled as Parsvnath Exotica Ghaziabad Resident's Association Vs. Parsvnath Buildwell Pvt. Ltd. & Anr., consumer complaint no.45/2015, decided by the Hon’ble National Commission, on 06.05.2016, wherein, it was argued by the project proponent that at the maximum, as provided in the Agreement, the consumer will be entitled to claim penalty for delayed compensation @Rs.5/- per square feet, per month. Noting that in case of delay in making payment, the project proponent was charging heavy penal interest, instead of penal amount, the interest on the deposited amount, for the period of delay was granted, by holding as under:-
“Though, the Agreement between the developer and the flat buyers provides for payment of compensation in case of delay @ Rs.5/- per square feet of the super area per month, such clauses have been found to be unfair trade practice and have been consistently rejected by this Commission in several decision, including Consumer Complaint No. 427 of 2014 Satish Kumar Pandey & Ors. Vs. Unitech Ltd. and connected matters decided on 08.6.2015. Therefore, the aforesaid clauses cannot be taken into consideration, while determining the compensation payable to the members of the complainant association for the aforesaid delay in completion of construction.”
Not only this, in another case, titled as Capt. Gurtaj Singh Sahni & anr. Vs Manager, Unitech Limited & anr., consumer complaint bearing no.603/2014, decided on 02.05.2016, the Hon'ble National Commission, directed the opposite party/builder to pay interest on the deposited amount, for the period of delay, till delivery of possession of the unit. Relevant contents of the said order reads thus:-
“8. If the compensation for the delay in construction is restricted to what is stipulated in the Buyers Agreement, there will be no pressure upon the builder to complete the construction since he will be more than happy to keep on paying paltry compensation of about 3% per annum of the capital investment, instead of arranging funds at much higher cost, to complete the construction.
9. xxxxxxxxxxxxx
10. For the reasons stated hereinabove, the complaints are disposed of with the following directions:
(1) xxxxxxxxxxxxxx
(2) The opposite party shall pay compensation in the form of simple interest @ 12% per annum from the expected date of possession till the date on which the possession is actually offered to the complainants after completing the construction in all respects and obtaining the requisite completion certificate.”
Thus, keeping in view the principle of law laid down by the Hon'ble National Commission, in the cases, referred to above, if interest @12% on the deposited amount for the period of delay, till delivery of possession of the unit, is awarded, that would meet the ends of justice.”
Not only as above, in H.P. Housing Board Vs. Janak Gupta [2009] INSC 627 (26 March 2009) (Civil Appeal No. 6346 of 2002), it was clearly held by the Hon’ble Supreme Court of India that in the cases of delay, in delivery of possession, award of interest @ 12% per annum, on the deposited amount, for the period of delay, would meet the ends of justice. Taking note of above said proposition of law, in the present case also, ends of justice would meet, if interest is granted for delayed period, to the complainant whereof 08.08.2014.
The same question, also came up before this Commission in a case titled as Ankur Gupta`s case (supra) , wherein also there was a delay in issuance of Allotment Letter/Agreement, by the opposite parties, after accepting booking amount. While dealing with above said contention, it was observed by this Commission, as under:-
“In the first instance, we will deal with an argument, raised by Counsel for the complainant that by offering Agreement for signing after many months of the allotment and receiving huge amount, the opposite parties have indulged into unfair trade practice. It is on record that the complainant purchased the built-up unit by moving an application on 14.03.2011. He paid an amount of Rs.8 lacs, towards booking amount. Thereafter, in terms of letter dated 01.08.2011 Annexure C-2 sent by the opposite parties, an amount of Rs.9,18,951.85Ps., towards price of the said unit, which also includes Rs.23,068.98Ps., towards service tax, was paid by him. After draw of lots, flat was allotted to him on 23.12.2011. It is positive case of the complainant that Agreement was offered for signing on 18.09.2012; he signed and gave it to the opposite parties, on the same day. However, thereafter, to gain time, it was wrongly shown to have been executed on 26.03.2013. To the contrary it is case of the opposite parties that Agreement was signed on the date mentioned above. To support above said contention, no evidence whatsoever, has been placed on record by the opposite parties. As such, it can safely be said that Agreement was got signed belatedly on 26.03.2013 i.e. after a period of about 15 months, from the date of allotment, in the month of March 2011. The said act would amount to unfair trade practice on the part of the opposite parties. It was also so said by this Commission in Sudesh Rani Vs. Omaxe Chandigarh Extension Developers Pvt. Ltd. and another, Consumer Case No.178 of 2016, decided on 16.08.2016.”
It was found as a matter of fact that by issuing Allotment Letter/Agreement after 15 months, from the date of accepting booking amount, the opposite parties have indulged into unfair trade practice. In the present case also, it is apparent on record that the final Allotment Letter/Agreement, in both the cases, was delayed by a year. By doing so, the opposite party has indulged into unfair trade practice. After acceptance of booking amount, it was required of the opposite party to issue allotment letter/agreement, within a reasonable time, say two or three months. It was also earlier so said by this Commission, in a case titled as Usha Kiran Ghangas Vs DLF Homes Panchkula Private Limited, Complaint Case No.93 of 2016, decided on 02.06.2016. Relevant portion of the said case, reads thus:-
“The opposite parties are also guilty of adoption of unfair trade practice. It is on record that the complainant booked the unit, in question, in the project aforesaid, on 16.02.2011. She was allotted unit, vide letter dated 23.02.2011, on which date, she had paid an amount of Rs.4 lacs. Buyer’s Agreement was not put for signing in a reasonable time, say two to three months. She continued to make payment and when Buyer’s Agreement was got signed, on 18.08.2011, she had already paid an amount of Rs.21,68,524/-. By not offering Buyer’s Agreement, for signing in a reasonable time, the opposite parties also committed unfair trade practice. The complainant is a widow. Her interest needs to be protected”.
As such, by not offering Allotment Letter/Agreement, for signing in a reasonable time, but after a delay of about a year of accepting booking amount, the opposite party committed unfair trade practice and is also deficient in providing service. In view of above default committed, we are of the considered opinion that compensation to the extent of Rs.50,000/-, if granted to the complainants, in both the complaints, shall meet the ends of justice.
In Consumer complaint bearing no.331 of 2017, titled as Tejpal Kaur Vs. Omaxe Chandigarh Extension Developers (P) Ltd., the opposite party is directed as under:-
Consumer complaint bearing no. 318 of 2017, titled as Gorav Gupta and another Vs. M/s Omaxe Chandigarh Extension Developers Private Limited. The opposite party/Company(s), addresses whereof have been mentioned in the head note of the main complaint is directed as under:-
Pronounced.
10-Aug-17
Sd/-
[JUSTICE JASBIR SINGH (RETD.)]
PRESIDENT
Sd/-
(DEV RAJ)
MEMBER
Sd/-
(PADMA PANDEY)
MEMBER
Rg.
STATE CONSUMER DISPUTES REDRESSAL COMMISSION,
U.T., CHANDIGARH
Complaint case No. | : | 318 of 2017 |
Date of Institution | : | 12.04.2017 |
Date of Decision | : | 10-Aug-17 |
Both R/o House No.2474, Sector 37-C, Chandigarh.
……Complainant
M/s Omaxe Chandigarh Extension Developers Private Limited, Regional Office SCO No.139-140, Sector 8-C, Madhya Marg, Chandigarh.
2nd Address:- Omaxe City, 111th Mile Stone Near Bad Ke Balaji Bus Stand, Jaipur-Ajmer Express Way Jaipur, 302026, through its Managing Director.
3rd Address:- M/s Omaxe Chandigarh 10th LSC, Kalkaji, New Delhi 110019, through its Managing Director.
.... Opposite Party
Complaint under Section 17 of the Consumer Protection Act, 1986.
BEFORE: JUSTICE JASBIR SINGH (RETD.), PRESIDENT.
MR. DEV RAJ, MEMBER.
MRS. PADMA PANDEY, MEMBER
Argued by: Sh.Raj Kumar Sahota, Advocate for the complainants.
Sh.Munish Gupta, Advocate for the opposite party.
PER JUSTICE JASBIR SINGH (RETD.), PRESIDENT
Vide our separate detailed order of the even date, recorded in consumer complaint bearing no.331 of 2017, titled as Tejpal Kaur Vs. Omaxe Chandigarh Extension Developers (P) Ltd., this complaint has been partly accepted with cost.
Sd/- Sd/- Sd/-
(DEV RAJ) MEMBER | (JUSTICE JASBIR SINGH (RETD.)) PRESIDENT | (PADMA PANDEY) MEMBER |
Rg.Top of Form
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.