Smt. Sanjila Bansal filed a consumer case on 17 Oct 2018 against M/s Omaxe Chandigarh Extension Developers Private Limited in the StateCommission Consumer Court. The case no is CC/787/2017 and the judgment uploaded on 30 Oct 2018.
STATE CONSUMER DISPUTES REDRESSAL COMMISSION,
U.T., CHANDIGARH
Complaint case No. | : | 787 of 2017 |
Date of Institution | : | 09.11.2017 |
Date of Decision | : | 17.10.2018 |
Smt.Sanjila Bansal, W/o Dr.Yogender Bansal, R/o # 1154, Sector 24-B, Chandigarh.
……Complainant
.... Opposite Parties
Argued by: Sh.Savinder Singh Gill, Advocate for the complainant.
Sh.Munish Gupta, Advocate for the opposite parties.
=====================================================
Complaint case No. | : | 69 of 2018 |
Date of Institution | : | 13.02.2018 |
Date of Decision | : | 17.10.2018 |
Lakhbir Singh s/o Sukhdev Singh, resident of Village Dulchi Ke, District Ferozepur, Punjab.
……Complainant
11nd Address:- M/s Omaxe Chandigarh Extension Developers Private Limited, SCO 143-144, Sector 8-C, Chandigarh, through its Managing Director/Directors/Chief Executive Officer.
IIIrd Address:- M/s Omaxe Chandigarh Extension, Site Address: In the revenue Estate of Villages Kansala, Parol, Kartarpur, Rani Majra Takipur Boothgarh, Dhode Majra Rasoolpurand Bhagat Majra in Mullanpur LPA (GMADA) District SAS Nagar (Mullanpur) Punjab, through its Managing Director/Directors/Chief Executive Officer.
.... Opposite Parties
Argued by: Sh.Sandeep Bhardwaj, Advocate for the complainant.
Sh.Munish Gupta, Advocate for the opposite parties.
=====================================================
Complaint case No. | : | 138 of 2018 |
Date of Institution | : | 04.04.2018 |
Date of Decision | : | 17.10.2018 |
Sunil Bali S/o Sh.Madan Lal Bali, R/o 2 Power Station, P.O. Khairi, Tehsil Dalhousie, Chamba, Himachal Pradesh 176325.
……Complainant
.... Opposite Parties
Argued by: Sh.Savinder Singh Gill, Advocate for the complainant.
Sh.Munish Gupta, Advocate for the opposite parties.
=====================================================
Complaints under Section 17 of the Consumer Protection Act, 1986.
BEFORE: JUSTICE JASBIR SINGH (RETD.), PRESIDENT.
MRS. PADMA PANDEY, MEMBER
SH. RAJESH K. ARYA, MEMBER
PER PADMA PANDEY, MEMBER
By this order, we propose to dispose of aforesaid three consumer complaints, filed by the respective complainants. Arguments in the said complaints were heard in common, on 05.10.2018. In all the complaints, referred to above, issues involved, except minor variations, here and there, of law and facts are the same. Consumer complaint bearing no.787 of 2017 has been filed by the complainant seeking directions to the opposite parties to deliver actual physical possession of the unit, in dispute; to pay compensation for the period of delay in delivering possession thereof, alongwith interest, compensation etc. Whereas, in consumer complaints bearing nos.69 of 2018 and 138 of 2018, the complainant(s) have sought directions to the opposite parties, to refund the entire amount paid by them, on account of delay in delivering possession of their respective units/plot(s) alongwith interest, compensation etc. As such, during arguments, it was agreed by the contesting parties, that all the three complaints can be disposed of, by passing a consolidated order.
It may be stated here that, such an issue, as to whether, in the face of existence of provision to settle disputes between the parties through Arbitration, in terms of provisions of Section 8 (amended) of 1996 Act, this Commission has jurisdiction to entertain the consumer complaint or not, has already been dealt with, by this Commission, in a case titled as ‘Sarbjit Singh Vs. Puma Realtors Private Limited’, IV (2016) CPJ 126, while relying upon ratio of judgments of the Hon’ble Supreme Court, titled as Fair Air Engg. Pvt. Ltd. & another Vs. N. K. Modi (1996) 6 SCC 385, C.C.I Chambers Coop. Housing Society Ltd. Vs Development Credit Bank Ltd. (2003) 7 SCC 233, Rosedale Developers Private Limited Vs. Aghore Bhattacharya and others, (Civil Appeal No.20923 of 2013), Secretary, Thirumurugan Cooperative Agricultural Credit Society v. M. Lalitha (2004) 1 SCC 305 and United India Insurance Co. Ltd. Vs. M/s Pushpalaya Printers, I (2004) CPJ 22 (SC), and LIC of India and another Vs. Hira Lal, IV (2011) CPJ 4 (SC), and held that even in the face of existence of arbitration clause in an Agreement/Allotment Letter, to settle disputes between the parties through Arbitration, in terms of provisions of Section 8 (amended) of 1996 Act, this Commission has jurisdiction to entertain the consumer complaint. Recently, the larger Bench of the National Commission in a case titled as Aftab Singh Vs. Emaar MGF Land Limited & Anr., Consumer Case No. 701 of 2015, vide order dated 13.07.2017, has held that an Arbitration Clause in the Agreements between the complainant and the Builder cannot circumscribe the jurisdiction of a Consumer Fora, notwithstanding the amendments made to Section 8 of the Arbitration Act. Feeling aggrieved against the said findings, the builder filed Civil Appeal bearing No.23512-23513 of 2017 before the Hon’ble Supreme Court of India, which was dismissed vide order dated 13.02.2018.
In this view of the matter, objection raised by the opposite parties, in this regard, stands rejected.
“It is evident from a bare perusal of Sections 21, 17 and 11 of the Consumer Protection Act that it’s the value of the goods or services and the compensation, if any, claimed which determines the pecuniary jurisdiction of the Consumer Forum. The Act does not envisage determination of the pecuniary jurisdiction based upon the cost of removing the deficiencies in the goods purchased or the services to be rendered to the consumer. Therefore, the cost of removing the defects or deficiencies in the goods or the services would have no bearing on the determination of the pecuniary jurisdiction. If the aggregate of the value of the goods purchased or the services hired or availed of by a consumer, when added to the compensation, if any, claimed in the complaint by him, exceeds Rs. 1.00 crore, it is this Commission alone which would have the pecuniary jurisdiction to entertain the complaint. For instance if a person purchases a machine for more than Rs.1.00 crore, a manufacturing defect is found in the machine and the cost of removing the said defect is Rs.10.00 lacs, it is the aggregate of the sale consideration paid by the consumer for the machine and compensation, if any, claimed in the complaint which would determine the pecuniary jurisdiction of the Consumer Forum. Similarly, if for instance, a house is sold for more than Rs.1.00 crore, certain defects are found in the house, and the cost of removing those defects is Rs.5.00 lacs, the complaint would have to be filed before this Commission, the value of the services itself being more than Rs.1.00 crore. ”
In the present case, total value of the unit, in question; plus compensation claimed by way of interest @18% p.a. on the deposited amount of Rs.40,28,878/- for the period of delay; interest on Rs.8,29,000/- from the respective dates of deposits till 12.11.2014 and also Rs.7 lacs, claimed as compensation for mental agony; physical harassment etc., if taken into consideration, it exceeds Rs.20 lacs and fell below Rs.1 crore. Thus, this Commission has got pecuniary Jurisdiction, to entertain and decide this complaint. The objection taken by the opposite parties, that this Commission lacks pecuniary Jurisdiction, being devoid of merit, must fail and the same stands rejected.
According to Section 17 of the Act, a consumer complaint can be filed, by the complainant, before the State Consumer Disputes Redressal Commission, within the territorial Jurisdiction whereof, a part of cause of action arose to her. In the instant case, it is evident that provisional allotment letter dated 23.11.2012 Annexure C-1 in respect of the unit, in question, was issued by Chandigarh Office of the opposite parties i.e. SCO No.139-140, Sector 8-C, Chandigarh. Not only as above, even the Allotment Letter/Agreement dated 12.11.2014 Annexure C-2 was executed between the parties at Chandigarh, as the same bores round stamp of the Chandigarh office of the opposite parties, on each and every page. The said address of Chandigarh Office of the opposite parties, is found mentioned on almost all the letters/documents, placed on record by the complainant. Since, as per the documents, referred to above, a part of cause of action arose to the complainant, at Chandigarh, this Commission has got territorial Jurisdiction to entertain and decide this complaint. Objection taken by the opposite parties, in their written version, in this regard, therefore, being devoid of merit, must fail, and the same stands rejected.
“In the case of the purchase of the houses which a builder undertakes to construct for the buyer, the purchase can be said to be for a commercial purpose where it is shown, by producing evidence, that the buyer is engaged in the business of a buying and selling of houses and or plots as a trading activity, with a view to make profits by sale of such houses or plots. A person cannot be said to have purchased a house for a commercial purpose only by proving that he owns or had purchased more than one houses or plots. In a given case, separate houses may be purchased by a person for the individual use of his family members. A person owning a house in a city A may also purchase a house in city B for the purpose of staying in that house during short visits to that city. A person may buy two or three houses if the requirement of his family cannot be met in one house. Therefore, it would not be correct to say that in every case where a person owns more than one house, the acquisition of the house is for a commercial purpose. In fact, this was also the view taken by this Commission in Rajesh Malhotra & Ors. Vs. Acron Developers Pvt. Ltd. & Ors. First Appeal No. 1287 of 2014 decided on 05.11.2015.”
The complainant, thus, falls within the definition of a ‘consumer’, as defined under Section 2(1)(d) of the Act. Such an objection, taken by the opposite parties, therefore, being devoid of merit, is rejected.
“The opposite parties are also guilty of adoption of unfair trade practice. It is on record that the complainant booked the unit, in question, in the project aforesaid, on 16.02.2011. She was allotted unit, vide letter dated 23.02.2011, on which date, she had paid an amount of Rs.4 lacs. Buyer’s Agreement was not put for signing in a reasonable time, say two to three months. She continued to make payment and when Buyer’s Agreement was got signed, on 18.08.2011, she had already paid an amount of Rs.21,68,524/-. By not offering Buyer’s Agreement, for signing in a reasonable time, the opposite parties also committed unfair trade practice. The complainant is a widow. Her interest needs to be protected”.
As such, by not offering Allotment Letter/Agreement, for signing in a reasonable time, but after a delay of about three years of accepting amount of Rs.12,82,820/-, the opposite parties committed unfair trade practice and are also deficient in providing service. In view of above default committed, we are of the considered opinion that compensation to the extent of Rs.1,00,000/-, if granted to the complainant, in this complaint, shall meet the ends of justice.
First coming to the question, as to whether, while computing the above said period of delay in handing over possession of the unit, Sundays, Saturdays, Bank Holidays, etc. are to be taken into account or not, it may be stated here that a similar question came up for consideration before this Commission in Ankur Gupta Vs. Omaxe Chandigarh Extension Developers Pvt. Ltd. and another, Consumer Case No.309 of 2016 decided on 22.11.2016, and when dealing this issue, it was observed by this Commission, as under:-
“We feel that the contention raised is liable to be rejected. In Clause 23(b) of the Agreement, it is stated that possession will be delivered within 24 months, from the date of allotment letter, with six months extension. It is further stated that when computing the said period all Saturdays, Sundays and Bank Holidays will be excluded. A similar issue came up for consideration before this Commission qua another project of the opposite parties, in the case of Dr.Divya Dahiya Vs. M/s Omaxe Chandigarh Extension Developers Private Limited and another, Consumer Complaint No.57 of 2016, decided on 15.07.2016, wherein, it was observed as under:-
“The first question, which falls for consideration, is, as to whether there was delay in offering possession of the plot, in question, and if so, to what extent. The allotment letter for independent floor in Row-Housing Project “Silver Birch” in the project of the Opposite Parties (Annexure C-4) was issued to the complainant on 30.08.2011. As per Clause 31(a) of the allotment letter, the Opposite Parties were to complete the development of the unit within 24 months or within an extended period of six months from the date of start of construction, subject to force majeure conditions. Since allotment letter is dated 30.08.2011, by computing 24 months plus 6 months period, the Opposite Parties were bound to deliver possession of the plot, in question, by 01.03.2014. The Opposite Parties have stated that period was to be computed by excluding Sundays, Bank Holidays, enforced Govt. holidays and the days of cessation of work at site in compliance of order of any Judicial/concerned State Legislative Body. Apparently, for seeking six months extension beyond 24 months or beyond six months extended period, the Opposite Parties owe an explanation, if the delay was on account of force majure conditions but nothing by way of cogent evidence to this effect has been placed on record. Thus, when no explanation for extension of six months period has been furnished, the Opposite Parties at the most could be allowed one out of the two benefits i.e. either six months extension beyond 24 months or period on account of Sundays/Holidays etc. This Commission in Consumer Complaint No.153 of 2015 titled ‘Mr. Madan Lal Taneja and another Vs. M/s Omaxe Chandigarh Extension Developers P. Ltd.’ decided on 03.11.2015, facts of which were almost identical, held that Opposite Parties were to hand over possession within 30 months from the date of start of construction. Thus, the possession of the unit, in question, was to be delivered by 01.03.2014.”
Similar view has also been reiterated by this Commission, in number of cases, thereafter, in respect of the same project. It was specifically held that when there is no explanation of getting extension of 6 months’ period to deliver possession beyond the stipulated date, the benefit of exclusion of Saturdays, Sundays, Bank Holidays etc. cannot be given. Out of the two benefits, only one can be made available to the opposite parties. In this view of the matter, contention raised by Counsel for the opposite parties, being devoid of merit, must fail and the same stands rejected.
In the present case, it has been noticed by this Commission that after receiving booking amount against the agreed consideration as far as back in the year 2011, the opposite parties deliberately failed to take any steps for starting the construction of the units till 2014. They kept on receiving amount from the complainant and, as stated above, allotment letter/agreement was sent for signatures of the complainant after about three years, just with a view to buy time for possession and for this act, they have been penalized, in the manner, referred to above. The opposite parties have not shown any cogent reason, which prevented them to complete construction of the unit and deliver possession thereof within the stipulated period.
What relief can be granted to a consumer, in case of delay, in offering possession of a residential unit purchased, in the absence of any force majeure circumstances having been faced by the builder, also came up for consideration before this Commission in Ankur Gupta`s case (supra), wherein dealing with similar issue, it was observed as under:-
“What relief can be granted to a consumer, in case of delay, in offering possession, came up for consideration before the Hon’ble National Commission, in a case titled as Parsvnath Exotica Ghaziabad Resident's Association Vs. Parsvnath Buildwell Pvt. Ltd. & Anr., consumer complaint no.45/2015, decided by the Hon’ble National Commission, on 06.05.2016, wherein, it was argued by the project proponent that at the maximum, as provided in the Agreement, the consumer will be entitled to claim penalty for delayed compensation @Rs.5/- per square feet, per month. Noting that in case of delay in making payment, the project proponent was charging heavy penal interest, instead of penal amount, the interest on the deposited amount, for the period of delay was granted, by holding as under:-
“Though, the Agreement between the developer and the flat buyers provides for payment of compensation in case of delay @ Rs.5/- per square feet of the super area per month, such clauses have been found to be unfair trade practice and have been consistently rejected by this Commission in several decision, including Consumer Complaint No. 427 of 2014 Satish Kumar Pandey & Ors. Vs. Unitech Ltd. and connected matters decided on 08.6.2015. Therefore, the aforesaid clauses cannot be taken into consideration, while determining the compensation payable to the members of the complainant association for the aforesaid delay in completion of construction.”
Not only this, in another case, titled as Capt. Gurtaj Singh Sahni & anr. Vs Manager, Unitech Limited & anr., consumer complaint bearing no.603/2014, decided on 02.05.2016, the Hon'ble National Commission, directed the opposite party/builder to pay interest on the deposited amount, for the period of delay, till delivery of possession of the unit. Relevant contents of the said order reads thus:-
“8. If the compensation for the delay in construction is restricted to what is stipulated in the Buyers Agreement, there will be no pressure upon the builder to complete the construction since he will be more than happy to keep on paying paltry compensation of about 3% per annum of the capital investment, instead of arranging funds at much higher cost, to complete the construction.
9. xxxxxxxxxxxxx
10. For the reasons stated hereinabove, the complaints are disposed of with the following directions:
(1) xxxxxxxxxxxxxx
(2) The opposite party shall pay compensation in the form of simple interest @ 12% per annum from the expected date of possession till the date on which the possession is actually offered to the complainants after completing the construction in all respects and obtaining the requisite completion certificate.”
Thus, keeping in view the principle of law laid down by the Hon'ble National Commission, in the cases, referred to above, if interest @12% on the deposited amount for the period of delay, till delivery of possession of the unit, is awarded, that would meet the ends of justice.”
Not only as above, in H.P. Housing Board Vs. Janak Gupta [2009] INSC 627 (26 March 2009) (Civil Appeal No. 6346 of 2002), it was clearly held by the Hon’ble Supreme Court of India that in the cases of delay, in delivery of possession, award of interest @ 12% per annum, on the deposited amount, for the period of delay, would meet the ends of justice. Taking note of above said proposition of law, in the present case also, ends of justice would meet, if interest is granted for delayed period, to the complainant whereof 11.08.2016 till 08.04.2017 (one month after the date of offer of possession i.e. 09.03.2017).
Besides as above, the opposite parties are also liable to pay compensation to the complainant, for providing her deficient service; guilty of adoption of unfair trade practice and causing her mental agony & physical harassment.
“From the material on record, it is evident that the OP-2 is the Chairman of the Company whereas the OP-3 is the Chief Executive Officer-cum-M.D. of the said company. Evidently, these two persons are holding such important positions in the Company, where they are directly involved with the decision-making process in the company. By virtue of their office, they can directly influence any decision regarding relief to be granted to the complainant, as asked for in the consumer complaint. It is held, therefore, that the State Commission has rightly dismissed the interim application, rejecting the plea of the appellants to delete the name of OP-2 & OP-3 from the array of parties. The impugned order passed by the State Commission is, therefore, upheld and the appeal is ordered to be dismissed with no order as to costs.”
In view of above, objection raised by Counsel for the opposite parties stands rejected.
In connected consumer complaint bearing no.138 of 2018, possession of the flat therein was offered belatedly, which is a material violation on the part of the opposite parties, as such, in our considered opinion, the complainant therein is not obliged to take the same. Our view is supported by the law laid down by the National Commission, in the case titled as Aashish Oberai Vs. Emaar MGF Land Limited, Consumer Case No. 70 of 2015, decided on 14 Sep 2016, wherein, under similar circumstances, while negating the plea taken by the builder, it was held as under:-
“I am in agreement with the learned senior counsel for the complainants that considering the default on the part of opposite parties no.1 and 2 in performing its contractual obligation, the complainants cannot be compelled to accept the offer of possession at this belated stage and therefore, is entitled to refund the entire amount paid by him along with reasonable compensation, in the form of interest.”
Not only as above, in a case titled as Brig Ajay Raina (Retd.) and another Vs. M/s Unitech Limited, Consumer Complaint No.59 of 2016, decided on 24.05.2016, wherein possession was offered after a long delay, this Commission, while relying upon the judgments rendered by the Hon`ble National Commission, ordered refund to the complainants, while holding as under:-
“Further, even if, it is assumed for the sake of arguments, that offer of possession, was made to the complainants, in July 2015 i.e. after a delay of about three years, from the stipulated date, even then, it is not obligatory upon the complainants to accept the same.
Furthermore, in another case titled as M/s. Emaar MGF Land Ltd. & Anr. Vs. Dr.Manuj Chhabra, First Appeal No.1028 of 2015, decided on 19.04.2016, the Hon’ble National Commission, under similar circumstances, held as under:-
“I am of the prima facie view that even if the said offer was genuine, yet, the complainants was not obliged to accept such an offer, made after a lapse of more than two years of committed date of delivery”.
The above view taken by the National Commission, has been reiterated by it, recently in the case titled as Sujay Bharatiya & Anr. Vs. Unitech Reliable Projects Pvt. Ltd., Consumer Case No. 1814 of 2017 decided on 05.07.2018. Relevant part of the said order reads thus: -
“This Commission in Emaar MGF Land Ltd. & Anr. V. Amit Puri (First Appeal No.250 of 2014), decided on 30.03.2015, has held that if the Developer fails to deliver possession of the allotted plot/flat within the stipulated time, the allottee is under no obligation to accept an alternative plot. At the cost of repetition, we may reiterate that in the event of Developer failing to deliver possession of the property within the stipulated period, for any reason, save and except a force majeure condition, agreed to between the contracting parties, an allottee cannot be compelled to accept an alternate site/plot and he would be within his rights to seek refund of the amount deposited with the Developer against allotment”.
In view of above, the complainants in connected consumer complaints, referred to above, are held entitled to refund of their amount deposited, alongwith interest, compensation and litigation expenses.
First coming to the objection taken by the opposite parties in consumer complaint bearing no.138 of 2018 that time is not be considered as essence of the contract, it may be stated here that, once a plea has been taken by the opposite parties that the complaint filed is beyond limitation, as such, in the same breath, taking another plea to say that time is not to be considered as essence of the contract, has no legs to stand and, is accordingly rejected. The plea raised to this effect also needs rejection in view of principle of law laid down by the National Commission in Consumer Complaint No. 315 of 2015 Pradeep Narula Vs. M/s. Granite Gate Properties Pvt. Ltd. & Anr. decided on 23.8.2016, wherein, it was held as under:
“10…….………Moreover, the decision in Chand Rani (supra) was rendered in the context of a suit for specific performance of an agreement to sell the first floor of an existing house, whereas the decision in the Hind Construction (supra) was rendered in the context of a Government contract. In neither of these cases, the Hon’ble Supreme Court was called upon to decide as to whether an unjustified and explained delay on the part of the builder/service provider in construction of a residential flat booked by a person seeking to have a shelter over his head amount to a deficiency in the service rendered by him to the consumer, or not. The primary purpose of a consumer in booking a residential flat which the builder is to construct for him, is to start living in that house on or about the date committed to him by the builder for delivering possession of the flat booked by him. If the builder does not deliver upon his contractual obligation and at the same time, is unable to show that the delay in completion of the flat and offering its possession to the consumer was on account on circumstances beyond his control, this would constitute deficiency on the part of the builder/service provider in rendering services to the consumer. If I accept the contention that the builder can indefinitely postpone and delay the construction of the flat and the flat buyer has no option but to wait till the builder decides to complete the construction and offer possession to the buyer, that would be nothing but a travesty of justice and result in a situation where the flat buyer is left at the mercy of the builder, without recourse to an appropriate legal remedy. Such an interpretation, if taken, is bound to defeat the very objective behind the enactment of the Consumer Protection Act, as far as housing construction is concerned. Therefore, I am unable to accept the contention advanced by the learned counsel for the opposite party. In my view, wherever the builder commits a particular date or time frame for completion of the construction and offering possession to the buyer, he must necessarily honour the commitment made by him, though a minor delay may not constitute deficiency in the service rendered by him to the buyer. Of course, if the builder is able to how that the delay in completion of the construction and offering possession to the buyer is attributable wholly to the circumstances beyond his control, that may not be a case of deficiency in the services rendered to the consumer”.
Now coming to another objection raised by the opposite parties that since it was mentioned in the Agreement that the Company shall only try to complete construction of the unit and development of the project within maximum period of 21 months, from the date of signing of the agreement, as such, no definite assurance was given, therefore, time was not to be considered as the essence of contract, is also devoid of merit. It may be stated here that it was clearly mentioned in Clause 7 (a) of the Agreement that the Company shall complete development of the project and construction of the unit, within a maximum period of 21 months, from the date of execution of the agreement, subject to force majeure circumstances or reasons beyond the control of the opposite parties. In the instant case, the opposite parties did not raise any force majeure circumstances, if any, encountered by them. In the absence of any force majeure circumstances having been faced by the opposite parties or any other valid and legal reason beyond their control, the stand taken by them, in this regard, for condonation of delay in delivery of possession of the unit, to the complainant, cannot be taken into consideration. Thus, under these circumstances, since as per Clause 7 (a) of the Agreement, the opposite parties were bound to deliver possession of the unit, within a maximum period of 21 months, from the date of signing of the agreement, as such, time was, unequivocally made the essence of contract.
At the same time, the opposite parties, also cannot evade their liability, merely by saying that since the word(s) “shall endeavor/try/propose etc.” was mentioned in the Agreement, for delivery of possession of the unit, as such, time is not to be considered as essence of the contract. The act of non-mentioning of exact date in the Agreement is violation of CHAPTER II Regulation of Promotion of Construction, Sale, Transfer and Management of Apartments, Plots and Properties, Condition no. 3(2) (g) of the Punjab Apartment and Property Regulation Act, 1995 (PAPRA), which says that the project proponent is duty bound to specify, in writing, the date by which possession of the unit is to be handed over and it shall hand over such possession accordingly. Relevant contents of condition no.3(2) (g) of PAPRA are reproduced below:-
“(g) specify, in writing, the date by which possession of the plot or apartment is to be handed over and he shall hand over such possession accordingly”;
Furthermore, non-mentioning of exact date of delivery of possession of the unit(s) in the Buyer’s Agreement/allotment letter, is an unfair trade practice on the part of the Builder. The builder is bound to mention the exact/specific date of delivery of possession of the plots/unit(s) to the allottees/purchasers thereof. It was so said by the Hon`ble National Commission, in Rajeev Nohwar & Anr. Vs. Sahajanand Hi Tech Construction Pvt Ltd, 2016 (2) CPR 769. Relevant portion of the said case reads thus:-
In view of above, plea of the opposite parties in this regard also stands rejected.
Since, it has been held above that there was delay on the part of the opposite parties, in offering possession of the unit, in question, as such, the plea taken by them that forfeiture clause will be applicable being devoid of merit stands rejected. Had possession of the unit, in question, been offered/delivered by the stipulated date and had the complainant refused to take the same, on account of some personal reasons, only in those circumstances, order with regard to forfeiture of amount out of the deposited amount, would have been passed, as per prevailing law.
As far as objection taken to the effect that the complainant has submitted affidavit Annexure OP-2 to the effect that he shall not claim any compensation for the period of delay in offer of possession, it may be stated here that in this case, the complainant is seeking refund of the amount paid and not possession of the unit, on account of delay in offering possession of the unit. As such, contents of the affidavit, is of no help to the opposite parties, as far as the case of the complainant, seeking refund of amount paid, on account of delay in the matter, is concerned. Objection taken in this regard, stands rejected.
In this case, it is evident from the record that, in the first instance, the complainant had purchased a plot measuring 300 square yards, in the project of the opposite parties, in October 2011, for which he had already paid an amount of Rs.59,38,800/-. As per agreement dated 27.07.2012 executed in respect of the said plot, the opposite parties were liable to deliver possession of the said plot by 26.07.2014. However, it appears that since the opposite parties were not in a position to deliver possession of the said plot, the complainant was relocated to a plot measuring 200 square yards, in the said project, for which affidavit cum undertaking dated 21.04.2014 was received from him, by the opposite parties. The complainant accepted relocation with a hope that he will get possession of the relocated plot shortly but to of no avail. Therefore, even if the contention of the opposite parties to the effect that possession of the plot, in question, was offered to the complainant vide letter dated 10.02.2017 is accepted as correct, yet, the complainant has denied of receiving such letter, even then we are of the considered opinion, that there was a material violation on their part. The complainant has started pouring money out of his pocket for a plot, from October 2011, yet, he was offered possession and that too of the relocated plot, only in February 2017. Under these circumstances, we are of the considered opinion that even if the plea taken by the opposite parties that possession of relocated plot was offered to the complainant in February 2017 is accepted as correct, even then, the complainant was not obliged to take over the same, in view of principle of law laid down by the National Commission, as referred to above.
Consumer Complaint no.787 of 2017. The opposite parties, jointly and severally are directed as under:-
Consumer Complaint no.69 of 2018. The opposite parties, jointly and severally are directed as under:-
Consumer Complaint no.138 of 2018. The opposite parties, jointly and severally are directed as under:-
Pronounced.
17.10.2018
Sd/-
(JUSTICE JASBIR SINGH (RETD.)
PRESIDENT.
Sd/-
(PADMA PANDEY)
MEMBER
Sd/-
(RAJESH K. ARYA)
MEMBER
Rg.
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.