So it is clear that The Consumer Protection Act is a special Act and even if there is a clause of arbitrator in the agreement, it will not oust the jurisdiction of the consumer courts. So this court has jurisdiction to try the case.
The opposite party no.1 has stated in affidavit that complainant is not a consumer. The complainant, beside the flat, also booked to other flats in the opposite parties project. The complainant is having more than one booking in the project of the respondent company hence he is not a consumer. The purpose of purchasing the flats from the respondentcannot be considered as a residential but for commercial gain through investment. The present complaint is also time barred. The cause of action, if any, has arise in on 28.07.2007 when alleged booking of flat was done by the complainant and alleged consideration was tendered to opposite party. The complaint is filed in the year 2015which is time barred.
There is nothing on record to show that the flat purchaser by the complainant was only for commercial use. No evidence has been given by the opposite parties which show that the flats were meant for resale orfor any commercial activities. If any person possesses more than one flat, it does not automatically means that this only for the purpose of investment and investment only. The complainant sent a legal notice to the respondent no 2 on 08.06.2015 asking it to disclose its authority for demanding money in respect of the aforesaid flat. So as far as cause of action is concerned, it also arises on 08.06.2015. Before it, the complainant has also sent a notice on 4 May 2015, so that was also a date of cause of action. So this complaint case is not time barred.
The opposite party also pleaded that the matter should have been referred to the arbitrator because there is a arbitration clause in the agreement. But this matter has already been discussed in detail that in spite of the arbitration clause, one may file a case before the consumer fora. The opposite party also stated that the complainant is the defaulter in this case and various reminder notices were sent to the complainant and it is stated that after making initial payment the complainant has failed to make further payment hence the complaint is liable to be dismissed. The opposite party has stated that the complainant deposited the money with the respondent no 1 company for availing the flat in project developed by the respondent company on the land allotted in the name of respondent no 2 i.e, ANS Apartment P Ltd situated at Greater Noida, Uttar Pradesh named as “The Alstonia Apartments” and the said project is duly approved project of the company and construction at site is going on and thereafter delay in completion of project on account of reasons well explained in present reply thus in present case on account of overall slump in real estate industry especially on account of slow recovery from investors in the said project and on account of force majeure reasons stated in the present reply, there is delay in completing the construction of project. The opposite party also stated that in the present case the delay in completion of the construction has been caused due to undue delay of tendering the payment by the various allottees including the complainant herein in the project and in view of such problem the respondents company wrote constantly letters to various allottees to make payment and further has gone even after the extent of making public notice in the newspapers by calling upon the allottees in the project to deposit their payment on time and to extend their cooperation to complete the project on time. So both the opposite parties have put the same version in their affidavits filed. They could not file their written statement in time and that was not taken on record. It shows that when the opposite parties failed to submit their written statement before the court of law, how can they say that the complainant was defaulter in the case?
In the present case flat no D-801 area 1725 square ft has been allotted to the complainant on 28.07.2007 and an agreement has been executed between the parties stating that that the complaint shall complete construction of the apartment and the residential complex and deliver the possession of the apartment to the complainant by December 2009. The component deposited Rs.1,158,500/– against Rs.441,168/– (11% of the basic sale price as required in the agreement). The total cost of the flat was Rs.4,421,000/–. It was duty of the opposite party no.1, who entered into an agreement with the complainant, to deliver the possession of the flat as promised by him. In the agreement three months grace period will be given to the opposite parties after the expected date of delivery of possession. So we have taken, after giving three months grace period, 01.04.2009 and the final date for delivery of possession. The date of the notice as published in the newspaper and copy of which has been filed by the opposite party shows July 14. This date is much beyond the date on which possession was to be delivered. So the opposite parties became defaulter when they did not deliver possession on or before 01.04.2009. They could not show the force majeure. Payment of instalments by the allottees is not a force majeure issue because the opposite parties have power to cancel the allotment in case of non-payment of instalments. So there was no reason which can genuinely be said as true for delay in the construction of the flats.
Whether the opposite parties have received the completion certificate and occupancy certificate? Both the certificates are necessary to obtain before offering delivery opposition to the allottee. It is importance should be known by the following legal article.
COMPLETION / OCCUPANCY CERTIFICATE
When buying a home, it is vital to obtain documents, such as the Occupancy Certificate (OC) and Completion Certificate (CC). These are essential documents that allow you to mortgage or sell your home. Hence, homebuyers are advised to take possession of their flat or property only after these documents have been issued.
According to Vikas Bhasin, CMD, Saya Group, “Completion Certificate and Occupancy Certificate are some of the most important documents for a home buyer. Civic authorities can evict the occupants in case of non-availability of the necessary approvals. Before investing in a property, people must be doubly assured that all the certificates and approvals are in place.”
Let us dive a little deeper into the details of these documents and their importance before you make a move to buy your dream home.
Owning a home is the culmination of years of savings, research, and paperwork. After patiently waiting for the construction to be complete, you finally register the property and take possession of your flat. But what if your dream home is declared unauthorised, and you are evicted by the authorities? This is not as far-fetched as it sounds. This nightmare could turn into reality without a crucial link in the property sale process - the Occupancy Certificate (OC).
The majority of apartments in different Indian cities have been occupied by owners without any occupancy certificate. This oversight can turn into a costly mistake, jeopardising the legal status of your dream home. The importance of the occupancy certificate cannot be overstated as it seals the legal status of your property and protects your ownership rights.
Decoding legal documents
To understand the importance of an occupancy certificate and other legal documents, let’s decode the legal jargon and understand their meaning in simple terms. Here’s a ready reckoner of the most important legal documents related to your property:
Occupancy Certificate
An OC certifies that the construction of the building has complied with the approved plans. It is issued by local municipal authorities or the building proposal department once the building has been completed and is ready to be occupied. Simply put, without an OC, your building has not been awarded a ‘pass certificate’.
Completion Certificate
A Completion Certificate (CC) is issued only after the construction meets other building standards like distance from the road, the height of the building, and rainwater harvesting system. A CC alone cannot legalise occupation; the OC is a must.
Commencement Certificate
If you are buying an under construction property, make sure you check the Commencement Certificate before signing the agreement. Many builders do not wait for a Commencement Certificate. This is illegal and can create serious problems in obtaining an OC at a subsequent stage.
Why is it unsafe to buy a flat without OC?
In the absence of a valid OC, the local municipal body can initiate serious action against flat owners. In 2014, residents of a well-known building complex in Mumbai’s upscale Worli area were hit with a bolt from the blue after their complex was declared unauthorised. At the time of possession, buyers overlooked the issuance of an OC from the builder. It was only after that they were forced to evacuate their flats that the writing on the wall became clear to them.
This is just one instance, and if buyers are not careful about getting the OC, they may face the following repercussions:
• In the absence of a valid OC, your building can be demolished as it can be classified as an unauthorised structure.
• The OC is crucial while applying for a home loan or loan to purchase a resale flat. If you wish to sell or hypothecate the property after a lapse of time, you will not be able to do so without a valid OC.
• The water connection, sanitary connection or electricity supply can be disconnected in the absence of an OC.
How to obtain an OC
The OC is obtained from local municipal bodies by submitting an OC application form along with the following documents:
• Commencement Certificate
• Completion Certificate
• Built and Section plan
• NOC for fire and pollution
• Area calculation sheet of floor signed by an authorised architect
• Photographs of the completed building
• Tax assessment with tax paid receipt
• Photographs of rain harvesting and solar panels
• Copy of the sanctioned plan
After submitting the form, authorities inspect the complex and confirm if it has conformed to the approved plan before issuing an OC. Legally and ideally, a builder should submit an application with the municipal commissioner for the OC within 30 days of completion of the property.
How you can apply for an OC
As a flat owner, you can also apply for an OC by approaching the local corporation or municipality, and if all approvals are in place, an OC is issued within 30 days of application. You will have to submit the same documents as the builder to procure an OC.
Know your rights
If the builder refuses to provide an OC, you should consider exercising your legal rights. You can issue a notice against the builder asking him to apply and hand over the copy of the OC within a month. You can also approach consumer forums and file a writ petition demanding the OC.
Some canny builders simply present the receipt of the OC and dupe gullible customers. But you shouldn’t accept anything less than the actual OC as the receipt may be dated.
Landmark legislations like the Real Estate Regulatory Act (RERA) have been passed to regulate the sector, promote transparency and protect consumer rights. However, consumers must be vigilant and understand their rights and responsibilities towards owning a property. Documents like OC are essential and ensure the security of your investment.
Going forward, real estate experts believe that the OC should be made mandatory for the registration of flats and essential services. Until then, buyers must ensure builders get all the necessary approvals before handing over a property.
A Completion Certificate (CC) is an important legal document that certifies that a building is constructed according to the laid down norms and master plan of the city. This document has all the information related to the project, such as the building materials used, building height, and building plan, among other things like provision for green belt.
In a nutshell, this document certifies that the building adheres to all the prevailing rules and has not violated any norms. In fact, this document is to be shown compulsorily to the authorities to obtain electricity and water connection.
Builders are allowed to obtain a provisional Completion Certificate when there are minor works left in the project. Authorities then provide a provisional certificate valid for six months. After the expiry of the six months, the developer is bound to get a final CC.
Who issues a Completion Certificate?
Local authorities issue the Completion Certificate after a thorough inspection of the premises. If the developer violates no rules, authority issues a Completion Certificate.
Why is Completion Certificate important?
Buyers must be aware of the fact that if they are buying or moving into a property that does not have a Completion Certificate, they might be making a risky investment choice. The civic authorities hold the power to slap heavy penalties on the developer, leading to stalling or cancellation of the registered layout of the project. In case the building is already occupied, residents may also have to face eviction in extreme cases.
Difference between Occupancy Certificate and Completion Certificate
Occupancy Certificate examines and certifies a property for adherence to bye-laws, civic amenities, electricity, sanitation and other clearances. On the other hand, a Completion Certificate is a document that certifies that a property is fit for possession by the buyers.
Clarifying the difference, Deepak Kapoor, Director, Gulshan Homz, says, “Completion Certificate is just a reaffirmation that the building has been constructed as per the building byelaws and the layout plan has been approved by various concerned authorities. Occupation Certificate signals that there is no violation of building construction norms, and thus, the structure is safe for occupants.
Generally, these documents are not required at the time of registry, and hence, buyers tend to overlook or ignore these. But for their own benefit and peace of mind, it is warranted that buyers of both ready-to-move-in as well as under-construction properties check these documents before taking possession. This would help avoid any unnecessary dispute or confrontation in the future.”
Not a single word has been said about these certificates by the opposite parties. Whether any offer has been given by the opposite party to pay penalty regarding delay in delivery of possession? No such averments made in the written statement.
The Hon’ble Supreme Court on occupancy certificate by the builders.
“Supreme Court: The bench of Dr. DY Chandrachud* and AS Bopanna, JJ has held that failure on the part of the builder to provide occupancy certificate is a continuing breach under the Maharashtra Ownership Flats (Regulation of the Promotion of Construction, Sale, Management and Transfer) Act 1963 and amounts to a continuing wrong.
Factual Background
The appellant is a co-operative housing society. The respondent constructed Wings ‘A’ and ‘B’ and entered into agreements to sell flats with individual purchasers in accordance with the Maharashtra Ownership Flats (Regulation of the Promotion of Construction, Sale, Management and Transfer) Act 1963 (MOFA). The members of the appellant booked the flats in 1993 and were granted possession in 1997. According to the appellant, the respondent failed to take steps to obtain the occupation certificate from the municipal authorities.
There was an obligation on the respondent to provide the occupancy certificate and pay for the relevant charges till the certificate has been provided, however, the respondent time and again failed to provide the occupancy certificate to the appellant society. For this reason, a complaint was instituted in 1998 by the appellant against the respondent. The NCDRC on 20 August 2014 directed the respondent to obtain the certificate within a period of four months. Further, the NCDRC also imposed a penalty for any the delay in obtaining the occupancy certificate beyond these 4 months. Since 2014 till date, the respondent failed to provide the occupancy certificate.
In the absence of the occupation certificate, individual flat owners were not eligible for electricity and water connections. Due to the efforts of the appellant, temporary water and electricity connections were granted by the authorities. However, the members of the appellant had to pay property tax at a rate 25% higher than the normal rate and water charges at a rate which was 50% higher than the normal charge.
Analysis
Obligations of Promoter under MOFA
Section 3 of the MOFA imposes certain general obligations on a promoter. These obligations inter alia include making disclosures on the nature of title to the land, encumbrances on the land, fixtures, fittings and amenities to be provided, and to not grant possession of a flat until a completion certificate is given by the local authority. The responsibility to obtain the occupancy certificate from the local authority has also been imposed under the agreement to sell between the members of the appellant and the respondent on the latter.
Sections 3 and 6 of the MOFA indicate that the promoter has an obligation to provide the occupancy certificate to the flat owners. Apart from this, the promoter must make payments of outgoings such as ground rent, municipal taxes, water charges and electricity charges till the time the property is transferred to the flat-owners. Where the promoter fails to pay such charges, the promoter is liable even after the transfer of property.
Limitation
In the instant case, the appellant submitted that since the cause of action is founded on a continuing wrong, the complaint is within limitation.
Section 24A of the Consumer Protection Act 1986 provides for the period of limitation period for lodging a complaint. A complaint to a consumer forum has to be filed within two years of the date on which the cause of action has arisen.
Section 22 of the Limitation Act 1963 provides for the computation of limitation in the case of a continuing breach of contract or tort. It provides that in case of a continuing breach of contract, a fresh period of limitation begins to run at every moment of time during which the breach continues
A continuing wrong occurs when a party continuously breaches an obligation imposed by law or agreement. The continuous failure to obtain an occupancy certificate is a breach of the obligations imposed on the respondent under the MOFA and amounts to a continuing wrong.
The appellants, therefore, were entitled to damages arising out of this continuing wrong and their complaint is not barred by limitation.
“Rejecting the complaint as being barred by limitation, when the demand for higher taxes is made repeatedly due to the lack of an occupancy certificate, is a narrow view which is not consonance with the welfare objective of the Consumer Protection Act 1986.”
Consumer
Section 2(1)(d) of the Consumer Protection Act defines a ‘consumer’ as a person that avails of any service for a consideration. A ‘deficiency’ is defined under Section 2(1)(g) as the shortcoming or inadequacy in the quality of service that is required to be maintained by law.
In the present case, the NCDRC had held that the appellant is not a ‘consumer’ under the provisions of the Consumer Protection Act as they have claimed the recovery of higher charges paid to the municipal authorities from the respondent. Extending this further, the NCDRC observed that the respondent is not the service provider for water or electricity and thus, the complaint is not maintainable.
The respondent was responsible for transferring the title to the flats to the society along with the occupancy certificate. The failure of the respondent to obtain the occupation certificate is a deficiency in service for which the respondent is liable. Thus, the members of the appellant society are well within their rights as ‘consumers’ to pray for compensation as a recompense for the consequent liability (such as payment of higher taxes and water charges by the owners) arising from the lack of an occupancy certificate.
[Samruddhi Co-operative Housing Society Ltd v. Mumbai Mahalaxmi Construction Pvt. Ltd, , decided on 11.01.2022]”
Regarding delay of possession the only Supreme Court has held in the following case law,
“In Kolkata West International City Pvt. Ltd. Vs. Devasis RudraCitation : 2019 Latest Caselaw 299 SC
Judgement Date : Mar/2019[Civil Appeal No. 3182 of 2019 @ SLP (C) No(S). 1795 of 2017], the Hon’ble Supreme Court has held regarding delay in giving possession.
“This appeal arises from the judgment dated 21 November 2016 of the National Consumer Disputes Redressal Commission1. A Buyer's Agreement dated 2 July 2007 was entered into between the appellant and the respondent. The respondent paid an amount of Rs 39,29,280 in 2006 in terms of a letter of allotment dated 20 September 2006. The agreement between the parties envisaged that the appellant would hand over possession of a Row House to the respondent by 31 December 2008 with a grace period of a further six months ending on 30 June 2009.
The respondent filed a consumer complaint before the West Bengal State Consumer Disputes Redressal Commission2 in 2011 1 "NCDRC" "SCDRC" 2 praying for possession of the Row House and in the alternative for the refund of the amount paid to the developer together with interest at 12% per annum. Compensation of Rs 20 lakhs was also claimed. The SCDRC allowed the complaint by directing the appellant to refund the moneys paid by the respondent together with interest at 12% per annum and compensation of Rs 5 lakhs. The NCDRC has modified this order by reducing the compensation from Rs 5 lakhs to Rs 2 lakhs. Mr. Ravinder Narain, learned counsel appearing on behalf of the appellant submits that the primary relief which was sought in the consumer complaint was for delivery of possession. According to the appellant, the completion certificate was received on 29 March 2016, which was intimated to the respondent on 11 April 2016.
Moreover, before the SCDRC, in its written submissions, the appellant had offered possession of the Row House to the respondent. It has also been stated that in a complaint which was filed by an association representing the allottees of 161 Row houses, a settlement was arrived on 11 September 2018 before the NCDRC specifying the date on which possession would be handed over together with interest at 6% per annum instead of 4% as mentioned in the Buyers' Agreement. It was urged that the developer having made a substantial investment in terms of the agreement, a direction for refund is not warranted. It has also been urged that the SCDRC in the course of its decision erroneously observed that the developer was unable to fulfill its obligation to complete the construction within the agreed period and it was not certain when the Row house would be handed over. It was urged that this observation by the SCDRC is contrary to the record since before it, a specific offer of possession was made.
It has been urged on behalf of the respondent by Mr. Supriya Bose, learned senior counsel that a consumer complaint was filed in the year 2011. At that stage, the appellant was bonafide ready and willing to accept possession. However, nearly seven years have elapsed after the extended date for the delivery of possession which expired on 30 June 2009. In spite of this, no offer of possession was forthcoming. Learned senior counsel submitted that the letter dated 22 March 2016 of the developer was conditional and despite the subsequent letter dated 11 April 2016, no formal offer of possession was ever made by the appellant. Moreover, it was urged that the interest awarded by the NCDRC at the rate of 12% is just having regard to the economic loss and hardship suffered by the respondent. While considering the rival submissions, we must at the outset advert to the following clause which was contained in the Buyer's Agreement:
“Unless prevented by circumstances beyond the control of the company and subject to Force Majeure, KWIC shall ensure to complete the said unit in all respect within 31st December 2008 only for the Cluster D. Further there will be a grace period of 6 months (up to 30th June, 2009) from the date of completion. In case the possession is not transferred after expiry of the said grace period, KWIC will be liable to pay prevailing 4 saving Bank interest of the State Bank of India for each month of delay on the money given by the allottee as compensation but no compensation will be paid on account of force majeure reasons.” It is the above clause which is pressed in aid by the developer. Under the aforesaid clause, any delay beyond 30 June 2009 would result in the developer being required to pay interest at the prevailing savings bank interest of the State Bank of India.
Interestingly, where the buyer is in default, the agreement stipulates that interest at the rate of 18 per cent from the date of default until the date of payment would be charged for a period of two months, failing which the allotment would be cancelled by deducting 5% of the entire value of the property. The agreement was evidently one sided. For a default on the part of the buyer, interest at the rate of 18% was liable to be charged. However, a default on the part of the developer in handing over possession would make him liable to pay interest only at the savings bank rate prescribed by the SBI. There is merit in the submission which has been urged by the buyer that the agreement was one sided.
The clause which has been extracted in the earlier part of this order will not preclude the right and remedy available to the buyer to claim reasonable interest or, as the case may be, compensation. The essential aspect of the case which is required to be analysed is whether the buyer was entitled to seek a refund or was estopped from doing so, having claimed compensation as the primary relief in the consumer complaint.
The Buyer’s Agreement is dated 2 July 2007. In terms of the agreement, the date for handing over possession was 31 December 2008, with a grace period of six months. Even in 2011, when the buyer filed a consumer complaint, he was ready and willing to accept possession. It would be manifestly unreasonable to construe the contract between the parties as requiring the buyer to wait indefinitely for possession. By 2016, nearly seven years had elapsed from the date of the agreement. Even according to the developer, the completion certificate was received on 29 March 2016. This was nearly seven years after the extended date for the handing over of possession prescribed by the agreement. A buyer can be expected to wait for possession for a reasonable period.
A period of seven years is beyond what is reasonable. Hence, it would have been manifestly unfair to non-suit the buyer merely on the basis of the first prayer in the reliefs sought before the SCDRC. There was in any event a prayer for refund. In the circumstances, we are of the view that the orders passed by the SCDRC and by the NCDRC for refund of moneys were justified. Having regard to all the facts and circumstances of the case, we modify the order of the NCDRC by directing that the appellant shall pay interest at the rate of 9% per annum to the respondent instead and in place of 12% as directed by the NCDRC. Save and except for the above modification, we affirm the directions of the NCDRC.
The amount outstanding in terms of the directions of this Court shall be released out of the moneys which have been deposited by the appellant. The balance, if any, that remains shall be refunded to the appellant. The appeal is, accordingly, disposed of. There shall be no order as to costs. Pending application(s), if any, shall stand disposed of.”
Now from all the given circumstances it has been clear that the opposite parties failed to deliver the possession of the unit within the promised time and they now sending different demand to extract the money from the complainant but did not disclose as how much penalty they had to pay to the complainant regarding delay in the delivery of possession to the complainant. The opposite parties have stated that there has been delay in payment of various instalments by the allottees. It cannot be raised because the actual date of handing over the possession of the flat has already been expired, the opposite parties are not in a position to demand extra money before adjusting the penalty in the balance amount to be deposited by the complainant. No new demand can be raised after the cut-off date because the possession was not handed over to the complainant. Now the defaulter is opposite parties and not the complainant.
Whether the opposite parties have paid any interest on the amount deposited by the complainant.? Regarding payment of interest on the deposited amount only Supreme Court has said in various judgment if you are being quoted here.
Ghaziabad Development Authority v. Balbir Singh