Andhra Pradesh

StateCommission

CC/45/06

BHARAT HEAVY PLATE AND VEESELS LTD - Complainant(s)

Versus

MS NATIONAL INSURENCE CO LTD - Opp.Party(s)

21 Dec 2009

ORDER

 
First Appeal No. CC/45/06
(Arisen out of Order Dated null in Case No. of District )
 
1. BHARAT HEAVY PLATE AND VEESELS LTD
VISAKHAPATNAM REP MANAGER
 
BEFORE: 
 HONABLE MRS. M.SHREESHA PRESIDING MEMBER
 
PRESENT:
 
ORDER

 

 

 

 

 

BEFORE THE A.P. STATE CONSUMER DISPUTES REDRESSAL COMMISSION

AT HYDERABAD.

 

C.C. No. 45/2006 

 

Between:

 

Bharat Heavy Plate & Vessels Ltd.

(A Subsidiary of Bharat Yantra Nigam Ltd.

(A Govt. of India Enterprise)

Visakapatnam- 530 012,

Andhra Pradesh,

Rep. by its Manager (Legal)                         ***               Complainant

 

                                                                   And

M/s. National Insurance Company Ltd.

Direct Agent Branch

Seethamapeta Road

Dwarakanagar

Visakapatnam-530 016.                              ***               Opposite Party     

 

 

Counsel for the  Complainant:                   M/s.  C. Kodanda Ram

Counsel for the OPs:                                   M/s. Katta Laxmi Prasad.
                                                                  

CORAM:

 

 

                         HON’BLE SRI JUSTICE D. APPA RAO, PRESIDENT     

&

                                          SRI R.L. NARASIMHA RAO , MEMBER

 

 

MONDAY, THIS THE TWENTY FIRST DAY OF DECEMBER  THOUSAND NINE

 

Oral Order: (Per Hon’ble Justice D. Appa Rao, President)

 

                                                          ***

 

 

1)                This is a complaint filed  against insurance company  claiming Rs. 67,00,030/- together with compensation and costs.

 

2)                 The case of the complainant in brief is that  it is  a public sector  engineering company a subsidiary unit of Bharat Yantra Nigam Ltd, owned by the Government of India specialized in erection of  cryogenic plants, process plants, boilers and storage vessels.    It secured  the contract of  lump sum turnkey project  from IOCL  for hydro treating  facilities.  The cost of the project being  Rs. 91.85 crores.    In pursuance to the said contract  it has placed  the purchase order  on M/s. Ingersoll Rand, Ahmedabad  for  design, manufacture,

 

 

Supply,  and  supervision of  erection, field  testing and commission of two  air

compressors.    It had taken marine-cum-insurance policy from the  opposite party by making  IOCL  as principal  valid from  19.1.2001 to  18.1.2004 and further extended up to 18.4.2004.    The policy commenced from the date of despatch of the first consignment and remain in force till the completion of above said period or till the completion of erection including test run whichever is earlier and the sum assured was Rs. 86,46,50,000/-     The consignment was despatched and the same was reached at Digboi site  on 16.5.2001 without any damage.   However, due to heavy rains   civil foundation was not laid immediately, and the consignment was stored for 70 days.    On  26.7.2001  air compressors were taken out  and  were successfully erected on respective foundations under the same roof.   Their engineers  and that of  IOCL   EIL and  S.K. Maitra, Engineer of supplier  on joint inspection on  23.6.2002  found accumulation of  rainwater and patches/pitting on 1st and 3rd stage  in one of  the air compressors.    Immediately said fact was intimated to the insurance company  on  24.6.2002  and requested to depute a surveyor  for assessment of the damage.    The insurance company in its turn  appointed  Mr. R.K. Agarwal  a surveyor on  8.8.2002  to conduct survey, investigate, and assess the damage.     The surveyor conducted the survey from  10.8.2002 to 26.11.2002 found damage to the equipment and directed the complainant to carry  out repairs and replacement in order to assess the exact loss caused in the said damage.    Accordingly it carried out repairs and replacements by incurring Rs. 67,00,330/- and successfully commissioned the equipment on 5.11.2003 which was inspected by the surveyor on  29.11.2003.    It lodged  a claim for Rs. 67,00,330/-.  It had taken an advance from IOCL  on interest @ 15.25% p.a. to release the payments to the supplier for the said repairs and replacements, and requested the insurance company to release the claim amount directly to  the IOCL.    The  surveyor  found  that  the loss was caused

due to accidental entry of rain water tinged with traces of acid in the oil tanks during the period of storage at site though  the consignment was covered with

 

tarpaulin.   However, it accepted the claim for Rs. 48,26,000/- instead of  Rs. 67,00,330/- by mentioning some untenable deductions.   When the insurance company failed to settle the claim  and when it addressed letters after letters  the insurance company again  introduced  Sri A. Chandra Mouli  of M/s. Mehta &  Padamsey another surveyor seeking his opinion in the matter  without giving any reason.  It is contrary to law.    Finally by letter Dt.  13.9.2004  the insurance company repudiated the claim  on the ground that the loss falls under expected peril and exclusion clause ( c ) of Section-I of  part-II i.e., normal wear and tear gradual deterioration due to  atmospheric  conditions or otherwise rust scratching of painted or polished  surfaces or breakage of glass.    When the first surveyor had categorically stated that the losses  do not fall under exclusion clauses of the policy , 2-1/2  years  thereafter  the second surveyor repudiated the claim on the ground that the risk falls under exclusions clause.  It  is unjust.    Despite repeated requests and meetings with the higher ups  the  claim was not settled and therefore it filed the complaint alleging deficiency of service on the part of insurance company and claimed Rs. 67,00,330/- towards loss together with  interest, compensation and costs in all Rs. 98,33,560/-. 

 

4)                 The insurance company resisted the case.  It denied each and every allegation made in the complaint.  However it admitted that it had issued marine-cum-erection policy subject to terms and conditions.   The claim does not fall come under  the purview of  consumer fora.    The complainant  is not a consumer.   No permission was obtained before initiating  the legal proceedings which is mandatory as the Government of India  is involved in the litigation.    When the application is pending clearance  the complaint was filed  and therefore it was liable to be rejected.   The marine portion  of the policy  no more survives  as it was successfully transhipped.   The other portion of the policy is erection and the  equipment  kept stored at site  in open for 70 days before erection.    

One year after commissioning of erection     M/s. Ingersol  Rand   reportedly found  water accumulation  in  1st and 3rd stage and found pinions, bearings and bull gear teeth rusted and pitted  and advised replacement before commissioning.   Initially they lodged the claim against the carrier during  conduction of survey.  and later the claim against the carrier was withdrawn.   In fact, the complainant could not able to understand exact cause of pitting  to give opinion.   The rusting of high grade steel parts could be explained by the suppliers only.    In the joint inspection Dt. 5.9.2002 they observed that the rusting and pitting on all rotor assemblies  were attributed to accumulation of water  which might have entered  accidentally  in oil reservoir  through one of the plugs meant for instruments while in transit or storage.    Since the carrier was given a clean chit, no claim survives against them.   The surveyor after taking into consideration  assessed the net loss at Rs. 48,26,000/-.   Rust   observed on the internal parts is excluded  as per the exclusion clause  (c) of  Schedule-I, Part-II of the erection  all risk cover of the  marine-cum-erection policy issued to the complainant.   It is borne out from  the technical  opinion provided by  M/s. Mehta & Padamsey  Surveyors Pvt. Ltd., Chennai.   Thus the claim was repudiated  on  13.9.2004.   There is no cause of action for the complainant to file the case.  When the complainant admits that when two  air compressors  were successfully erected  it was absolved from any liability  under the policy coverage.    They did not admit their liability  to pay any  amount.   Therefore, it prayed for dismissal of the complaint with costs.

         

5)                The complainant filed rejoinder to the written version filed by the opposite party insurance company alleging that the very surveyor who was appointed by the insurance company concluded that the loss does  not fall under any of the exclusions of the policy.    There was no breach of policy terms and conditions.  The risk has been reinstated to the satisfaction of the insured  and recommended the insurance company to reimburse the loss.   Appointment of  second surveyor  after two years was bad under law and  was made to get over the first surveyor report,  and therefore prayed that the complaint be allowed.

 

6)                The complainant in proof of its case filed the affidavit evidence of  K. Abrham, Manager and filed Exs. A1 to A53 while the insurance company filed the affidavit evidence of   D. C. Baheti its authorised signatory  and filed Exs. B1 to B5.

7)                The points that arise for consideration are:

i)                   Whether the complainant is a consumer?

 

          ii)       Whether the loss that occurred  does not fall  under any of the

exclusions of the policy?

 

iii)              Whether there was any breach of policy terms and conditions?

 

iv)                Whether the complainant is entitled to any  amount  covered

under the policy?

 

           v)      Whether the complainant is entitled to any damages?

         

vi)      To what relief?

 

8)                It is an undisputed fact that the opposite party  insurance company  issued marine-cum-erection policy effective from  19.1.2001 to 18.4.2004.  The claim towards marine portion of the policy does not survive as the consignment of  air compressors was successfully transhipped from  Gujarat to Assam.    It is also not in dispute that  when the machinery  was tested at site  on 16.5.2001  there was no damage.   The dispute pertains to the other portion of the coverage of the policy viz.,   erection and commissioning of the equipment.   When the equipment was checked  while commissioning   by Ingersol Rand, the  service Engineer observed that  water accumulation had taken place on 1st and 3rd  stage.  The pinions and bearings were found  in rusted condition  along with the bull gear teeth, and advised to replace the components  before  commissioning  the  compressor.   The complainant thinking that the water in the compressor  might have entered  accidentally in transit  lodged a complaint with the carrier.    Later it came to learn that it was occurred  at the site  on a claim made by  complainant,   Sri  R. K. Agarwal a surveyor was appointed by the insurance company.    He observed that  there was heavy rusting  and pitting   on  all the impeller with shaft and pinion, plain bearings and  thrust bearings etc., and the possible cause of  damage was  accumulation of water,  which might have entered accidentally  in the oil reserve  through one of the plugs  which was meant for instrument, in transit or  storage.    Sri  R. K. Agarwal conducted  survey, investigated  and assessed the claim.  In his report Dt. 27.1.2004  after conducting the survey  traced out the antecedents of the consignment  and found  :

 

  1. The  suppliers  Ingersol Rand had sold the air compressor  S.No.  N00-1150 vide invoice No. 00138 for Rs. 1,00,11,205/-.

 

  1. The goods were shipped in 8 different boxes by the carriers  Economic  Transport  Organization  under C.N. No. 8482 Dt. 30.4.2001 by trailer truck  No. HR-38-6451.

 

  1. The consignment reportedly reached Digboi  on 16.5.2001.

 

  1. There was no apparent physical damage to the packages and the consignee gave a clean chit to the carrier.  The consignment thereafter was kept at site and reported to have been covered by a tarpaulin. 

 

  1. The packing was removed and erection/commissioning started on 26.7.2001.  The packed goods remained in their packages from 16.5.2001 to 26.7.2001 i.e., for nearly 70 days covered by a tarpaulin at site. 

 

  1. Third party inspection was carried out at the works of Ingersol  Rand at Naroda by  Lioyd’s  Register  Industrial Services (India) Pvt. Ltd.  (LRIS)  who had witnessed the tests of the compressor on 26.4.2001.

 

  1. Shipment preparation certificate after inspection of packages were also issued by the suppliers which have been witnessed by the representative of LRIS.

 

  1. The third party inspection at the works  and the shipment clearance  on LRIS  eliminates  any possibility  of any water being trapped prior to shipment at the manufacturer’s work. 

 

 The  surveyor has contacted the officials  of   IOCL,  BHPV Ltd., Ingersol Rand India Ltd.  He observed that  “it was obvious that the rusting had occurred because of the trapped moisture.  The consignment was  kept at site covered by a tarpaulin  for  nearly 70 days  at the site before the packages were removed and erection started.   It is a high rainfall area where there is  heavy rain.   In our opinion water  must have  accidentally  entered the oil  chamber through one of  the plugs  meant  for fixing instrument  and during bright sunny day  the trapped water  had  evaporated and passed through  the oil lines  and got  condensed  on the rotor  assemblies  and bull gear.   This trapped water  must have contained  some acidic  traces which  is possible  in the refinery  area and the rusting of the internal components  have taken place.   Once the process of rusting  and corrosion  started  it progressed  and caused  pitting.    There was  sufficient  time for the process of  corrosion to set  in as these parts  were in enclosed steel body and the damage  was observed only during commissioning on  23.6.2002 i.e., almost after 13 months after the arrival of goods at  the destination.”    Finally he made the following remarks :   

1)     The loss do not fall under any of the exclusions  of the policy.

2)     There is no breach of policy terms and conditions  in our opinion.

3)     The risk has been reinstated to the satisfaction of the insured.

4)     There is no under insurance.

5)     The salvage value have been deducted.

 

Ultimately he assessed the  net loss at Rs. 48,26,000/-. 

 

9)                Obviously  the said report was not to the liking of the insurance company.   It was thinking as to how it could be repudiated.  Predictably  it has  appointed  another surveyor  M/s. Mehta and Padamsey  Surveyors  Pvt. Ltd., unilaterally  after a lapse of  two years from the date of loss  and 6 months from the date of first  surveyor’s  report, in contravention of  Section 64 UM of the  Insurance Act. 

 

10)              It is not a case where the insurance company approached the authorities and made allegation against the first surveyor  on the ground that  he  had colluded or fraud was perpetrated  and therefore necessitated  appointing a  second surveyor.   The second surveyor  can be termed as extra legal authority  as opined by National Commission in   New India Assurance Company Ltd. Vs.  Shree Shyam  Cotspin Ltd. reported in 1 (2009) CPJ 110 (NC).    Be that as it may,  the second surveyor without mentioning   any details  contradicted  report of the first surveyor by giving specious reasons,   repudiated the claim.  He opined that the claim falls under exclusion  clause vide Section-I Part-II of the policy.    The surveyor  noted omissions and discrepancies  like in a Criminal case, and imported its  own knowledge as to the process at Digbai refinery by IOCL.     It  could not substantiate by referring to any expert on the subject.  It  put a sort of queries for considering the exclusion clause.  Para 17 of their report reads as follows :    

          “All the above information from suppliers  contractors  and the surveyors admit that the cause of damage was rusting  and pitting due to contact  with water at some stage  before the testing commenced.  The issue therefore now revolves around whether the damage due to rusting would constitute an exclusion under the policy or not.  We shall now analyse the relevant section of the policy dealing with the exclusion. 

                  

          Exclusion to Section-I – item  ( c ) dealing with the relevant portion  reads as follows :

          ( c )    normal wear and tear, gradual deterioration  due to atmospheric  conditions or otherwise, rust, scratching of painted  or polished surfaces or breakage of glass. 

 

 

11)               One of the grounds  they pointed out was that the damage was observed only during commissioning on  23.6.2002  i.e., almost  13 months  after the arrival of the goods at destination.   Therefore they reasoned that there was sufficient time for the process of corrosion to set in as these parts were enclosed steel body.   Once the process of rusting and corrosion started it progresses and cause pitting.    They further observed  that “ The damage was not caused by mere accidental entry of water but because of not taking note of such entry of water or moisture  in time, allowing the same affect the material gradually further progressing  into corrosion and  pitting  over a period.   It is confirmed that the unit was held covered by tarpaulin  and if water found its way  inside due to whatever cause,  the same will have a green  house effect on the atmosphere inside leading to high humidity, condensation, rusting and progress of the same when not detected and attended.  The damage is clearly due to an exception under the policy and we see no reason for considering a claim under marine cum erection.    Further too much of discussions are devoted to the source of entry of water in a location to cause rusting.  There was no need for any separate water entry source at all in a situation where  the insides are being looked into more than thirteen months after receipt at a location of high rainfall and substantial humidity.”

 

 

 

12)               The second surveyor has referred to  Section 413 of Halisbury’s  Laws of England dealing with intention of parties as a test in insurance.  It opined that   the document will be construed  in such a way  as to give efficacy to the  transaction  in accordance with the maxim “  ut res magis valeat quam pereat”  ( it is better for a  thing to have effect than to be made void).  Where two constructions are possible, the one which tends to defeat the intention or to make it practically illusory will be rejected.   It thought that the rusting and damage of similar nature constitute an exclusion under the marine-cum-erection policy.  The printed words specifying the exclusion cannot be circumvented to bring another construction.    Therefore it opined that the damage due to rusting was excluded  and therefore it comes under exclusion clause.   

 

13)              PW1 Manager of the complainant categorically stated that  on   26.7.2001 both the  air compressors were taken out and were successfully erected on  its respective foundations  under the same roof under the supervision of  supplier’s service engineer Mr. S. K. Maitra and the complainant’s engineers,  which actually was  the beginning of the erection process.   The erection of  the air compressor would  be completed only  when levelling, alignments works,  piping works, utilities  were  to be completed up to battery limits.   Hence the erection of the air compressor was not completed on 26.7.2001.          Having obtained a  report  from the first surveyor M/s.  R. K. Agarwal  appointed  by it and  having invited  their adverse findings  that the loss  did  not  fall under any  of the exclusion clauses,  and there was no breach of  policy terms and conditions, it does not lie in the mouth of the insurance company to appoint again another surveyor  contrary to Section 64 UM of the Insurance Act.   The appointment  of second surveyor that too with a delay of  six months cannot be lost sight off  and the report of the  second surveyor is non-est  and void.   The reasons all that prompted them to repudiate the claim was not inconsonance with  the facts and circumstances of the case.    The first surveyor estimated the loss at Rs. 50,80,000/- however deducted Rs. 2,54,000/- towards the excess for storage and  erection risk  as per the policy is 5% of the claim amount subject to a minimum excess of Rs. 1 lakh accordingly the excess applicable was 5% of Rs. 50,80,000/-. and   therefore  recommended the loss payable to the insured was Rs. 48,26,000/-.    The insurance company  could not show any fallacy  in the report.  Therefore, we accept the report of the first surveyor  and of the opinion that the complainant is entitled to  the said amount of  Rs. 48,26,000/-.

 

14)               Learned counsel for the  opposite party insurance company  contended that  the  Consumer Fora has  no jurisdiction  to entertain the dispute.   He did not expatiate.  However, it is settled law that  the insurance is one of the services  and therefore  comes under the definition of  Sec 2(O) of the Consumer Protection  Act.    The Supreme Court distinguished the contract of insurance with  other contracts in United India Insurnace Company Ltd. Vs. Great Eastern Shipping  Company Ltd. reported in   III (2007) CPJ 3 (SC).

 

15)              Learned counsel for the  opposite party insurance company  has taken yet another contention stating that without taking clearance from the Committee constituted by the Government  the complainant cannot file a complaint.   The complainant as well as the insurance company are public sector undertakings. It is necessary that  all the disputes between the government departments or public sectors undertakings  of  Union of India  have to be settled amicably after obtaining clearance from the  committee set up by the Government of India.   The said procedure is mandatory.    In support of his contention he relied a decision   of  Supreme Court in

 M/s. Oil & Natural Gas Commission  Vs.  Collector of  Central  Excise  reported in  JT 1991 (4) S.C. 158 wherein  their Lordships opined that “ It shall be  the obligation of every Court and every Tribunal where such a dispute is raised  hereafter to demand a clearance from the committee  in case it has not been so pleaded and  in the absence of the clearance, the proceedings would not be proceeded with.”

         

 

 

The Committee on Disputes  in its meeting held on  13.3.2008 in the presence of  opposite party insurance company permitted the complainant  to pursue it  before the A.P. State Consumer Disputes Redressal Commission, Hyderabad.  It may be stated herein that the representative of the complainant  submitted before the Committee that the surveyor had submitted his report indicating that the claim does not fall under any exclusion clause of the insurance policy and recommending payment  of Rs. 48.60 lakhs to BHPV.   The company rejected the claim on the ground that it  is not tenable under the MCE policy invoking the exclusion clause.   Even the  Supreme Court  in the above decision directed the Court or Tribunal  not to proceed till  the clearance is obtained.   It did not say till  the clearance is made the parties cannot demand the amount covered under the dispute.  At some times, the claims  might be barred by limitation if one has to wait for clearance.   Whatever be the reason, since  Ex. A52  authorises the complainant to go ahead with the case filed and in the teeth of the  Supreme Court  judgement, we are of the opinion that the complaint is not barred  and cannot be dismissed on that score. 

 

16)               In the result the complaint is allowed in part granting  Rs. 48,26,000/- together with interest  @ 9% p.a., from the date of repudiation viz., 13.9.2004  till the date of realization together with costs of Rs. 5,000/-.  Time for compliance four weeks.

 

 

1)       _______________________________

PRESIDENT                 

 

 

 

2)      ________________________________

 MEMBER          

 

                                                          Dt.      21.  12.  2009.

*pnr

 

C.C.NO.45 OF 2006

APPENDIX OF EVIDENCE

 

Complainant:                                                       Opposite party

 

Affidavit evidence and Addl.Affiavit                       Affidavit evidence filed.

Evidence filed.

 

Reply to written version filed.

 

Exhibits marked for complainant

 

Ex.A-1         General Power of Attorney dt.8.2.2003.

Ex.A-2         Purchase orders dt.1.1.2001.

Ex.A-3         Marine-cum-Erection policy issued by the opposite party
                   dt.19.1.2001.

Ex.A-4         Letter from R.K.Agarwal, Surveyor and Loss Assessor to
                   Mr.V.R.K.Raju dated 14.8.2002

Ex.A-5         Letter addressed by the complainant to the opposite party
                   dt.2.7.2003.

Ex.A-6         Letter addressed by the opposite party to the complainant
                   dt.7.7.2003.

Ex.A-7         Letter addressed by the complainant to the opposite party
                   dt.8.6.2004.

Ex.A-8 to
A-10             Letters  dt.16.7.2004, 18.8.2004 and 23.8.2004 respectively 
                   addressed by the complainant to the opposite party requesting for
                   settlement of claim.

Ex.A-11       Repudiation letter dt.13.9.2004 issued by the opposite party.

Ex.A-12       Letter from opposite party to the complainant dated 27.9.2004
Ex.A13 &    Letter from IOCL to the opposite party dated 1.10.2004 & 27.1.05
Ex.A14

Ex.A-15       Letter addressed by IOCL to the complainant dt.1.4.2005.

Ex.A-16       Report submitted by Mr.R.K.Agarwal, Surveyors &
                   Loss Assessors dated 27.1.2004

Ex.A-17        Letter dt.8.8.2002 addressed by the opposite party to the
                   Surveyor.

Ex.A-18       Copy of Marine-cum-erection policy issued by the opposite party
                   dated 19.1.2001.

Ex.A-19       Copy of the Letter addressed by Mr.V.R.K Raju to the Sr.Divisional
                   Manager of opposite party Insurance Company dt.24.6.2002.

Ex.A-20       Letter addressed by Mr.V.R.K.Raju to the opposite party Insurance
                   Company dt.25.7.2002.

Ex.A-21       Purchase indent issued by the IOC Ltd., Assam.

Ex.A-22       Letter addressed by Ingersoil Rand to the Complainant
                   dt.24.5.2004.

Ex.A-23       Invoice issued by Ingersoil Rand.

Ex.A-24       Copy of invoice.

Ex.A-25       Document transmittal sheet.

Ex.A-26       Schedule of Demurrage charges issued by Economic Transport
                   Organization.

Ex.A-27       Order acknowledgement dt, 26.3.2001.

Ex.A-28       Packing note issued by Ingersoll Rand (India) Ltd.,

Ex.A-29       Inspection release note

Ex.A-30       Shipment preparation certificate issued by Ingersoll Rand
                   dt.20.7.2000.

Ex.A-31       Guarantee certificate issued in Ingersoll Rand  dt.30.4.2001.

Ex.A-32        Letter addressed by Mr.V.R.K.Raju, Project Incharge to
                   Mr.R.K.Agarwal dt.29.8.2002.

Ex.A-33       Report issued by Sri S.P.Maitra.

Ex.A-34       Letter addressed by Ingersoll Rand dt.1.7.2003 to the
                   complainant.

Ex.A-35       Minutes of the discussion held on 5.9.2002.

Ex.A-36       Joint Inspection report dt.21.1.2003.

Ex.A-37
and             Letters addressed by Ingersoll Rand to the complainant
A-38           

Ex.A-39       Amendment dt.8.5.2003 issued by the complainant.

Ex.A-40       Letter addressed by Ingersoll Rand dt.16.5.2003 to the
                   complainant.

Ex.A-41       Copy of D.D for Rs.48,33,679/-.

Ex.A-42       Receipt issued by Ingersol Rand.

Ex.A-43       Lorry receipt issued by  IBC India Ltd.,

Ex.A-44       Inter office memo dt.11.9.2003 issued by the Project Director of the complainant.

Ex.A-45       Insurance claim for repair of Air compressor

Ex.A-46       Inter office memo issued by Sr.Manager of the complainant
                   dt.14.5.2003.

Ex.A-47       Letter dt.20.1.2004 issued by Chief Project Manager, IOC, Digboi.

Ex.A-48       Letter addressed by Ingersoll Rand to the complainant
                   dt.6.11.2003.

Ex.A49        Letters from IOC to the complainant dated 5.1.04 26.3.04& to Ex.51                  11.9.2006

Ex.A52        COD Permission issued Govt. of India dt.13.3.2008
Ex.A53        Book containing Schedule of Air Compressor Erection
                   (129 Pages.)

 

Exhibits Marked for opposite party

 

Ex.B1                   Letter from opposite party to first surveyor dt.24.3.2004
Ex.B2                   Reply from first surveyor to opposite party dt.20.4.2004
Ex.B3                   Reminder dated 22.4.2004 issued by the opposite party
                   to the first surveyor
Ex.B4                   Letter from opposite party to the second surveyor dt.30.6.2004
Ex.B5                   Report from Surveyor to the opposite party dt.27.7.2004

 

 

 

 

 

                                                                             1)           _______________________________

PRESIDENT                 

 

 

 

2)      ________________________________

 MEMBER          

 

 

 

 

 

 

 

 

 

 

 

 

“UP LOAD – O.K.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 
 
[HONABLE MRS. M.SHREESHA]
PRESIDING MEMBER

Consumer Court Lawyer

Best Law Firm for all your Consumer Court related cases.

Bhanu Pratap

Featured Recomended
Highly recommended!
5.0 (615)

Bhanu Pratap

Featured Recomended
Highly recommended!

Experties

Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes

Phone Number

7982270319

Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.