BEFORE THE A.P.STATE CONSUMER DISPUTES REDRESSAL COMMISSION :HYDERABAD
C.C.No.30/2009
Between:
Srinivas Mopuri, S/o.Mobanna,
aged about 33 years,
R/o.1509 Weatherford Drive,
Austin, Texas-78753, Rep. by his
G.P.A.Holder Mopuri Obanna ,
S/o.M.C.Kondaiah, aged about 63 years,
The R/o.11-3-155 Venkateswara Colony,
Road No.13, Saroor Nagar, Hyderabad-35. … Complainant
And
M/s. Maytas Properties Ltd.,
(Earlier Maytas Hill County Pvt. Ltd),
Registered Office 6-3-1186/5/A 3rd floor,
Amogh Plaza, Begumpet,
Hyderabad , rep. by its Directors. … Opposite party
Counsel for the Complainant : M/s. Manne Haribabu
Counsel for the Opposite party : M/s.A.Venkatesh.
CORAM:HON’BLE JUSTICE SRI D.APPA RAO, PRESIDENT,
AND
SMT. M.SHREESHA, HON’BLE MEMBER
FRIDAY, THE THIRTIETH DAY OF APRIL,
TWO THOUSAND TEN.
Oral Order :(Per Smt. M.Shreesha, Hon’ble Member)
***
The brief facts as out in the complaint are that the complainant entered into an agreement of sale dt.16.2.2007 for flat No. 8A, 8th floor, Type 4 in Simla Block having built up area of 1584 sq.ft., common area of 396 sq.ft. and one car parking area with 88 sq. yards of undivided share in the common land in Sy.No.194/P, 196/P, 197/P for the total consideration of Rs.74,49,352/- payable in a phased manner from 1.12.2006 to 15.3.2008 and as per the agreement of sale the opposite party has to complete the construction by 31.8.2008 or 24 months from the date of execution of the sale agreement which ever is later.
The complainant submits that he paid total amount of Rs.63,37,984/- , the details of which are as follows:
Receipt Date | Cheque/DD No. | Amount | Payers bank | Branch |
18-Nov-2006 | 697130 | 744,935.00 | Andhra Bank | Saroornagar |
16-Jan-2007 | 109491 | 400,000.00 | ABN Bank | New Delhi |
16-Jan-2007 | 109492 | 369,706.00 | ABN Bank | New Delhi |
2-Feb-2007 | 109539 | 968,781.00 | ABN Bank | New Delhi |
29-Mar-2007 | 110029 | 968,781.00 | ABN Bank | New Delhi |
15-May-2008 | 241378 | 968,781.00 | ABN Bank | New Delhi |
4-Aug-2008 | 697121 | 960,000.00 | Andhra Bank | Saroornagar |
4-Aug-2008 | 697122 | 960,000.00 | Andhra Bank | Saroornagar |
Though the said amounts were paid by 4.8.2008 the opposite party did not complete the structure. Recently the government ordered CBI enquiry and the Company Law Board appointed Special Director along with two Directors of the Company to the opposite party company . The Special Director conducted a meeting on 25.3.2009 at Hill County with the flats and house purchasers of Hill County. At that time the complainant requested to cancel the agreement and to refund the amount as he lost the confidence on the opposite party company but there was no response. As per the Termination Clause of the Agreement, the opposite party promised to pay the amount within a month from the date of termination failing which they agreed to pay interest at 10% p.a. The complainant gave termination letter dt.25.3.2009 to cancel the agreement but there was no response. The complainant got issued a legal notice dt.28.4.2009 for which opposite party replied on 13.5.2009 in which they have stated that as per clause 6 of the agreement construction of flats (from 5th to 12 floors) depends upon the High Court order in W.P.No.23635/2005 as such it could not get approval for additional floors construction. The complainant submits that opposite party never stated that they did not have approval for 5 to 12 floors and had they informed him the same he would not have purchased a flat in the 8th floor. Even in their allotment letter dt.18.11.2006 they did not mention that there is no approval for 5th to 12th floors. The PIL and W.P.No.23635/2005 are in the year 2005 whereas the agreement was arrived in the year 2007. Opposite party in their letter dt.18.9.2007 stated that “ this project as now got all approvals, more particularly HUDA approval for all the 13 floors its sub cellars and the fire department approval for the same.”. It is also stated that this approval copies were sent to the Home Loan Bankers, which means that HUDA had already approved the construction of 13 floors.
If opposite party is not constructing the said floors the complainant is compelled to pay heavy interest on the loan taken and moreover the if opposite party constructed all the 13 floors, four blocks fully and 60% in other blocks basing on the HUDA approval and there would be no constraints in the complainant’s case and there is no legal hurdle since these 13 floors in four complexes were constructed after 2005 when the matter was subjudiced and there was no direction from the High Court to stop these works. Thereafter the opposite party sent a letter dt.10.1.2009 mentioning HUDA approval. The newly appointed Special Director Mr.Ved Jain conducted a meeting on 25.3.2009 and only explained financial constraints for the completion of project, but never contended that there was any legal hurdle. Vexed with their attitude the complainant cancelled the agreement and as per the schedule II in the Agreement total amount of Rs.74,,49,352/- is to be paid on the dates indicated in the schedule as sale consideration. The schedule of payment was made without indicating any progress of the works. However the complainant paid 90% of the amount and the structure was completed only upto 6 floors where as the complainant’s flat is in the proposed 8th floor. Hence the complainant submits that there is deficiency in service on behalf of the opposite party and seek the following directions to the opposite party:
a). to direct the opposite party to return an amount of Rs.63,37,984/- which was paid towards sale consideration of flat No. 8A , 8th floor, type-4 in Simla Block having built up area of 1584 sq. ft. common area of 396 sq.ft. and one car parking with 88 sq. yards of undivided common land share in Sy.No.194/P, 196/P, 197/P with interest at 24% p.a. from the date of receipt of the amount till realization
b). to award an amount of Rs.10 lakhs as compensation to the complainant for the inconvenience, pain and suffering,
c) to pay an amount of Rs.20,000/- towards costs and incidental expenses.
The opposite party filed counter stating that they started a new venture at Bachupally under the name and style of M/s.Maytas Hill County and the complainant approached the opposite party with a request for purchase of flat bearing no.8(A) , 8th floor, Type IV in Shimla Block having a built up area of 1584 sq. ft. with common area of 396 sq. ft. together with undivided share of land of 88 sq.yds. in the opposite party project ‘Hill County’. After discussions and deliberations the complainant agreed to purchase the above flat for a total sale consideration of Rs.74,49,352/- excluding stamp duty, registration fee, VAT, service tax etc. The complainant entered into an agreement of sale on 16.2.2007. As per the said agreement, opposite party had to complete the construction on or before 31.8.2007 or 24 months from the date of execution of the agreement whichever is later excluding the grace period of 3 months. However the said period stands suspended from the period of computation because of a).Force Majure Event, b).availability of steel and construction material, c).result of W.P. 26365/05 . The clause 6 of the Agreement of Sale clearly stipulates that in view of the Interim direction of the A.P.High Court in W.P.No.26365/2005 the approval for plans from 5th to 12th floors would be granted after disposal of the Writ Petition wherein it is stated as follows:
“Whereas in view of the interim directions of the Hon’ble High Court of Andhra Pradesh in W.P.No.23635 of 2005 in suo-moto PIL (PIL is not against Maytas Hill County Private Limited or the property in question), the approval for plans form floor five to twelve is expected only after necessary directions from the Hon’ble High Court of Andhra Pradesh and this is likely to have a impact on the likely date of completion of the said floors. “
The complainant being fully aware and conscious about the Writ Petition agreed to purchase the flat in the 8th floor and the construction could not be completed for certain events beyond the control of the opposite party and government and other agencies have taken up investigation on the affairs of the opposite party and they are extending full cooperation. Opposite party denies that the complainant made a request to cancel the agreement and for refund of the amount. Opposite party denied that they promised to pay amount within a month from the date of termination failing which agreed to pay interest at 10%. They deny that the complainant had given termination/request letter to cancel the agreement. The letter dt. 18.9.2007 is fabricated and the complainant was informed that the amounts were due to be paid and because of Clause 6 of the Agreement which states that because of any force maejure events if the completion is delayed there is no violation of terms of the agreement. The opposite party has started the venture with bonafide intention to construct the world class township and because of writ petition and unavoidable circumstances it could not complete the construction and they seek for dismissal of the complaint with costs on the ground that there is no deficiency in service on their behalf .
The complainant filed his affidavit by way of evidence and Exs.A1 to A18 are marked on his behalf. The opposite party also filed affidavit by way of evidence and Exs.B1 and B2 are marked on their behalf. The opposite party also filed written arguments.
The brief fact that falls for consideration is whether there is any deficiency in service on behalf of the opposite party and whether the complainant is entitled for the relief sought for in the complaint. ?
It is the case of the complainant that he entered into an Agreement of Sale dt.16.2.2007 for flat No. 8A, 8th floor, Type-4 in Simla Block having built up area of 1584 sq.ft., common area of 396 sq.ft. and one car parking area with 88 sq. yards of undivided share in the common land in Sy.No.194/P , 196/P, 197/P for a total consideration of Rs.74,49,352/- to be paid in a phased manner from 1.12.2006 to 15.3.2008 which evidences under Ex.A4. On perusal of Ex.A4 shows that the completion of construction should be by 31.8.2008 or 24 months from the date of execution of sale agreement which ever is later. Clause 7 (a) and (f) of the agreement states as follows:
“(a).The Developer and Land Owner assures to complete the construction of the Scheduled Apartment by 31st August, 2008 or 24 months from the date of execution of this Agreement which ever is later as corrected to any time overrum consequent upon actions arising out of recital 6 and subject to the availability of steel or other construction material and any other causes beyond the control of the Developer”
“(b).Where construction of Scheduled Apartment is not yet complete on execution of this Agreement for Sale, it is the responsibility of the Developer to complete construction of the Apartment. It is fully understood by the Purchaser that any construction in Hill County shall be solely arranged by the Developer and the purchaser has agreed to the same.”
The case of the complainant is that he has paid an amount of Rs.63,37,984/- from 18.11.2006 to 4.8.2008 but the opposite party has not completed the structure and have built only upto 6th floor and the Company Law Board appointed a Special Director who conducted meeting on 25.3.2009 at Hill County at which time the complainant made a request to cancel the agreement and to get his money refunded, but there was no response. He even got issued a legal notice dt.28.4.2009 which was served on the opposite party and they gave a reply dt.13.5.2009.
The learned counsel for the opposite party submitted that it is only because of the pending W.P.No.23635/05 in the High Court they could not get permission for 5th to 12th floors and because of force maejure conditions and other unforeseen conditions in the company which necessitated investigation by the Government and statutory authorities, the construction could not be completed and denied the receipt of the termination letter of the complainant.
The contention of the opposite party that it is only because of W.P.No.23635/2005 that they could not get permission for 5th to 12th floors and therefore could not complete the construction is unsustainable. The complainant filed Exs.A16 and A17 which are the copies of orders of A.P.High Court in W.P.No.23635/2005 and 26365/2005 respectively. We observe from the record that W.P.No.23635/05 i.e. Ex.A16 has nothing to do with the opposite party and is a case with respect to Co-operative Societies and W.P.No.26365/2005 (Ex.A17 ) is with respect to fire approvals and precautions to be taken in buildings for which the opposite party is not even a party. Therefore to take umbrage under the pendency of afore mentioned W.Ps is totally unsustainable.
The contention of the opposite party that as per the agreement dt. 16.2.2007 there is an arbitration clause no.14 which has to be adhered to and therefore the Commission has no jurisdiction to entertain the complaint is also unsustainable since the opposite did not raise this question of arbitration by filing an application as per Sec.8(1) of the Arbitration and Conciliation Act to refer it to an arbitrator prior to filing his written version . The opposite party filed an application to refer the complaint on the ground that it is contrary to Sec.8 of the Arbitration and Conciliation Act,1996 which reads as follows:
“8. Power to refer parties to arbitration where there is an arbitration agreement –(1) A judicial authority before which an action is brought in a matter which is the subject of an arbitration agreement shall, if a party so applies not later than when submitting his first statement on the substance of the dispute, refer the parties to arbitration”.
The State Commission observed as follows:
“This kind of petition should be filed only before filing the written version. In this case, the opposite not only filed written version, but also adduced evidence and it has come up for arguments, it thereby, undisputably, forfeited the opportunities available under the provisions of Sec.8(1). This petition is liable to be dismissed as it is filed belatedly and contrary to the provisions of Sec.8(1) of the Arbitration and Conciliation Act,1996. The petition is dismissed.”
This order is final and the opposite party cannot raise this contention now at the this belated stage.
In view of the decision of Apex Court in FAIR AIR ENGINEERS PVT. LTD. AND ANOTHER v. N.K.MODI reported in II (1996) CPJ 13 (SC) wherein the Apex court held that it does not exclude the jurisdiction of this Commission even if there is an arbitration clause in the agreement, we are of the considered view that this Commission has jurisdiction to entertain this complaint.
Ex.A1 is the brochure issued by the opposite party offering houses and flats to the public promising world class construction and it is pertinent to note that nowhere in the brochure they have stated that permission for 5th to 12th floors is still pending. Ex.A2 is the pricing structure given to the complainant by the opposite party and the complainant adhered to all the terms of the payment. Ex.A3 is the letter dt.18.11.2006 addressed by the opposite party to the complainant giving him provisional allotment of unit no.381 in Shimla Block for Apartment no.8A in which they have called the complainant to pay an amount of Rs.7,69,706/- but nowhere they have stated about not having approval for construction of 8th floor. Having allotted vide Ex.A3 provisional allotment of Unit no.381 for apartment 8A in the 8th floor keeping the complainant in dark of any such non approval is an act of deficiency of service. We also observe from the record that the opposite party vide their letter dt.25.2.2009 evidenced under Ex.A5 acknowledged payment of Rs.63,40,984/- made by the complainant to the opposite party. Ex.A7 is the legal notice got issued by the complainant to the opposite party dt. 28.4.2009 and Ex.A8 is the reply dt.13.5.2009 in which they contended that the complainant can terminate this agreement of sale unless the opposite party fails to complete the construction as agreed in Clause 7(a) (b) (c) of the Agreement of Sale which reads as follows:
(a) The Developer and Land Owner assures to complete the construction of the Scheduled Apartment by 31st August , 2008 or 24 months from the date of execution of this Agreement which ever is later, as corrected to any time overrum consequent upon actions arising out of recital 6 and subject to the availability of steel or other construction material and any other causes beyond the control of the Developer.
(b) Provided that the Developer shall have a further grace period of three (3) months.
(c) The Developer shall be entitled to further periods if the construction is delayed due to natural calamities like floods, war, earthquake, fire or stay of construction by any court or authority or any other emergencies including riots and any terrorist activities, which are beyond the normal control of the First Party
It is an admitted fact that the opposite party could not complete the construction and also that the complainant has paid 90% of the amounts. Ex.A13 dt.18.9.2007 which is the offer of discount letter addressed by the opposite party to the complainant in which it is clearly stated as follows:
“We are glad to inform you that this project has now all approvals, more particularly the HUDA approval for all the 13 floors with sub cellars and the fire department approval for the same. We have since forwarded these approval copies to home loan bankers. A copy of the approvals is available at Hill County Site just in case you wish to take a look.”
Opposite party in the written arguments stated that they still have time to complete the construction and relied on Clause 9(b) which is extracted below:
“The purchaser can terminate this Agreement upon the Developer failing construct the property within the period stipulated in this Agreement and the given grace period and the additional 8 months penalty period as provided in clause 7(a), 7(b) and 7(c) . The purchaser shall have no right, at any time whatsoever to obstruct or hinder the progress of the construction activity. The purchaser further agrees that if the Developer gives prior to the expiry of the grace period of eight months, a revised schedule of construction completion or assures that the construction shall be completed by a new contractor of repute or a combination of both , the purchaser shall accept the same provided the Total consideration is not increased”.
The contention of the opposite party that the complainant is not entitled to terminate the agreement unless the opposite party fails to deliver the property as contemplated under Clause 7 and is therefore not entitled for cancellation or for refund of the amount is unsustainable since in the instant case the opposite party has admittedly not even constructed more than six floors and the complainant’s flat no.8(a) is in the 8th floor, their contention that they did not receive letter dt.25.3.2009(A6) request for cancellation and they are not aware of any such request does not hold good in the light of legal notice also got issued by the complainant and replied to by the opposite party . To reiterate Ex.A6 is the letter dt.25.3.2009 addressed by the complainant to the opposite party seeking cancellation of his allotment and to refund his money with interest. Thereafter even in Ex.A7 dt. 28.4.2009 which is the legal notice got issued by him and which was admittedly received by the opposite party and replied to, he seeks cancellation of the agreement and refund of the amount . So denial of the opposite party that no such request for cancellation was made is unsustainable. It is pertinent to note that Clause 9(b) (c)(d) of Ex.A4 Agreement of Sale have given option to the purchasers to cancel the agreement. Clause 9(c) states that termination shall be by a written notice delivered to the opposite party as stated in the agreement. We observe from the record that the complainant has given a written request and also stated in his legal notice that he seeks for cancellation of Agreement of sale and for
refund of the amounts. We are of the considered view that the act of the opposite party in not adhering to the terms of the agreement and taking umbrage under Force maejure events for non completion of construction and refusing to refund the amount of Rs.63,37,984/- paid by 4.8.2008 i.e. 1 ½ years ago when the opposite party has not even raised the building upto the 6th floor and admittedly the complainant’s flat is in the 8th floor, only goes to show that the construction of the complainant’s flat has not even begun and this amounts to deficiency of service. We direct the opposite party to refund the amount of Rs.63,37,984/- to the complainant with interest at 12% p.a. from 4.8.2008 i.e. the date of payment of last instalment together with compensation of Rs.5 lakhs for the mental agony and disappointment suffered by the complainant in taking loan and paying such huge amounts but not fulfilling his vision of Home World Class Construction. Today, the market values of such flats has escalated and we are of the considered view that compensation of 5 lakhs would meet the ends of justice. We also award costs of Rs.5,000/-.
In the result this complaint is allowed in part directing the opposite party to pay Rs.63,37,984/- with interest at 12% p.a. from 4.8.2008 i.e. the date of payment of last instalment by the complainant till the date of realization together with compensation of Rs.5 lakhs and costs of Rs.5000/-
PRESIDENT
MEMBER
Dt. 30.4.2010
APPENDIX OF EVIDENCE
Witnesses examined
For the complainant: For the opp.party :
Affidavit filed in lieu of chief affidavit filed in lieu of
Evidence of P.W.1 on behalf chief examination of RW.1
of the complainant Mr.Teja Pratap Raju, authorized
signatory of opp.party
Exhibits marked on behalf of the complainant :
Ex.A1 : Brochure issued by opposite party
Ex.A2 : Pricing structure for apartments
Ex.A3 : Lr. Dt. 18.11.2006 of opp.party to the complt.
Ex.A4 : Agreement for sale dt.16.2.2007
Ex.A5 : Lr. Dt. 25.2.2009 of opp.party to the complt.
Ex.A6 : Lr dt. 25.3.2009 to the Director of opp.party from complt.
Ex.A7 : Legal notice dt.28.4.2009 issued by complt to the O.P.
Ex.A8 : Reply notice dt.13.5.09 issued by the OP. counsel to
Complainant counsel .
Ex.A9 : Lr dt. 18.9.2007 from O.P. to complt.
ExA10 : Lr.dt.10.1.2009 from opposite party to the complt.
Ex.A11 : Financial Express Report paper c utting
Ex.A12 : G.P.A. issued by the complainant
Ex.A13 : Lr dt.18.9.2007 from opp.party to complainant
Ex.A14 : News letter dt. 22.5.2009 of opp.party
Ex.A15 : News paper cutting dt.8.6.09 pertaining to the O.P.
Ex.A16 : Order in Writ Petition No.23635/05 dt. 3.11.05
Ex.A17 : Order in Writ petition no.26365/05 dt.12.10.2007
Ex.A18 : Lr.dt.3.9.2007 of opposite party to the complainant .
Ex.A19 : Building permission report issued by HMDA
Exhibits marked on behalf of the opposite party:
Ex.B1 : Certificate of Incorporation dt.31.12.2007
Ex.B2 : Copy of resolution dt.10.11.2006passed by Board of Directors of O.P.Company.
PRESIDENT
MEMBER
Dt.30.4.2010
Pm*