IN THE CONSUMER DISPUTES REDRESSAL FORUM, KOTTAYAM
Present:
Hon’ble Mr. Bose Augustine, President
Hon’ble Mr. K.N. Radhakrishnan, Member
Hon’ble Mrs. Renu P. Gopalan, Member
CC No. 302/2013
Friday the 28th day of April, 2017
Complainant : Chirakkadavu Sree Mahadeva
Seva Sangam, Chirakkadavu
Centre, Kottayam District
Reptd. By its Secretary,
N. Somasekharan Pillai,
Mulavelil (Ushus)
Chirakkadavu Center P.O,
Kottayam - 686 519
(Adv. C.N. Rajasekharan Nair)
Vs.
Opposite parties : 1) M/s. Kirloskar Oil Engineers Ltd.,
Laxman Rao Kirloskar Road,
Khadki, Pune – 411 033.
(Adv. Muhammed Nizar)
2) M/s. N.K. Poduval & Co.,
IX/543 Pukadiyil Building,
Sastri Road, Kottayam-686 001.
(Adv. Sheeba Tharakan)
3) Praveen,
Authorised Service Dealer,
Girideepam School Road,
M/s. Vibrant Power Services,
Kalathipady(As per Order on IA-
293/14 3rd OP impleaded)
(Adv. Muhammed Nizar)
O R D E R
Hon’ble Mr. Bose Augustine, President
The case of the complainant filed on 07/11/13 is as follows.
The complainant purchased a diesel Generator manufactured by the 1st opposite party from the 2nd opposite party the dealer for Rs, 2,45,000/-, it was installed and commissioned on 20/08/12 by the technicians of the 1st and 2nd opposite party. The 3rd opposite party is the authorised service centre. According to the complainant within short period the generator showed serious defect ie., sudden stoppage while on running. The mechanics of the opposite parties attended and repaired the generator set on several times. But even after several repairs the problem remained unresolved. The generator set is not functioning from 04/07/13. It was worked only for a period of about 4 months. Then the complainant on 20/06/13 issued a notice to the opposite party 1 & 2 demanding replacement of the generator set. Even after accepting the same they have neither replied nor replaced the generator set. According to the complainant the generator is having 18 months warranty and the defect is within warranty period. And the above said act of opposite parties amounts to deficiency in service and unfair trade practice . Hence this complaint.
1st opposite party filed version contenting that the complaint is not maintainable. According to them the 1st service check was done on 31/08/12 and by that time the generator set was used for 2 hours. The second service check up was done on 16/11/12 after running the same for 28.9 hours. Neither any complaint was reported by the complainant nor any defect was found at the time of checkups. Then on 17/12/12 the complainant raised 1st complaint to the 1st opposite party through the 2nd opposite party and on the same day itself it was attended by the service persons and certain timing irregularities were found, which were rectified. Till 01/04/13 the said generator set was used for total 142 hours. Thereafter on 27/06/13 the same complaint was raised through the 2nd opposite party. During the inspection it was found that the said generator set was used for 179 hours. So the settings were required and the same was done. The load test was also carried out and found correct. As the secretary of the complainant wanted to see and monitor the performance of the generator, after one week the service person again visited the said premises and inspected the generator again on 07/07/13 after its use of total 184.3 hours. And there were no irregularities found in the said generator. The complainant was using the said generator set initially for their temple renovation purpose and hence the running hours were on a higher side. Subsequently they were used the same only as a stand by application to cover up the power interruption. According to the 1st opposite party the generator set was good and properly working as per its standards. Only necessary service for correcting the timing functions of the same was done to it. And there was no manufacturing defect. 1st opposite party prayed for dismissal of the complaint.
2nd opposite party filed version contenting that the complaint is not maintainable. According to the 1st opposite party on 20/08/12 they had supplied 10 KVA diesel generator to the complainant and the complainant install the generator set with the help of their own electrical contractor. After the installation is completed the 2nd opposite party done the supervision of commissioning of the generator. Thereafter the 2nd opposite party send the commissioning report to the 1st opposite party and the communication goes to the authorised service centre of the 1st opposite party, who thereafter is fully responsible for the service of the generator set. The 2nd opposite party is in no way involved directly with the customer for the after sale service of the generator set. In the event of any manufacturing defect or malfunction of the generator set, the authorised service dealer has to give their report to the 1st opposite party and it is the responsibility of the 1st opposite party to replace the set if any manufacturing defect is reported by the authorised service dealer. According to the 2nd opposite party, the authorised service contractor of the 1st opposite party was done proper service in time and the complaints reported by the complainant were attended properly. The generator set had run for 184.3 hours, within short period and there is no manufacturing defect or any other defects. According to the 2nd opposite party there is no deficiency in service or unfair trade practice on the part of them and they also prayed for dismissal of the complaint with cost.
The additional 3rd opposite party filed version contenting that the complaint is not maintainable. According to the 3rd opposite party, on 31/08/12 they had done 1st service checkup, that time the generator set was used for two hours. The second service check up was done on 16/11/12 after running the said generator for 28.9 hours. Neither any complaint was reported nor was any defect found at the time of check ups. Then on 17/12/12 the complainant raised their 1st complaint through the 2nd opposite party and on the same day itself it was attended and done the service for rectifying the timing irregularities. Again on 08/02/13, 13/03/13 and on 01/04/13 the service person of the 3rd opposite party was attended the complaints and corrected the RPM to avoid the sudden stoppage of the said generator. Till 01/04/13 the said generator was used for total 142 hours. Thereafter on 27/06/13 the service person of the additional 3rd opposite party inspected the said generator set. During the inspection it was found that the said generator set was used for 179 hours. So the settings were required and the same was done by the service persons and carried out the load tests. The said generator set was under observation of the said service person after the said service, since the secretary of the complainant wanted to see and monitor the performance of the said generator for one week to his satisfaction, before signing the report. Even though there was no complaints, as requested by the secretary of the complainant it was under observation. So the said service persons again visited the said premises after one week and inspected the generator set again on 04/07/13, after its use of total 184.3 hours and not found any defect. There after Additional 3rd opposite party has not received any complaint directly or through the other opposite parties. The statement of the complainant that the generator set is not functioning from 04/07/17 and that the generator set worked only for a short period of about four months is false. There is no defect to the said generator and so for the complainant has not raised any complaint for the alleged defect. They had done only necessary service for correcting the timing functions, since the said generator was good and properly working as per its standard, there was no occasion to repair it. The 3rd opposite party has not received any notice for the replacement of the generator set. But on receipt of the intimation of this case as instructed by the 1st opposite party the additional 3rd opposite party approached the complainant for verifying the alleged defect to the said generator set on 30/11/13. But the complainant did not allow to inspect the generator stating that this case is pending. The complainant was using the said generator set initially for their temple renovation purpose and hence the running hours were on the higher side. Subsequently they were using only as a stand by application to cover up the power interruption. Since the service persons were not allowed to inspect the generator set on 30/11/13 they did not get any opportunity to check whether there is any settings change in the panel board. It is alleged that the complainant is not using the generator set for last several months. In such a situation there is every chance to loose the charge of the battery or damaged the same. According to the 3rd opposite party there is no deficiency in service or unfair trade practice on the part of them and they also prayed for dismissal of the complaint with cost.
Points for considerations are:
1) Whether there is any deficiency in service or unfair trade practice on the part of opposite parties?
2) Relief and cost.
Evidence in this case consists of the proof affidavits of both sides and the depositions of the PW1, PW2 and DW1. And Ext. A1 to A6 documents, C1 Commission report and Ext. B1 to B8 documents.
Point No. 1
Gist of the complainants case is that the diesel generator set purchased from the 2nd opposite party by the complainant manufactured by the 1st opposite party is having serious manufacturing defects. So complainant seek direction of Fora to replace the same. Opposite parties contented that the generator, when set it run for short period and thereafter, began to show sudden stoppage while running is false. According to the opposite parties on all service check up it is seen that the set was used for long hours. Service details of the defective generator is produced and the same were marked as Ext. B1 to B8. The details of services are as follows.
Services | Date | Run hours | Complaint |
1 | 31/08/12 | 2 | Nil |
2 | 16/11/12 | 28.9 | Nil |
3 | 17/12/12 | 68 | Engine high speed |
4 | 08/02/13 | 120.8 | Engine RPM High speed |
5 | 13/03/13 | 139 | Engine high speed |
6 | 01/04/13 | 142 | -do- |
7 | 27/06/13 | 179 | -do- |
8 | 04/07/13 | 184.3 | Nil |
According to opposite parties the diesel generator set is not defective, only necessary service for correcting time function is to be done to the generator. They further stated that the complainant were using the generator set initially for their temple renovation. So much so the running hours were on higher side. Subsequently the generator is used as stand by application to cover power interruption.
In order to prove manufacturing defect complainant taken a commissioner. Commissioner filed C1 report. Commissioner was examined as Pw1. From Ext. B1 to B8 documents it can be seen that there was some minor defects to the generator and the same were cured by correcting time functioning. Since there is no evidence of any manufacturing defect we cannot direct the opposite party to replace the generator set. PW1, expert Commissioner, opined that present complaint can be rectified by replacing the control panel and also rectify the fault on the diesel guage and load current. So we are of the opinion that, it is genuine and we direct the opposite party to rectify the defects by replacing the control panel and rectify the fault on the diesel guage and load current measuring meter. So point No. 1 is found accordingly.
Point No. 2
In view of finding in point No. 1, complaint is allowed.
In the result:
1) Opposite parties are ordered to repair the complainants diesel generator in proper working condition.
2) Opposite parties are ordered to pay Rs. 3,000/- as the cost of this litigation to the complainant.
The Order shall be complied with within a period of 30 days from the
date of receipt of copy order. If not complied as directed, the award amount will carry 15% interest from the date of Order till realization.
Pronounced in the Open Forum on this the28thday ofApril ,2017.
Hon’ble Mr. Bose Augustine, President
Hon’ble Mr. K.N. Radhakrishnan, Member
Hon’ble Mrs.Renu.P.Gopalan, Member
Documents for the petitioner:
Ext. A1: Letter Dtd: 17/06/12
Ext. A2: Retail Invoice Dt: 30/06/12
Ext. A3:Service/Commissioning report (6 Nos.)
Ext. A4:Copy of Regd. Notice. Dtd: 20/06/13
Ext. A5:Postal Receipt
Ext. A6:Warranty certificate and manual.
Witness from the side of petition:
-
-
Documents for the opposite parties
Ext. B1: Service report Dtd: 31/08/2012
Ext. B2: Service report Dtd: 16/11/12
Ext. B3: Service report Dtd: 17/12/12
Ext. B4: Service report Dtd: 08/02/13
Ext. B5: Service Report Dtd: 13/03/13
Ext. B6: Service report Dtd: 01/04/13
Ext. B7: Service report Dtd: 27/06/13
Ext. B8: Service report Dtd: 04/07/13
Witness from the side of opposite party:
DW1: Praveenkumar V.P
C1: Commission Report
By Order,
Senior Superintendent