Mukesh Kohli filed a consumer case on 09 Dec 2024 against M/s Innovative Housing and Infrastructure (P) Ltd. in the StateCommission Consumer Court. The case no is CC/80/2024 and the judgment uploaded on 11 Dec 2024.
STATE CONSUMER DISPUTES REDRESSAL COMMISSION,
U.T., CHANDIGARH
Consumer Complaint No. | : | 80 of 2024 |
Date of Institution | : | 20.08.2024 |
Date of Decision | : | 09.12.2024 |
Sh. Mukesh Kolhi son of Sh.Uday Singh, aged about 39 years, resident of House No. 1111, Sector 24-B, Chandigarh.
...Complainant.
Versus
1. M/s Innovative Housing and Infrastructure (P) Limited, Corporate Office: SCO No. 198, Opposite Sports Complex, Sector 7, Chandigarh through its Managing Director-Sh. Jagjit Singh.
2. Sh. Jagjit Singh, Managing Director of M/s Innovative Housing and Infrastructure (P) Limited, Corporate Office: SCO No. 198, Opposite Sports Complex, Sector 7, Chandigarh.
….Opposite Parties.
BEFORE: | JUSTICE RAJ SHEKHAR ATTRI, PRESIDENT. MR. RAJESH K. ARYA, MEMBER |
ARGUED BY:
Sh. Devinder Kumar, Advocate for the complainant.
Sh. Harjeet Singh Bedi, Advocate for the opposite parties.
PER RAJESH K. ARYA, MEMBER
Brief facts:-
The complainant, seeking residential accommodation near Chandigarh for personal and family use, was attracted to the "PCL GATEWAY" project, located in Sector 17 & 18, New Chandigarh, District SAS Nagar, Mohali, based on multiple assurances made by the opposite parties through advertisements, marketing, emails and telemarketing. In November 2019, the opposite parties assured the complainant that the project was approved by the Punjab Government, with all requisite permissions and that possession of the plot would be delivered within 6 months from the date of booking. Relying on these assurances, the complainant proceeded to book a plot by paying an initial booking amount of ₹1,00,000/- via cheque dated 30.11.2019. The total sale price of the plot was quoted at ₹29,00,000/-. Following further demands from the opposite parties, the complainant paid an additional sum of ₹5,00,000/- on 11.01.2020. Upon receipt of ₹6,00,000/-, the opposite parties issued a Letter of Allotment dated 06.02.2020, allotting Plot No.1510, measuring 112 sq. yards (100 sq. yards as per site). A Developer-Purchaser Agreement was executed on the same date, which stipulated that possession would be handed over on or before 31.03.2020 with a grace period of 6 months. Subsequently, the opposite parties issued a Demand Letter dated 13.02.2020, requesting the complainant to pay the balance sum of ₹23,00,000/-. The complainant also entered into a Tripartite Agreement with the opposite parties and Housing Development Finance Corporation Limited (HDFC Bank), whereby a loan sum of ₹12,50,000/- was directly paid to the opposite parties by HDFC Bank on 06.03.2020. By March 2020, the complainant had paid a total of ₹18,50,000/-. From that point, the complainant has been making monthly installments of ₹12,091/- to HDFC Bank without default. Despite payment of ₹18,50,000/- by the complainant and the stipulations of the Agreement, the opposite parties failed to deliver possession of the plot by the promised date. The complainant made repeated visits to the office and project site but the opposite parties continually delayed the possession without valid reasons. In May 2021, the opposite parties issued an Offer of Possession letter, directing the complainant to clear any outstanding dues. Following this, the complainant paid an additional sum of ₹10,50,000/-, bringing the total paid to ₹29,00,000/-, the full and final amount as per the basic sale price. However, the complainant did not receive possession and the opposite parties failed to respond to requests for compensation for the delay.
2] Upon attempting to apply for internal building plan approval from GMADA, the complainant discovered that the opposite parties had not obtained the necessary approvals from the relevant authorities. Despite this, the opposite parties issued the possession letter in May 2021 without the required No Objection Certificate (NOC). The complainant requested clarification regarding the validity of the possession letter for obtaining approvals from GMADA and starting construction but received no response. An RTI application filed by the complainant revealed that GMADA had failed to provide the relevant information concerning the "PCL Gateway" project and instead provided details about a different project, "The Address." In June 2024, when the complainant visited the project site, he found that no progress had been made and the project remained incomplete. The complainant documented the situation with photographs, confirming the ongoing delay. He further averred that the terms and conditions of the Developer-Purchaser Agreement are one-sided, placing undue burden on the complainant and primarily benefiting the opposite parties, reflecting an intent to extract financial gain at the expense of the complainant. It has been averred that the opposite parties’ actions have thus been fraudulent and in violation of the terms agreed upon.
3] Thus, by filing this complaint, the complainant has sought directions to the opposite parties to handover physical possession of the Plot No.1510, measuring 112 sq. yds. (100 sq. yds. as per the site) in the project "PCL-Gateway" situated at Sec 17&18, New Chandigarh, Distt: SAS Nagar Mohali alongwith all basic amenities, after obtaining completion certificate from the competent authorities; pay compensation by way of interest @18% p.a. as delayed compensation on the entire amount deposited by the complainant from the due date of possession i.e. 31.03.2020 to till possession is actually delivered as per the clause No.6 of the Agreement; pay compensation to the tune of ₹5,00,000/- for deficiency in rendering service, suffering of pain and mental harassment and also pay ₹75,000/- as litigation charges.
Reply of the opposite parties:-
Observations/findings of this Commission.
9] Furthermore, the opposite parties have cited Covid-19 as force majeure, to this, the complainant in his rejoinder has specifically stated that in the event of any force majeure situations (delays after and institutional delays by concerned authorities), the opposite parties should be put to strict proof qua NOCs/Connections/approvals/licenses issued by the competent local authority and/or judicial or regulatory orders. In this regard, it may be stated here that there is nothing on record to show that opposite parties suffered any force majeure circumstances, on account of which, the construction and development work at the project site could not be completed and possession of plot was not delivered to the complainant by the committed date, referred to above, or even till date. Regardless of external challenges or delays, it remains the responsibility of the opposite parties to ensure that all steps are taken to fulfill their contractual obligations. Delays in approvals, while possibly outside the immediate control of the developer, do not justify the complete failure to deliver possession unless they are clearly linked to an event that qualifies as force majeure under the law. Not only this, in contractual agreements, timelines are typically fixed based on certain expectations and assumptions. While general disruptions like COVID-19 could cause delays, the promoter could not use the pandemic as an excuse unless it directly impacted the ability to meet specific contractual milestones, such as regulatory approvals, construction work or inspections. Further, while the opposite parties claim that delays are due to various institutional delays by concerned authorities, this argument does not absolve them from responsibility for the timely delivery of possession. Delays in possession, irrespective of institutional factors, need to be addressed by the developer or the party responsible for the project’s delivery timeline. The parties involved must account for the fact that customers or buyers entered into an agreement with the developer or builder, not with external authorities. Therefore, it is the developer’s responsibility to ensure timely coordination with these authorities.
10] From the peculiar circumstances of this case, it is proved that the builder-Company made false representations, which were materially incorrect and were made in such a way that the complainant, to whom it was made, was entitled to rely upon it and he may act in reliance on it. The complainant is thereby involved in a disadvantageous contract with builder-Company and suffered financial loss, mental agony and physical harassment. All the facts established that from the very inception, there was intent to induce the complainant to enter into an unfair contract and also intent to deceive him, which act amounts to grave deficiency in providing service, negligence and adoption of unfair trade practice on the part of the builder-Company.
11] On account of delay in actual delivery of possession within the stipulated period, the complainant has suffered mental agony, hardships and financial loss. In the case titled as Lucknow Development Authority v. M K Gupta (1994) 1 SCC 243, the Hon’ble Supreme Court discussed about the extent of the jurisdiction of the Consumer Fora to award just and reasonable compensation for the harassment and agony suffered by a consumer. In Nagesh Maruti Utekar Vs. Sunstone Developers Joint Venture, Consumer Case No. 12 of 2017, decided on 04 May 2022, The Hon’ble National Commission awarded interest @9% p.a. from the committed date of delivery till possession is delivered. Relevant part of the said order is reproduced hereunder:-
“……Consequently, the Opposite Party Developer is directed to pay interest @9% w.e.f. 31.03.2014, i.e., the expected date of delivery of the possession, on the amount deposited by the respective Complainant till 02.09.2017, i.e., the date on which the possession of the Flat was offered by the Opposite Party Developer, within two months from today..…..”
In Shreya Kumar & 11 Ors. Vs. M/s. Ansal Housing & Construction Ltd. & 3 Ors., Consumer Case No. 1021 of 2017, decided on 05 May 2022, the Larger Bench of the Hon’ble National Commission has awarded interest @9% p.a. from the committed date of delivery till possession is delivered. In the present case, the complainant purchased the plot in question, as far as back in November 2019. He is still empty handed and has been forced to approach this Commission for redressal of his grievance. The opposite parties have played fast and loose with the complainant and has caused harassment and mental agony to him, which is unacceptable and this practice needs to be deprecated. In our considered opinion, if we grant interest @9% p.a. to the complainant on the entire amount deposited by him, from the due date of possession onwards till delivery of possession thereof, that will meet the ends of justice.
12] Since fault lies with the opposite parties in not delivering the possession of the plot in question, therefore, they are not entitled to any delayed interest or penalty from the complainant.
13] For the reasons recorded above, the complaint is partly accepted with costs and the opposite parties, jointly and severally, are directed as under:-
14] Certified copies of this order be sent to the parties free of charge.
15] File be consigned to Record Room after completion.
Pronounced.
09.12.2024.
(JUSTICE RAJ SHEKHAR ATTRI)
PRESIDENT
(RAJESH K. ARYA)
MEMBER
Ad
Consumer Court | Cheque Bounce | Civil Cases | Criminal Cases | Matrimonial Disputes
Dedicated team of best lawyers for all your legal queries. Our lawyers can help you for you Consumer Court related cases at very affordable fee.